Oracle Project Management Cloud 2024 Implementation Professional

Last Update 19 hours ago Total Questions : 126

The Oracle Project Management Cloud 2024 Implementation Professional content is now fully updated, with all current exam questions added 19 hours ago. Deciding to include 1z0-1057-24 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our 1z0-1057-24 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these 1z0-1057-24 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Oracle Project Management Cloud 2024 Implementation Professional practice test comfortably within the allotted time.

Question # 4

You have a billable project for which the following details are provided:

Associated Inception-To-Date (ITD) Project Actual Cost: USD 60

Associated Project Budgeted Cost: USD 300

Contract Amount: USD 1000

Project Funded Amount: USD 750

Sum of Existing Revenue Events: USD 80

Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

A.

USD 184

B.

USD 120

C.

USD 134

D.

USD 70

Question # 5

As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)

A.

Pool Membership

B.

attributes that the project enterprise resources are assigned after creation

C.

Jobs

D.

Person Type

Question # 6

While creating a new project template, you notice that a default Asset Cost Allocation method is being automatically associated. Identify the source setup from which the default value is being inherited. (Choose the best answer.)

A.

project classification

B.

project type

C.

project unit

D.

project organization

Question # 7

You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify thereasonwhy the project transaction controls are notapplied. (Choose the best answer.)

A.

There is no expenditure type information available on the distribution set line.

B.

There is no expenditure organization information available on the distribution set line.

C.

There is noexpenditure item dateinformation available on the distribution set line.

D.

The account code combination is not available on the distribution set line.

Question # 8

You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)

A.

On Hold > Pending Acceptance > Active

B.

On Hold > Pending Approval > Active

C.

Pending Approval > Pending Acceptance > Active

D.

Pending Acceptance > Pending Approval > Active

Question # 9

Which three are valid password complexity criteria while setting up password policies? (Choose three.)

A.

Complex: At least 8 characters, 1 uppercase, and 1 number

B.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters

C.

Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character

D.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character

E.

Simple: At least 8 characters and 1 number

Question # 10

Green House Corporation has decided to enable the budgetary control feature for their projects. At which two levels will they be able to enter the amounts in the budget versions for these projects?

(Choose two.)

A.

Expenditure Type

B.

Task

C.

Top resource

D.

Expenditure Category

E.

Project