Summer Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

Question # 4

An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

A.

Leverage continuous feedback from customers to seamlessly align delivery with requirements.

B.

Define software functionality by relying on the developers' experience designing similar system

C.

Engage end users in user acceptance testing to ensure the product meets their expectations.

D.

Educate end users and other stakeholders to understand desired outcomes through user stories.

Full Access
Question # 5

What should the agile project manager do?

A.

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.

B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.

C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.

D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.

Full Access
Question # 6

During a team meeting, members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks which has lowered motivation.

What should the agile practitioner do?

A.

Organize a team-building activity to improve team morale

B.

Have team members work in pairs to learn from each other and develop new skills

C.

Ask team members to perform a value stream analysis of their activities

D.

Add more resources to the team to help with the tasks

Full Access
Question # 7

What should the Scrum Master do first?

A.

Work with the customers to build the product backlog and identify their initial requirements.

B.

Meet with the stakeholders and enterprise architects to understand the project's vision.

C.

Plan and execute a sprint 0 to establish the project's foundational needs.

D.

Create a backlog, and execute a sprint 1 to quickly deliver value to the customers.

Full Access
Question # 8

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Full Access
Question # 9

What should the team do?

A.

Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Full Access
Question # 10

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Full Access
Question # 11

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Full Access
Question # 12

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Full Access
Question # 13

What should the agile practitioner do?

A.

Review established ground rules with the team

B.

Ask team members specific questions to identify the cause

C.

Encourage the team to continue working to maintain the iteration's schedule

D.

Meet with the product owner and stakeholders to discuss the issue

Full Access
Question # 14

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

Full Access
Question # 15
A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Full Access
Question # 16

A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?

A.

Have the development team follow the product owner's direction

B.

Openly challenge the product owner in an effort to poke holes in their approach

C.

Facilitate a conversation about the user story between the development team and the product owner

D.

Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Full Access
Question # 17

A team developing application software is working in pairs. A project manager notices that important information is sometimes not shared among team members, leading to delays in the development process.

What should the project manager do to improve team performance and eliminate any communication impediments?

A.

For new pairs of developers based on the years of expertise and project management Knowledge

B.

Use task boards so the team can keep track of the work done and future implementation planning.

C.

Schedule in-person meetings at the end of each iteration, allowing team members to share knowledge and experience.

D.

Seek expert judgment and a new collaboration model that will strengthen team cohesiveness.

Full Access
Question # 18

An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.

What should the scrum master do first?

A.

Build a product roadmapthat shows the features and releases.B Request an existing cross-functional team be dedicated to the project

B.

Obtain specific product requirements from a customer focus group.

C.

Develop a project budget based on the project charter.

Full Access
Question # 19

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the Scrum Master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the Scrum Master respond to this request?

A.

Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.

B.

Create and update bi-weekly project status reports for the stakeholder who requested the report.

C.

Escalate this to the stakeholder's supervisor because this is an unreasonable request.

D.

Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.

Full Access
Question # 20

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

Full Access
Question # 21

What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

A.

Invite people from across the organization to attend daily stand-ups

B.

Invite people from across the organization to attend retrospectives

C.

Invite people from across the organization to attend the release meeting and project retrospectives

D.

Regularly meet with people across the organization to share the project's lessons learned and best practices

Full Access
Question # 22

What should the project leader do?

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Full Access
Question # 23

In companies where decision-making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?

A.

A formalized agile approach offers controlled flexibility in dealing with unknown variables in a manner that adds business value.

B.

Agile is focused only on digital transformation project management, whereas a predictive approach focuses on traditional "brick and mortar" projects.

C.

The agile formal change management system is better able to deal with unknown variables.

D.

Agile is relatively new; therefore, it is inherently more aligned with data-analytic-based efforts.

Full Access
Question # 24
A.

Document the problem, escalate to the project manager, and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

Full Access
Question # 25

An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?

A.

Report this as a blocker and ask senior management to provide the right subject matter experts (SMEs) until all the outstanding issues can be dosed.

B.

Identify the key business stakeholders and invite them to day-long sessions until all the dependencies and outstanding issues can be closed.

C.

Identify the key dependencies that need to be resolved in order of priority level so the user stories can meet the definition of ready (DoR) criteria.

D.

Report this as a blocker and ensure the product owner is able to deprioritize the issues so the user stories can meet the definition of ready (DoR) criteria.

Full Access
Question # 26

When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?

A.

Calculated planned percent complete (PPC)

B.

Many small minimally marketable features (MMFs)

C.

Story points rather than cost estimates

D.

Calculated earned value (EV)

Full Access
Question # 27

Two team members are working together to deliver an asset management tool. The code delivered by team member A during this sprint is not aligning with the specifications written by team member B. Both team members do not seem to agree on the look and feel of some functionality.

What should the Scrum Master do in this situation?

A.

Understand the root cause of this issue and recommend discussing their differences to find common ground.

B.

Hold a team meeting to discuss these issues and help direct the whole team on how to proceed further.

C.

Let the two team members resolve the conflict on their own.

D.

Ask their functional manager to intervene and resolve the issue.

Full Access
Question # 28

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team's productivity.

How should the team leader exhibit servant leadership?

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments

Full Access
Question # 29

What should the agile practitioner have done to ensure stakeholder satisfaction?

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Full Access
Question # 30

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?

A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.

B.

Request the team work overtime to get the work done on time and within the allocated budget.

C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.

D.

Review the contract documentation with the customer to clarify the specific agreed-upon budget amount.

Full Access
Question # 31

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Full Access
Question # 32

Several team members are new to agile and there is a lot of confusion. It seems everyone is coming in with different experiences and following their own agendas. The scrum master decided to hold a presentation on core agile principles and values.

What should the scrum master emphasize to the team during the presentation?

A.

The value of agile ceremonies and methods

B.

Performance and chain of command

C.

Product deliverables, procedures and features

D.

Collaboration, value delivery and shared mindset

Full Access
Question # 33

What should the team do?

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Full Access
Question # 34

During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.

How should the project manager explain this to the customer and save time in the meeting?

A.

Team performance and velocity can be determined only after the project has started

B.

Point out the Walking Skeleton and highlight the basic features that provide value.

C.

Create a kanban board for visualizing the work in process (WIP) and future development.

D.

High-level release planning is part of iteration 0 and works as a proof of concept

Full Access
Question # 35

What should the Scrum Master do?

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

Full Access
Question # 36

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Full Access
Question # 37

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

A.

To better listen, serve, and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Full Access
Question # 38

The product owner is very concerned about work not being completed and tested before a hard release date.

What can the agile team do to mitigate this risk?

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Full Access
Question # 39

A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.

What should the agile lead do?

A.

Explain that the testable acceptance criteria are included in each story and it is necessary for the expert to collaborate with the developers, testers, and product owner for common understanding of the solution.

B.

Agree, and ask the developers to explain to the testers how the solution should perform for quality assurance. The testers will demonstrate to the stakeholders how the system should perform to gain acceptance.

C.

Agree, because the developers can copy and paste the requirements and include the technical specifications and performance criteria while writing the stories to save time.

D.

Explain to the project sponsor that the user stories should be assigned to the analysts, because they helped write the requirements and better understand them.

Full Access
Question # 40

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Full Access
Question # 41

A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.

How should the project manager handle a review with the team member?

A.

Talk to the team member about project deliverables and how poor performance is unacceptable.

B.

Discuss performance with the team member on the project deliverables and provide constructive feedback.C Inform the learn member that this project is complex and consider moving them to another project

C.

Extend support to the team member as this is the first project in which the team member underperformed.

Full Access
Question # 42

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.

What should the Scrum Master do?

A.

Ask the lead developer to identify a solution, and then share the details with the team

B.

Ask a technical manager or architect to determine a solution to the problem

C.

Work with the product owner to add a spike to the next sprint to identify a solution

D.

Create a collaborative team environment so that the team can explore a solution together

Full Access
Question # 43

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?

A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.

B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

Full Access
Question # 44

How can this issue be resolved?

A.

Break down the feature into smaller parts, and commit to completing the minimum viable product.

B.

Complete the iteration to which they have already committed, and include the feature in the next release.

C.

Change the planned features to include only the vitally important one.

D.

Extend the iteration to complete the feature.

Full Access
Question # 45

An agile practitioner is in the process of refining requirements. The requirements keep changing based on with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

A.

Ask the Scrum Master to help reduce the rate of change.

B.

Work with the Agile Coach to document the requirements in a collaborative way.

C.

Work with the stakeholder directly rather than go through different layers of people.

D.

Work with the development team to confirm the requirements.

Full Access
Question # 46

A new Agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The Scrum Master and the team are currently defining their working agreement.

What should be part of the working agreement for a dispersed team?

A.

Identify support needed from external vendors to assist dispersed team members.

B.

Meet face to face at regular intervals to enhance shared understanding.

C.

Designate one person to communicate with all team members working at different locations.

D.

Define what project work can be done by dispersed team members.

Full Access
Question # 47

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

Full Access
Question # 48

An executive sponsor of a new Scrum team actively attends Scrum ceremonies.

How does this benefit the team?

A.

It helps the team to focus on and meet sprint goals.

B.

It reminds the team about who sponsors the project.

C.

It provides high-level project updates to the sponsor.

D.

It helps to quickly resolve issues using the sponsor's influence.

Full Access
Question # 49

To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?

A.

A list of templates to be used to create the project vision

B.

A list of project stakeholders and user stories

C.

A checklist for future acceptance tests for project deliverables

D.

A list of questions for the team and customer representative

Full Access
Question # 50

A food company seeks additional business-to-business (B2B) revenues from some customers by

implementing purchase order (PO) functionality. To achieve this, the agile project team is exploring PO integration options (see item #3 in Exhibit A), as the product increment (PI) planning process is underway.

What should the project team do next?

A.

Use agile estimation techniques like planning poker or relative sizing for collaborative assessment.

B.

Break down the feature into smaller tasks or user stories for better assessment and incremental delivery.

C.

Analyze current system requirements and dependencies, including integration levels and regulatory compliance.

D.

Refer to past performance and historical data from similar projects to identity potential risks and challenges.

Full Access
Question # 51

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: "I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles."

What is the agile lead attempting to highlight?

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

Full Access
Question # 52

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Full Access
Question # 53

What should the team do next?

A.

Use agile estimation techniques to create a shared understanding of when the user stories will be completed.

B.

Agree upon development and testing activities for the user stories.

C.

Complete the user stories, and provide a demo for the product owner and customer.

D.

Complete the user stories, and hold a retrospective to discuss them.

Full Access
Question # 54

A project's Product Owner asks the Scrum Master to facilitate the estimation activity. The Scrum Master then meets with the team and the Product Owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Full Access
Question # 55

What should the agile coach do in this situation?

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after all spikes are executed

Full Access
Question # 56
A.

Coach team members to improve functional specialties and increase overall velocity.

B.

Identify where team processes misalign with accepted Scrum practices.

C.

Facilitate the identification of problems or issues and help the team resolve them.

D.

Review the backlog to ensure that it is prioritized, refined, and properly tasked.

Full Access
Question # 57

During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.

What should the product owner do to help the team?

A.

Work with the client to ensure that the requirements are clear enough to allow a correct estimation and refine the backlog if needed.

B.

Assist the team with schedule planning to mitigate risks, including the possibility of crashing if needed.

C.

Implement clear measurements to control any deviation and therefore ensure the project's success per client requirements

D.

Recommend that the team skip requirements that are too complex and estimate them later through progressive elaboration.

Full Access
Question # 58

Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?

A.

Ask the agile practitioner to help write the user stories.

B.

Ask the agile team to facilitate a story-writing workshop.

C.

Ask subject matter experts (SMEs) to help write the user stories.

D.

Ask the agile practitioner to facilitate a story-writing workshop.

Full Access
Question # 59

Which option describes how risk should be managed in an agile project?

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stories they have been assigned.

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.

Full Access
Question # 60

A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"

How should the agile lead respond?

A.

Total time and average process time

B.

Critical path and queue lengths

C.

Delays and bottlenecks in the process

D.

End date/time and start date/time

Full Access
Question # 61

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities.

How should the stakeholders ensure their objectives are met by product delivery?

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

Full Access
Question # 62

A business analyst has been assigned to optimize a process to deliver healthcare services to patients in a clinic. In creating a value stream map, what will the business analyst’s key observations include?

A.

Process breakdowns and workflow

B.

Wait times and cycle times

C.

Process maps and story points

D.

Activity sequences and earned value (EV)

Full Access
Question # 63

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?

A.

Estimate and define the work items.

B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.

C.

Add features to the product backlog.

D.

Determine if the demand is or is not feasible.

Full Access
Question # 64

What should be done with this story?

A.

Mark it as incomplete and prioritize it for the next sprint

B.

Mark it as complete, since the product owner has the final say

C.

Discard it and create a new story for the remaining scope of work

D.

Mark it as complete, since the team completed the scope of work

Full Access
Question # 65

An organization is shifting to an agile delivery methodology. An agile project manager has been assigned to the transformation project.

What should the agile project manager do to ensure a high level of adoption?

A.

Focus on not just the "what," but also the "how" of delivering projects.

B.

Ensure that there is buy-in from senior management to adopt agile.

C.

Identify strong product owners to ensure project teams are delivering value.

D.

Train the team on the fundamentals of the agile mindset and principles.

Full Access
Question # 66

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

A.

Allow stakeholders to discuss without the scrum master's intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Full Access
Question # 67

What should the team do to improve the accuracy of their estimates?

A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

B.

Discuss estimating techniques in the daily scrum meeting

C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

D.

Begin tracking estimated effort metrics as an input to performance evaluation

Full Access
Question # 68

A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?

A.

Resolve the disagreement for the team as a servant leader.

B.

Encourage the team to continue trying to resolve their disagreements.

C.

Advise the team on the correct course of action to avoid disagreements.

D.

Remove the team members that are in disagreement to ensure unity in the team.

Full Access
Question # 69
A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Full Access
Question # 70

What should the product owner do to resolve this?

A.

Ask the development team to address the issue since it is in their domain.

B.

Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.

C.

Meet with the team and stakeholders to address rework and rewrite stories as needed.

D.

Cancel the current sprint, and meet with stakeholders to reassess the project's validity.

Full Access
Question # 71

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Full Access
Question # 72

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace.

What analysis should the team use to understand the issues?

A.

Risk management

B.

Variance and trend

C.

Kano model

D.

Fishbone diagram

Full Access
Question # 73

How could the project leader have avoided this?

A.

Led by example by encouraging the team to engage in consensus-driven decision making

B.

Iterated the need for agile teams to make quick decisions, then followed up with that team member

C.

Empowered a team member to facilitate decision making then made a final decision on behalf of the team

D.

Refrained from participating in the team's decision-making process, except to document and communicate results

Full Access
Question # 74

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)

A.

Implement a dynamic feedback platform leveraging collaboration tools, accommodating diverse schedules and enabling stakeholders to provide feedback asynchronously.

B.

Establish a rotating stakeholder committee composed of representatives from different regions and departments, ensuring diverse perspectives are considered in decision-making processes.

C.

Enforce a strict policy requiring stakeholders to attend weekly synchronous feedback sessions, leveraging technology to accommodate various time zones and scheduling conflicts.

D.

Appoint regional liaison officers responsible for coordinating stakeholder interactions within their respective time zones, facilitating regular communication and feedback exchange.

Full Access
Question # 75

A team member does not understand what the project risks are or the impact that they could have.

How should an Agile leader communicate risks in a way that the team will understand?

A.

Create a RAG chart (Responsible, Accountable, Consulted, Informed) that identifies who is accountable for each risk.

B.

Create a Gantt chart that includes slack to accommodate for unknowns.

C.

Create a communications management plan that details who is responsible for communicating risks.

D.

Create a risk burndown chart showing the reduction of risks over time.

Full Access
Question # 76

What should the Scrum Master advise the team to do?

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story's technical approach.

C.

Transfer the story to a Scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story's priority and wait until more technical details are available.

Full Access
Question # 77

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starting the project.

Full Access
Question # 78

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Full Access
Question # 79

A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?

A.

To produce a fast return on investment

B.

To reduce risk as quickly as possible

C.

To gain competitive advantage as soon as possible

D.

To maintain visibility with project stakeholders

Full Access
Question # 80

What should the product owner do?

A.

Accept responsibility for the product's delay.

B.

Ensure that the project sponsor's priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

Full Access
Question # 81

A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.

What should the scrum master do?

A.

Review the release plan with the product owner and invite the stakeholders to a series of release reviews.

B.

Review the metrics and the process to determine where the overhead could be further reduced to speed up delivery.

C.

Explain to the product owner why the sprint reviews are now replaced by release reviews as inspect and adapt is a key principle in Scrum.

D.

Explain to the product owner that getting feedback early and often from stakeholders is important so necessary changes can be made quickly.

Full Access
Question # 82

After completing the release plan, the team realizes that the project is very likely to have a negative ROI.

What should the team do?

A.

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI

B.

Replace some team members to reduce the release costs and minimize a negative ROI

C.

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI

D.

Communicate the risk of a negative ROI to the stakeholders, and update the release plan

Full Access
Question # 83

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Full Access
Question # 84

A user interface (UI) developer has features for channels ready for review. During the team review, the architect is disappointed that Splunk software has not been implemented for better server and client logs. The architect insists on the implementation of Splunk software, which will impact the release date.

Which one of the following is the ideal option for the team to resolve this conflict?

A.

Have the team brainstorm and propose error logging at the client level, which will have a higher impact with less effort within the release timeline.

B.

The product owner should explain to the architect that monitoring, alerting, and logging are not essential for the customer and can be prioritized post-release.

C.

Inform the sponsor that features are being added and will extend the release date after getting approval and communicating this to the architect.

D.

Ask the developer to build and let the testing be postponed until after the release, and inform the architect that the feature will be implemented.

Full Access
Question # 85

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?

A.

Escalated the issue to management

B.

Ensured the early engagement of key stakeholders

C.

Provided feedback to the architecture team to change the enterprise architecture standards

D.

Raised an exception for non-adherence to the enterprise architecture standards for this product

Full Access
Question # 86

A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

A.

Send the member to training

B.

Ask the outside specialists if database administration is required from the team

C.

Send one member to training only after asking the team if there is an issue with the current workflow

D.

Wait until all members of the team can attend training

Full Access
Question # 87

What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?

A.

Team capacity and competence profiles

B.

A list of tools used for implementation

C.

A list of open technical issues

D.

Up-to-date project radiators

Full Access
Question # 88

A software project is being implemented by a small, colocated team. What should the project manager do to keep the team focused and engaged with the high level of requirements?

A.

Arrange afternoon touchpoints where the team can discuss what they have done during the day

B.

Request that the project sponsor is present during daily standups to increase commitment from the team.

C.

Send out daily activity tasks to each member of the team, mitigating the risk of tasks being forgotten.

D.

Make use of a kanban board so that the team will have a clear view of the work in progress (WIP) for the release.

Full Access
Question # 89
A.

The increase in velocity and cost

B.

A buffer in the sprint to mitigate unexpected risks

C.

Assigning extra points to each task to allow time for changes

D.

Stories describing infrastructure tasks and analysis tasks

Full Access
Question # 90

A Product Owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog.

What should the Product Owner do next?

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Full Access
Question # 91

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Full Access
Question # 92

During an executive review, a scrum master uses a burndown chart to demonstrate team deliverables through time. The scrum master declared that velocity increased from 27 to 35 over the last 3 sprints, but one of the executives asks to clarify the importance of these metrics.

How should the scrum master respond?

A.

Project velocity should be stable overtime.

B.

Moving velocity from 27 to 35 is a decrease in productivity.

C.

A burndown chart compares planned versus actual, not velocity.

D.

Velocity is iterative and will only be used for sprint numbers.

Full Access
Question # 93

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen.

What should an agile practitioner do?

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Full Access
Question # 94

Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date.

What should the agile practitioner do?

A.

Deal with the issues in a retrospective if they ever come up again.

B.

Create a task board to track issues when they appear.

C.

Identify and monitor issues through a risk burndown chart.

D.

Create an issue log as an information radiator and monitor.

Full Access
Question # 95
A.

Add new security features to the backlog and prioritize.

B.

Execute a spike to research security features for the project.

C.

Ask questions to determine where and how the product owner wants to use the product.

D.

Ask questions to determine if the product owner can define the desired level of security.

Full Access
Question # 96

The project manager has requested that the customer participate in the requirements gathering session for the next release. A conflict comes up regarding the requirements between the customer and team.

What should the project manager do?

A.

Based on value to the organization, the project manager should decide what can be included or not in the final requirements.

B.

The customer is the end user of the product and should have the authority to decide about the product requirements.

C.

The project manager should discuss the requirements with the customer alone so that the team can deliver the prioritized requirements.

D.

Encourage self-organization by communicating the importance of a collaborative approach in decision making about the requirements.

Full Access
Question # 97

How should the agile practitioner address this?

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the Kanban board and assign it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Full Access
Question # 98

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Full Access
Question # 99

Which agile practice would most significantly increase a team's velocity?

A.

Daily standups

B.

Iteration and release planning

C.

Training in areas of weakness

D.

Iteration

Full Access
Question # 100

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.

What should the agile practitioner do?

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team's estimated velocity.

Full Access
Question # 101

The vice president (VP) of an organization has been asked by the chief information officer (CIO) to have their teams to embrace an agile approach to projects. The VP, however, often insists teams use a more predictive approach to project management which allows the project managers to do what they like.

How should an agile team member coach the VP and teams be more effective?

A.

Coach the chief information officer (CIO) on implementation of agile benefits and expectations.

B.

Coach the teams on implementation of agile benefits and expectations.

C.

Coach the managers on implementation of agile benefits and expectations.

D.

ICoach the vice president (VP) on implementation of agile benefits and expectations.

Full Access
Question # 102

While reviewing the sprint burndown during a stand-up, the Scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.

What should the Scrum team do?

A.

For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories

B.

Have QA team members with the appropriate skill sets spend extra time to help the team succeed

C.

Ensure that QA team members who lack the appropriate skill sets sign up for training within the next few weeks

D.

Ask QA team members experienced with the new automation framework to cross-train the other QA members

Full Access
Question # 103

A development team has started working on a new service but is unsure if the service fits the customer's requirements. What should the product owner do to ensure that the service will benefit the customer?

A.

Release the minimum viable product (MVP) to a group of customers and end users for their feedback.

B.

Build a prototype and review it with the targeted customer segment for their feedback.

C.

Invite a group of customers and end users to the biweekly demos to obtain feedback.

D.

Release the prototype of the software for 6 months to a pilot group of customers for feedback.

Full Access
Question # 104

What should the agile team do next?

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Full Access
Question # 105

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

A.

Address this impediment by obtaining suitable training for the team.

B.

Address the risks resulting from complexity within sprint zero.

C.

Facilitate team brainstorming of the risks resulting from complexity for the risk register.

D.

Motivate the team to try new technical approaches.

Full Access
Question # 106
A.

Parametric

B.

One-to-one comparison

C.

Affinity

D.

Planning poker

Full Access
Question # 107

An agile team is working on the first sprint, and has already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

A.

Communicate the importance of the business need to the team and refine the product backlog.

B.

Ask the team to discuss the changes to the features with the customer.

C.

Meet with the agile team lead to prioritize the requirements.

D.

Discuss and prioritize the requirements with the team.

Full Access
Question # 108

A seven-member agile team's composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?

A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Full Access
Question # 109

What should the agile coach do to develop members into a high-performance team?

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Full Access
Question # 110

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team's capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team's capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Full Access
Question # 111

An agile team is optimizing the workflow by investing in initiatives to identify and reduce unnecessary handovers and delays. What should the team do in this situation?

A.

Create a value stream map.

B.

Draw a risk burndown chart.

C.

Use a kanban board.

D.

Make a cumulative flow diagram.

Full Access
Question # 112

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Full Access
Question # 113

A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project

deliverables could not be completed on time.

How should the project team improve during their retrospective for future implementations?

A.

Use the scrum or team board and daily scrum meetings to track and manage issues and optimize deliverables.

B.

Encourage team members to become general specialists to reduce bottlenecks and create a cross-functional team.

C.

Empower teams and encourage emerging leadership to produce effective solutions to manage complexity.

D.

Define the roles of the individual or group and define the what, how, why, when, and where to do each task.

Full Access
Question # 114

During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?

A.

The Kanban approach relies on storyboards.

B.

The Kanban approach focuses on adaptive, simultaneous workflows.

C.

There are no work-in-process limits in the Kanban approach.

D.

Kanban teams employ a pull system.

Full Access
Question # 115

What should the agile practitioner do?

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Full Access
Question # 116

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team.

What is the agile project leader doing?

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement

Full Access
Question # 117

A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.

What should the project lead do to help the team?

A.

Coordinate a collaboration session so all the team members are involved in the solution process.

B.

Plan a minimum viable product (MVP) in collaboration with the product owner to reduce technical complexity and move issues to the next release.

C.

Provide training for all team members to enable higher technical skills and the ability to resolve complex issues.

D.

Hire external consultants to advise on solution options and train team members in any technical gaps.

Full Access
Question # 118

A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the Scrum Master do to accomplish this?

A.

Ask the team members' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the Scrum Master.

Full Access
Question # 119

What action should the product owner take?

A.

Invite the executive to the standup.

B.

Direct the executive to the information radiator.

C.

Personally meet with the executive.

D.

Email the requested information to the executive.

Full Access
Question # 120

Conversation transcript between the customer and the product owner (PO):

Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that.

PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar?

Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app?

PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own?

Customer: I own an Android phone, but I also need integration with the Apple phones.

Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)

A.

Monthly calendar view

B.

Android phone integration

C.

Windows end of support deadlines

D.

Vacation calendar for team members

E.

Scheduler to add events

F.

Product increment release dates

Full Access
Question # 121

During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

A.

Inform the product owner's manager so that corrective action may be taken.

B.

Communicate this to the product owner, and offer to help facilitate discussions with the team.

C.

Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.

D.

Escalate this issue to the sponsor so that corrective action may be taken.

Full Access
Question # 122

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Full Access
Question # 123

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?

A.

Self-organize

B.

Assign tasks to each team member

C.

Meet with the customer

D.

Identify the Scrum Master

Full Access
Question # 124

What should the agile team do?

A.

Demand frequent product reviews by the product owner

B.

Continuously work with the product owner to do backlog refinement and product reviews

C.

Have the product owner provide detailed requirement specifications to ensure the proper features are delivered

D.

During the planning session, ensure the team is committed to deliver within the specifications

Full Access
Question # 125

In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.

How should the agile lead implement an effective and efficient solution?

A.

Review the quality assurance and control processes with the team to ensure that even new team members understand the service level agreement (SLA) made with the customer.

B.

Suggest the team commit to a 2-month trial using Kanban. Focus on delivering value to the customer using pull criteria before advancing work. The team will have planning meetings as needed with no special meetings about the process.

C.

Hire a consultant team to perform a root cause analysis, which will determine the fundamental issues from both perspectives, then meet with the team to determine the best method to get the project back on track.

D.

Work with the team to create a spike story for the next iteration to investigate the issue. Create a plan to get the project back on track and present it at the next status meeting to gain stakeholder acceptance.

Full Access
Question # 126

What should the agile team do?

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority

D.

Discuss the performance of the solution at the next sprint review

Full Access
Question # 127

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Full Access
Question # 128

How should this be handled?

A.

The story should be assigned eight story points as per the majority vote

B.

The story should be added to the backlog and reassessed later

C.

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.

The decision for the number of story points should be made by the customer

Full Access
Question # 129

During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.

What should the Scrum Master do?

A.

Discourage the team member from deviating from the plan and document the request during the retrospective

B.

Encourage the team member to research the issue and present the findings during the retrospective

C.

Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases

D.

Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important

Full Access
Question # 130

Answer Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Full Access
Question # 131

What should the agile team do?

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Full Access
Question # 132

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.

What should the agile coach do?

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

Full Access
Question # 133

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

Full Access
Question # 134

A diverse team can sometimes create misunderstandings and conflict, leading team members to isolate. How can an agile project manager promote effective communication and collaboration among team members with diverse backgrounds and perspectives?

A.

Reduce emotions by emphasizing areas of agreement rather than areas of difference.

B.

Create a shared vision for the team and use techniques to increase empathy and positive interaction.

C.

Coach the team to focus on areas of agreement and the company's profitability.

D.

Confront the team and follow the formal procedures as described in the project management plan.

Full Access
Question # 135
A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Full Access
Question # 136

DRAG DROP

All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)

Full Access
Question # 137

During product development, changes in technology and regulations require the team to reassess product architecture.

How should this technical debt be captured?

A.

Include it in the product backlog and use a new indicator to annotate that it is technical debt

B.

Include it in the product backlog as a low-priority issue

C.

Since it is not a part of Agile methodologies, it should not be tracked

D.

Have team members maintain personal lists of issues and consolidate the lists during review

Full Access
Question # 138

How should the agile team lead respond?

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.

Work with the team to create a vision from the stakeholder's supplied requirements.

D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Full Access
Question # 139

What should the agile project manager have done to avoid this?

A.

Invited end customers to attend the stand-ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Full Access
Question # 140

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Full Access
Question # 141

Iterations last between a couple of weeks to a couple of months, with a preference for the shorter time. What is the goal for each iteration?

A.

Complete the assigned tasks.

B.

Deliver working software frequently.

C.

Demonstrate the software to the customer.

D.

Provide a high-level timeline.

Full Access
Question # 142

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Full Access
Question # 143

A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?

A.

The purpose of the daily coordination meeting is for the scrum master to be able to follow up on the sprint plan. The team should explain what may be impeding them from reaching the sprint goal.

B.

According to the Scrum guide, the daily coordination meeting is part of the Scrum framework. The purposes of this meeting are to enable the scrum master to verify the team is on track and to escalate impediments.

C.

The daily coordination meeting is an effective way for the development team to follow up on progress toward the sprint goal and discuss anything that may hinder their work. It is a way to actively manage risks and dependencies.

D.

The daily coordination meeting is held to verify that people are working on the right things. The whole Scrum team should be able to answer these questions: What did I do yesterday, what will I do today, and what can stop me from making progress?

Full Access
Question # 144

Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item.

What should the agile project manager do?

A.

Use an information radiator to help increase the transparency of work for key stakeholders.

B.

Send status updates whenever the stakeholders request them.

C.

Hold Scrum meetings more frequently to ensure stakeholders are well informed.

D.

Instruct the team to focus on their own assignments rather than the work of others.

Full Access