You'll find that our CTS-D exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CTS-D sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Technology Specialist – Design practice test comfortably within the allotted time.

Question # 4

Which document defines responsibilities, timelines, and deliverables in an AV project?

A.

Project management plan

B.

User manual

C.

Equipment list

D.

Training schedule

Question # 5

What does “latency” mean in AV system design?

A.

The amount of delay between signal input and output

B.

The strength of an audio signal

C.

The distance a signal can travel without degradation

D.

The volume level of a speaker

Question # 6

Which wireless frequency band is commonly used for AV equipment communication?

A.

2.4 GHz

B.

5 MHz

C.

10 GHz

D.

1 GHz

Question # 7

Which standard specifies the color coding for balanced audio connectors?

A.

AES3

B.

RS-232

C.

XLR pinout standards

D.

HDMI

Question # 8

What does the term “gain before feedback” refer to in audio system design?

A.

The maximum volume before distortion occurs

B.

The maximum amplification before the system produces feedback noise

C.

The increase in amplifier power over time

D.

The difference between input and output signal strength

Question # 9

What is the term for a graphical representation of signal flow between system components?

A.

Block diagram

B.

Wiring diagram

C.

Floor plan

D.

Gantt chart

Question # 10

Which document outlines the detailed responsibilities, schedule, and deliverables in an AV project?

A.

Project management plan

B.

User manual

C.

Equipment datasheet

D.

Installation guide