You'll find that our AD0-E903 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these AD0-E903 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Adobe Workfront Project Manager Professional practice test comfortably within the allotted time.

Question # 4

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Question # 5

What are two ways to associate milestone steps to tasks? (Choose two.)

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Question # 6

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

A.

Assigned To

B.

Assignments

C.

Assigned

Question # 7

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

A.

Estimated Date

B.

Projected Date

C.

Planned Date

Question # 8

A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Question # 9

Which date type should an assignee update to change the completion date of a task?

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date

Question # 10

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

A.

Actual Completion Date

B.

Progress Status

C.

Status