You'll find that our PDD exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PDD sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any ARE 5.0 Project Development and Documentation Exam practice test comfortably within the allotted time.

Question # 4

In which of the following locations in concrete masonry should a control joint be placed?

A.

At the first course of masonry walls

B.

At each corner of the foundation wall

C.

At changes in wall height

D.

In the center of window openings

Question # 5

Refer to the exhibit.

It is required to cut a hole in the web of the beam shown.

Which of the locations would be best? Check the two that apply.

A.

Location 1

B.

Location 2

C.

Location 3

D.

Location 4

E.

Location 5

Question # 6

In a brick veneer wall, what is the primary purpose of the 2-inch air space between the back of the brick and the sheathing?

A.

To meet the minimum R-value

B.

Allow for differential movement

C.

Provide space for roof drain piping

D.

Minimize mortar bridging

Question # 7

Why is the vertical surface of a dry-stacked stone wall often battered into the retained material?

A.

Increased resistance to soil thrust

B.

Increased resistance to surface erosion of the wall

C.

Increased impermeability that reduces equivalent fluid pressure

D.

Increased cohesion between individual stones that make up the wall

Question # 8

Owners of a busy two-story theater complex want to renovate. The new renovations include increasing the second floor lobby and doubling the number of second floor movie screens. The owner favors the use of escalators. Movies are scheduled to start simultaneously every three hours. The theater currently has a pair of 24-inch-wide parallel escalators, one of which goes up and the other down.

Which of the following should be proposed to accommodate the increased traffic to the second floor?

A.

Increase the existing escalator speeds to 130 fpm

B.

Install a new elevator in the lobby

C.

Install a new escalator that reverses direction

D.

Extend balustrades at escalator landings

Question # 9

In winter conditions, when the outdoor air is below freezing and the indoor humidity is maintained at 40 percent relative humidity for 24 hours a day, ice forms on the exterior surface of the stone facing.

Which of the following elements is missing from the building wall section?

A.

Vapor barrier

B.

Wall insulation

C.

Air space

D.

Rain screen

Question # 10

Where is the proper place to put a vapor barrier in a cold climate?

A.

On the exterior between the metal siding and the sheathing

B.

On the exterior between the framing and the sheathing

C.

On the interior between the gypsum wallboard and the framing

D.

In the cavity of the framing space