SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing

Last Update 16 hours ago Total Questions : 82

The SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include C_TS422_2021 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our C_TS422_2021 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these C_TS422_2021 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing practice test comfortably within the allotted time.

Question # 4

For which categories can you define BOMs in SAP S/4HANA?

A.

Work Center

B.

Sales order

C.

Class

D.

Document Structure

Question # 5

Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA?

A.

First in first out (FIFO)

B.

100% check

C.

Simultaneous

D.

By usage probability

Question # 6

What are the possible results of a production planning run in Advanced Planning (PP/DS)?

A.

Planned order

B.

Production order

C.

Purchase requistion

D.

Stock transport order

E.

Scheduling agreement schedule line

Question # 7

Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?

A.

When multiple operations are maintained for one product

B.

When alternate resources are used within one operation

C.

When multiple planned orders exist on one resource

D.

When multiple production versions are maintained for one product

Question # 8

Which mhetods are available for goods issue posting of material components for process orders?

A.

Transfer order

B.

Picking list

C.

Blackflushing

D.

Kanban

Question # 9

You want to use capacity availability checks for production orders. Which settings have to be made for this?

A.

A checking rule must be assigned in the checking control

B.

The PRT Availability Check must be set in the checking control.

C.

An overall profile must be assigned in the checking control.

D.

The Relevant for Finite Scheduling indicator must be set

Question # 10

What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing?

A.

The work center has several invidula capacities.

B.

The finite Scheduling indicator is NOT set in the strategy profile.

C.

The Change Planning Direction indicator is set in strategy profile.

D.

Alternative work centers are fully occupied.