Question # 4

A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates

that would include both predictive and agile approaches,

What should the project manager do after the documents are completed?

A.

Hire an external consultant to monitor the execution of the new procedures.

B.

Upload the files to the corporate website to be available for internal use.

C.

Meet with the department managers to help them roll out the new procedures.

D.

Develop a training plan for all of the stakeholders to learn about the updates.

Full Access
Question # 5

A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the keystakeholders.

What should the project manager do first?

A.

Agree on quality standards with the key stakeholders.

B.

Engage experienced key stakeholders in the implementation of the project.

C.

Develop a requirements traceability matrix.

D.

Review the test and inspection plan with the key stakeholders.

Full Access
Question # 6

A project manager is working with the product owner and customer stakeholders on prioritizing the product backlog and planning the product delivery dates. The customer stakeholders are asking to include several deliverables as high priority. The product manager also has technical tasks that should be added as high priority.

What should the project manager do?

A.

Allow the customer stakeholders to define the project priorities and set the delivery dates.

B.

Work with the team to estimate tasks and delivery dates, and then create a project roadmap.

C.

Lead the team to identify the product objectives at every delivery iteration and clarify priorities.

D.

Create a sprint board to allow all customer stakeholders to be aware of the task status and impediments.

Full Access
Question # 7

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. Theproject manager has to meet animportant milestone in a week.

What should the project manager do next?

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Full Access
Question # 8

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allowfor more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, butalso wants to accommodate newinformation and changes as the project progresses.

Which project management approach should the project manager select for this project?

A.

Hybrid

B.

Agile

C.

Phased

D.

Incremental

Full Access
Question # 9

A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides withthe company's financial budget planning period.

Which two actions should the project manager take next to address this concern? (Choose two)

A.

Facilitate a risk workshop with all stakeholders in attendance to identify and assess all risks to the project.

B.

Change the project implementation date so that the concern is alleviated and no longer applicable.

C.

Communicate to the project sponsor that the implementation date is low risk and will not impact the project.

D.

Advise the sponsor that it is not feasible to determine if the end date will be met as the project is in the initiation phase.

E.

Log the concern as a risk in the project risk register and assess the impact and severity of the risk.

Full Access
Question # 10

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent

to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

A.

Seek an external expert to review the framework.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Foster knowledge sharing and coaching among team members.

Full Access
Question # 11

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not

have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

A.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

B.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place.

D.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

Full Access
Question # 12

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?

A.

Compare the cost of improving quality against the cost of failure and adjust the budget.

B.

Help the team create the definition of done (DoD) to improve delivery quality. 0 2 Add testing items to the backlog to assess quality periodically. oO

C.

Expand the team in order to improve the quality of the project.

Full Access
Question # 13

A product owner is trying to understand how many of the user stories have been completed within a 2-week sprint. How should the project manager approach this situation?

A.

Invite the product owner to regular standup meetings.

B.

Use retrospectives to deliver the finished products.

C.

Have a face-to-face conversation with the product owner.

D.

Share the burndown chart with the product owner.

Full Access
Question # 14

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignmentsfrom multiple people and states they are not able to work effectively.

What should the project manager establish first in the project governance structure?

A.

Risk management and issues resolution plan

B.

Resource management and conflict resolution plan

C.

Clear responsible, accountable, consult, and inform (RACI) matrix

D.

Clear project work breakdown structure (WBS) and timeline

Full Access
Question # 15

project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

A.

The deliverables that are performing well and those that need more work.

B.

Specialized reports created specifically for the meeting as per directions from the project sponsor.

C.

Potential changes to the project's strategy and the feedback from senior executives.

D.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.

Full Access
Question # 16

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining. What will

help the project manager understand why this has occurred?

A.

Project audit

B.

Procurement audit

C.

Lessons learned

D.

Organizational process assets (OPAs)

Full Access
Question # 17

A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the

organization and have varying levels of interest.

Which approach should the project manager use with the stakeholders?

A.

Schedule one-on-one meetings with stakeholders to provide project updates.

B.

Provide daily reports to maximize stakeholder communication.

C.

Share all relevant project information with the stakeholders.

D.

Minimize communication until project completion as it will be finished quickly.

Full Access
Question # 18

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the differentrequirements?

A.

Include only the key requirements and keep the stakeholders informed about scope decisions.

B.

Add only the opinions of the team, because they know the objectives of the project.

C.

Include only the common requirements of each stakeholder group in the project goals.

D.

Analyze the interests and influence of stakeholders and evaluate their requirements.

Full Access
Question # 19

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

A.

Clarify the relevance of reviewing the documentation on the intranet.

B.

Create a training schedule for the new team member to follow over the next few weeks.

C.

Ask a senior team member to help the new team member navigate through all the documentation.

D.

Escalate the inquiry to the team member's functional manager.

Full Access
Question # 20

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

A.

Adjust the original budget estimates with the current cost variance.

B.

Perform a root cause analysis of the project performance.

C.

Review the activity duration to reforecast the project completion date.

D.

Negotiate the project changes and adjust stakeholder expectations.

Full Access
Question # 21

A bank wantsto initiate a new service for its customers that will also increase revenue. This service must comply with strict cyber regulation guidelines. Halfway through the project life cycle, the cyber

regulations change, which has a large impact on the project.

What type of status report should the project leader present to the stakeholders?

A.

Areport that includes a detailed risk mitigation plan and action items for complying with changes

B.

Areport that is concise and simple, and that clearly states the impact the changes will have

C.

A report containing statistics, detailed tasks to be done, and an explanation of the impact of the changes

D.

A report including the change control process for the requested changes and the updated risk register

Full Access
Question # 22

A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in

meetings with end users. The meetings have been slowing down project progress.

What should the project manager do to keep the deployment on track while obtaining stakeholder approval?

A.

Put all of the requirements, priorities, and progress on a visible board, share it with all entities, and decrease the number of meetings.

B.

Ask the project sponsor to attend the meetings on behalf of the team while the team is working on the development.

C.

Inform the stakeholders that a daily meeting will take place at a specific time and ask them to share their feedback during this time.

D.

Stop attending meetings, start development with what was collected so far, and define a date for the first delivery of the solution.

Full Access
Question # 23

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?

A.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

B.

Create a reward system granting incentives to the team members who are able to catch more defects.

C.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems.

D.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones.

Full Access
Question # 24

A project manager is newly assigned to the second phase ofan ongoing project. During theimplementation, a defect occurred and no oneknows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?

A.

Acquire knowledgeable resources.

B.

Check the organizational process assets (OPAs).

C.

Update the risk management plan.

D.

Extend the timeline of the project.

Full Access
Question # 25

A project manager has just been assigned to a new project. The project manager's first task is to present the project benefits to the stakeholders.

Which three items should form part of the presentation? (Choose three)

A.

Risks associated with achieving the target benefits

B.

Communications management plan

C.

Metrics to measure benefits throughout the project

D.

Expected business value

E.

Stakeholder register

Full Access
Question # 26

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain. When attempting to gain an understanding of the risks for this agile project, what is the primary tool the project manager should employ?

A.

Probability assessments

B.

Workshops for risk avoidance

C.

Interview with the project champion

D.

Collaborative discussion

Full Access
Question # 27

Some project teams are voicing frustration because of conflicting priorities between agile and predictive work in a complex project. Which leadership style would effectively promote collaboration across the

project teams?

A.

Delegative leadership

B.

Servant leadership

C.

Directive leadership

D.

Leadership by example

Full Access
Question # 28

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a

timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

A.

Delegate certain authorities and share information to allow fair decision-making.

B.

Delegate most authorities and control the authority by withholding important information.

C.

Delegate most authorities and share information to allow fair decision-making.

D.

Delegate certain authorities and control the authority by withholding important information.

Full Access
Question # 29

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The

project manager starts to present the budget, but the CEO suddenly asks to end the meeting.

What should the project manager have done to avoid this situation?

A.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register.

B.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting.

C.

Reviewed the communications management plan before inviting an external client representative to the meeting.

D.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting.

Full Access
Question # 30

At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product

owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.

What should the project manager do?

A.

Organize a workshop after the standup to assess the impact.

B.

Prepare a budget change request for additional resources.

C.

Create a new product backlog item for the next sprint planning.

D.

Ask the product owner to provide more details in the standup.

Full Access
Question # 31

A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company’s operations support team. However, many new members have just been added

to the operations support team who are not familiar with the project and the project's acceptance is now at risk.

What should the project manager do to mitigate this transition risk?

A.

Request the steering committee to authorize an early project deployment (i.e., a “beta” transition release) and engage the operations support team in the early release.

B.

Request the steering committee to reevaluate the feasibility of transitioning and closing the project given the personnel changes on the operations support team.

C.

Request the steering committee to train only the selected operations team members who are familiar with the project and then train the new team members separately.

D.

Request the steering committee to exclude the new team members during the transition and train the new members after the planned transition is completed.

Full Access
Question # 32

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

A.

Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.

B.

Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

C.

Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Full Access
Question # 33

A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk. The sponsor forwarded the email to the project managerasking for further details. After speaking with the sponsor, the project manager decided to take preventive action.

Which document should the project manager review with their team?

A.

Procurement management plan

B.

Communications management plan

C.

Quality management plan

D.

Risk management plan

Full Access
Question # 34

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agilepractices, which are relevantto the project.

What should the project manager do to gain buy-in from the different stakeholders?

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.

B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.

C.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.

D.

Ask the project management office (PMO) to get buy-in from the stakeholders because agile is an approach that differs from their previous ways of working.

Full Access
Question # 35

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.

During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

A.

Ensured that all the required approvals were received per the organizational procedures

B.

Ensured that all defects identified during testing were resolved before implementation

C.

Ensured that all of the required tasks identified in the scope were completed successfully

D.

Ensured that all documentation was completed post implementation before closing the project

Full Access
Question # 36

A verbal announcement is made that the new team member joining the Scrum team has limited mobility. The scrummaster is aware that some teammembers are unsure how the dynamics of the team will change.

What should the scrum master do?

A.

Create a stakeholder engagement plan.

B.

Design a communications management plan.

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make.

Full Access
Question # 37

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not

be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline.

B.

Review and update the issue log and determine if any alternative components can be offered.

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Replace the vendor with a new vendor who can offer the component on time.

Full Access
Question # 38

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in

the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for

the second milestone are changed.

Which two actions should the project manager take? (Choose 2)

A.

Ask the customer for their priorities regarding the requirements for the second milestone.

B.

Convince the customer to leave the second milestone in place and not change it.

C.

Tell the customer that moving the milestone has a very high impact on the cost of the project.

D.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

E.

Escalate the issue to upper management to resolve the problem, and suggest a plan.

Full Access
Question # 39

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the

project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

A.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions. @]

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Full Access
Question # 40

Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts arise due to a lack

of clarity on processes and the project manager's relationship with company B.

What should the project manager do to resolve this conflict?

A.

Work with the team to analyze which processes are suitable to use and define them in the ground rules.

B.

Ask the team to use company B's processes since they are more familiar with these processes.

C.

Avoid the conflict as the customer feels comfortable with using processes from company A.

D.

Review the historical information and make the decision based on the return on investment (ROI).

Full Access
Question # 41

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do toovercome this challenge?

A.

Approach the project sponsor and request help in discussing the project deliverables with team members.

B.

Assign multiple managers to the various teams and delegate all of the tasks to them.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Meet with each team member separately and apply an appropriate approach with each one.

Full Access
Question # 42

A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.

To what level should the project manager decompose their project?

A.

To the level where the highest level of quality is maintained

B.

To the lowest level where cost and duration can be estimated and managed

C.

To level four of the schedule for bridge construction

D.

To the level where the bridge can be constructed safely

Full Access
Question # 43

A hybrid project is experiencing several issues with both the agile delivery of the product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.

Refer to the communications management plan.

B.

Refer to the stakeholder engagement plan.

C.

Set up a conference call for all stakeholders.

D.

Send an email to all stakeholders.

Full Access
Question # 44

A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know

how frequently the risks are being reviewed.

Which document project manager should check first?

A.

Risk management plan

B.

Risk register

C.

Issue log

D.

Risk report

Full Access
Question # 45

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team

members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

A.

Draft a points system to allocate a portion of the money for each resource.

B.

Arrange a luncheon for all team members and include team-building sessions.

C.

Meet with the team members and ask them how to spend the reward.

D.

Allocate the reward to the team leaders to spend on the team as they see fit.

Full Access
Question # 46

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customerdetailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent theproject from being completed in the number of iterations initially planned.

What should the project manager do next?

A.

Create a contingency plan in case the project deviates from the initial plan.

B.

Create an assumption log and map assumptions to impediments based on the impact to the project value.

C.

Create an issue log template that will be used to identify and track impediments.

D.

Create a schedule management plan to ensure the project meets the delivery date.

Full Access
Question # 47

An agile project is starting its seventh out of eight iterations. In a planning meeting, the team realizes that an unidentified risk became an issue, and the contingency reserve has to be used.

What should the project manager do?

A.

Help the team review the project approach to initiate the corrective actions.

B.

Ask the sponsor to approve inclusion of an additional iteration to the project.

C.

Ask the sponsor for money to implement the contingency plan.

D.

Ask the team to include the contingency plan in the iteration backlog.

Full Access
Question # 48

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and verycomplex to define at this stage.

What should the project manager do?

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment withoutinterference from a predictiveapproach.

B.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define theproject scope.

C.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex items.

D.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.

Full Access
Question # 49

A project manager is in the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence. The project isahead of schedule and running under budget.

Which two actions should the project manager take initially to resolve this problem? (Choose two)

A.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected.

B.

Check if the team member's activities are sufficiently documented to facilitate handover.

C.

Check the risk register for a prepared response to a resource being suddenly unavailable.

D.

Obtain the project sponsor's support to replace the team member on leave.

E.

Reassign responsibilities across the remaining members using the available float for training.

Full Access
Question # 50

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

Full Access
Question # 51

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.

How should the project manager handle the situation?

A.

Have a discussion with the project sponsor and cancel the project.

B.

Have a discussion with the sponsor and recommend the project business value be reassessed.

C.

Remove the items no longer applicable from the backlog and present the backlog to the project team.

D.

Continue working on the defined scope and review the risk matrix.

Full Access
Question # 52

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.

This is going to significantly impact the deliverable.

What should the project manager do?

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

D.

Inform the customer of the impact immediately and prepare for escalation.

Full Access
Question # 53

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the

team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

A.

Discuss the issue with the team member's functional manager.

B.

Inform the human resource (HR) department about the issue.

C.

Speak to the team member regarding the need to improve performance.

D.

Allow the project team to discuss the problem with this team member.

Full Access
Question # 54

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Full Access
Question # 55

A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

A.

Talk to the client privately to highlight the situation.

B.

Remove the project team member from all future meetings.

C.

Recommend a performance improvement plan to the project team member.

D.

Explain the impact of the scenario to the project team member.

Full Access
Question # 56

A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.

Which tool is the project manager using?

A.

Secureanalysis

B.

Time and materials (T&M) contract

C.

Earned value (EV)

D.

Control chart

Full Access
Question # 57

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue?

(Choose three)

A.

Adjust the project management plan to include the changes in scope.

B.

Continue the execution as planned and defer the changes to a future phase.

C.

Highlight the impacts of the changes during the next project meeting.

D.

Schedule a meeting with the customer to align the approach.

E.

Update the relevant project documents with this obstacle.

Full Access
Question # 58

A company is transitioning from a predictive approach to an agile approach. The team members work remotely, and some have personal conflicts that make themunavailable for some project ceremonies. The product owner has made it clear that the agenda is very tight and the team should make every effort to participate in allceremonies.

What should the project manager, as a servant leader, do to address this situation?

A.

Ask the team members to decide collectively on how to support the team.

B.

Engage in separate ceremonies with these team members to allow them to stay on the project.

C.

Evaluate alternative options and try to find resources with similar skills.

D.

Perform the ceremonies without the team members and send them notes by email.

Full Access
Question # 59

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user partywas not included in any of therequirements collection communications.

Which of the documents was likely missed or outdated?

A.

Stakeholder Register

B.

Business Documentation

C.

Project Charter

D.

Risk Register

Full Access
Question # 60

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail the service instructions to avoid anyredo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

A.

Document the task on the kanban board and make it the highest priority.

B.

Escalate the issue to the engineer's functional manager.

C.

Discuss the issue with the engineer and determine how to prevent another problem.

D.

Assign another engineer to the task due to the urgency.

Full Access
Question # 61

A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the

executives regarding the processes to be followed.

How should these conflicts be resolved?

A.

Request that the executives use agile practices.

B.

Include the executives in team retrospectives.

C.

Train the executives on agile practices.

D.

Negotiate with the executives and agree on a process.

Full Access
Question # 62

A senior project manager is assigned to lead a team of project managers to run a large initiative. Oneof the key stakeholders oftenbypasses the senior project manager and gives instructions to the other project managers directly.

What should the senior project manager do?

A.

Tell the project managers to document the stakeholder's instructions.

B.

Evaluate the stakeholder analysis to identify the stakeholder's influence.

C.

Review the benefits realization plan with the sponsor and the stakeholder.

D.

Escalate to the project sponsors and the manager of this stakeholder.

Full Access
Question # 63

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

A.

Establish a project schedule.

B.

Assign a team leader.

C.

Recognize the team's contributions.

D.

Establish a team charter.

Full Access
Question # 64

Drag the interpersonal skill on the left to the correct scenario on the right.

Full Access
Question # 65

A team has been working for two months and has consistently missed planned user stories. How should the project manager address this issue?

A.

Promote changing the iteration duration in order to commit as planned.

B.

Consider using a reward system to encourage timely delivery.

C.

Ensure the sprint size is appropriate for the iteration duration.

D.

Engage in recruiting a highly skilled resource to reinforce the skills.

Full Access
Question # 66

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

A.

Build the functionality in the software to collect the operational usage data.

B.

Send out a questionnaire to all users regarding the most useful features.

C.

Embed a feedback form into the system for users to respond.

D.

Interview a sampling of users to obtain the usage data.

Full Access
Question # 67

A project manager is appointed to manage an infrastructure project that spans across several countries, including different time zones withina subregion. It is likely thatmost of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

A.

Discuss the concerns with the project sponsor and modify the project charter to include more budget for interactions.

B.

Set the ground rules and identify a contingency plan in the risk register.

C.

Plan a communication method and allow the project team members to virtually interact.

D.

Create a social media group platform for the team to create a supportive environment.

Full Access
Question # 68

A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to

continue in the event of this occurrence.

What shouldthe project manager do?

A.

Ask the supplier to continue providing software support until the end of the project.

B.

Inform the sponsor that the risk has been realized and that a decision has to be made for the project to continue.

C.

Tell the project team to stop work, as software support will be canceled and the project cannot continue.

D.

Advise the supplier that the sponsor will pay for software support as previously planned.

Full Access
Question # 69

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of thecomponents is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has

been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

A.

Show the customer the tolerance and control limits.

B.

Show the customer sample results from the current batch.

C.

Show the customer a sample history of quality.

D.

Show the customer the quality control measurements.

Full Access
Question # 70

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.

What should the project manager do?

A.

Ask the team member to develop a dashboard to fulfill the request.

B.

Tell the team member to route the request through the project manager.

C.

Update the communications management plan to include informal requests.

D.

Update the stakeholder engagement assessment matrix.

Full Access
Question # 71

A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.

What should the project manager do to improve communication among the team?

A.

Setup a team communications management plan for the company and team members to follow immediately.

B.

Explain the benefits of common working hours to aid better communication among the project team.

C.

Share a contact log document for all the team members to make communication easier.

D.

Arrange for some initial face-to-face team meetings for the project team to meet each other.

Full Access
Question # 72

A project manager has noticed that the performance of a new team member has increased dramatically over the past fewmonths. The project manager hasbeen measuring this team member's performance through the cost performance index (CPI) and schedule performance index (SPI) of work packages. The

project manager has also assigned new, unrelated work packages to this team member. The project manager wants to formally record the team member'ssuccess in the project documentation.

What should the project manager do?

A.

Attach a note to the project management plan about the team member.

B.

Send a communication to management recognizing the team member's contributions.

C.

Hold a project team meeting about the team member's contribution and take minutes.

D.

Record the team member's contribution in the responsibility assignment matrix (RAM).

Full Access
Question # 73

A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, the company recorded a drastic reduction in revenue. The strategic direction was to implement cost-reduction measuresimmediately.

What should the project manager do next?

A.

Schedule a meeting with the product owner, discuss priorities, and decide if anything from the backlog can be eliminated, based on current constraints.

B.

Continue the current sprint without interruption and address priorities in the upcoming product backlog grooming sessions.

C.

Allow the project team to decide on the best path forward for the current sprint. ~ J

D.

Meet with the sponsor for guidance on the best path forward before executing sprints.

Full Access
Question # 74

During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?

A.

Identify the resources that were responsible for the deliverable and request a team development plan.

B.

Update the risk register and implement the approved risk response plan for quality deviations.

C.

Update the issue log, identify the involved stakeholders, and assign resources to the corrective actions.

D.

Submit a change request to update the project quality requirements for the involved project deliverable.

Full Access
Question # 75

A project manager is meeting with the project sponsor regarding a new project. The project manager tells the sponsor that, as part of the communications management plan, a weekly email will be sent with thestatus of the project, so the sponsor can be informed of the progress. The sponsor indicates that the email is not necessary because they will ask for a status update whenever it is needed.

What should the project manager do next?

A.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

B.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

C.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

D.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

Full Access
Question # 76

Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next

iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.

What should the project manager do next?

A.

Check the project budget to verify if there is enough contingency reserve.

B.

Tell the team members that more equipment is not part of the project's scope.

C.

Submit a change request to increase the budget and buy new equipment.

D.

Review the cost management plan to determine how to address this issue.

Full Access
Question # 77

Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.

What should the project leader do?

A.

Explain the financial constraint and ask each team member to pay their own share for the event.

B.

Use the office facilities and support to organize an interactive event for the team members in-house.

C.

Tell the team that the event will be handled at the end of the project due to current financial constraints.

D.

Bypass the event because the team members’ seniority is enough to engage without further activities.

Full Access
Question # 78

A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?

A.

Engage with the project sponsor to understand the scope.

B.

Develop a comprehensive set of requirements.

C.

Create a project schedule containing milestones.

D.

Identify the tangible and intangible benefits.

Full Access
Question # 79

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

A.

Instruct the team to analyze and interpret the data before including it in the report.

B.

Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

C.

Instruct the team to make only a graphical representation of all the data for the report.

D.

Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

Full Access
Question # 80

An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult toknow what to work on next as so many items are listed as high priority.

What should the project manager recommend?

A.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

B.

Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.

C.

Discard the current categorization of requirements as "high, medium, and low" and prioritize numerically.

D.

Ask the team to prioritize the high-priority items based on the release plan and what allows for testing most effectively.

Full Access
Question # 81

In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

A.

Empower the team members to do their work.

B.

Inform the project sponsor about this situation.

C.

Work with the team to develop a risk response plan.

D.

Send an email to human resources (HR) about this situation.

Full Access
Question # 82

A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

A.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the project.

B.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the restof the scope at the end of theproject.

D.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver valueincrementally.

Full Access
Question # 83

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project execution. The

acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the stakeholder who was providing additional funds remained interested in the project.

C.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

Full Access
Question # 84

A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

A.

Implement a project management information system (PMIS).

B.

Encourage better team communication by positioning team members closer together.

C.

Update the communications management plan to ensure correct delivery of the latest version.

D.

Restrict team members from sending the requirements documents via email.

Full Access
Question # 85

A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability

to perform a what-if analysis in the tool based on the customer demand and forecast.

What should the project manager do next?

A.

Include the new capability to the product backlog and continue activities based on the current plan.

B.

Perform an impact analysis on the schedule and budget based on the additional scope.

C.

Analyze and negotiate with the executive steering committee regarding this new request.

D.

Revise the project schedule and budget based on the additional scope, and review with the team.

Full Access
Question # 86

A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

A.

Mark the product backlog completion status and update the communications management plan.

B.

Release the resources and plan for a project completion celebration.

C.

Hold a steering committee meeting to inform them of the project completion.

D.

Ensure that knowledge transfer activities are executed as planned.

Full Access
Question # 87

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two teammembers are not responding tothe construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the

construction manager.

What should the project manager do to improve the situation?

A.

Ask the construction manager to meet with the two team members to resolve the situation.

B.

Ask the team members to tolerate the cultural differences as they have a different cultural background.

C.

Discuss the team members’ concern with the construction manager and seek solutions.

D.

Provide the construction manager with instructions on how to resolve the situation.

Full Access
Question # 88

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.

Full Access
Question # 89

A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this teammember could add value to the project.

What should the project manager do to get the most value from this team member?

A.

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

B.

Advise the team member not to share personal information from past projects with the entire team.

C.

Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

D.

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

Full Access
Question # 90

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT team, the releases are delayed.

What action should the project manager take?

A.

Work with the IT team to prioritize the validation and release of the new features.

B.

Escalate the issue from the IT team to management and get the validation prioritized.

C.

Request the IT team to immediately release the product and then validate the features.

D.

Deliver the features when the IT team is able to validate them.

Full Access
Question # 91

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is

dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

A.

Notify the stakeholder that arbitration procedures will be followed.

B.

Review the requirements traceability matrix and conduct inspections.

C.

Document the issue in the issue log and send a report to management.

D.

Inform the project sponsor of the stakeholder's dissatisfaction.

Full Access
Question # 92

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

A.

Assign an owner for each backlog activity and track progress.

B.

Ask for more resources to clear the backlog activities.

C.

Prioritize which backlog activities should be kept.

D.

Work on the backlog activities with fewer story points.

Full Access
Question # 93

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that

having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

A.

Ask the scrum master to attend the workshops.

B.

Ask the Scrum team members to share retrospectives.

C.

Invite the Scrum team members as mandatory participants.

D.

Invite the Scrum team members as optional participants

Full Access
Question # 94

A company is initiating a project to enhance one of its existing products. All of its products are developed internally.

What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Create a lessons learned document for the initiation phase.

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Review the lessons learned from the previous project

Full Access
Question # 95

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team

was average.

What should the project manager do to help the new compliance specialist improve?

A.

Coordinate a one-to-one meeting with the specialist to assess the situation.

B.

Contact the human resources (HR) manager about the team's feedback.

C.

Escalate this situation to the manager of the area for a possible solution.

D.

Provide time for the specialist to adjust to the pace of the project.

Full Access
Question # 96

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use toupdatethe details and communicate to relevant stakeholders?

A.

Change request

B.

Project schedule

C.

Risk register

D.

Issue log

Full Access
Question # 97

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for

installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.

Inform the project team only.

B.

Inform the product owner.

C.

Inform the relevant stakeholders.

D.

Inform the project sponsor.

Full Access
Question # 98

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.

What should the project manager do next?

A.

Reject the change request since it may negatively impact the project's performance.

B.

Implement the change request as soon as possible to avoid accumulating new scope.

C.

Keep the focus on the priority items while the change goes through the change control process.

D.

Use the team's connections with international colleagues to get early warnings on future changes.

Full Access
Question # 99

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project managermainly make reference to?

A.

Competencies of team members

B.

Agreed-upon key performance indicators (KPIs)

C.

Feedback from the project sponsor

D.

Input from project stakeholders

Full Access
Question # 100

Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.

What should the project manager do to ensure success of the project?

A.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

B.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

C.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project.

D.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.

Full Access
Question # 101

A project manager has been assigned to a new project. There is one team member who never says anything during meetings. After meetings, however, the team member

sends detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

A.

Motivate the team members to speak freely in the meeting.

B.

Arrange a team-building activity to involve all team members.

C.

Remind the team members to follow the team charter.

D.

Review the communications management plan with the team members.

Full Access
Question # 102

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done.

What should the project manager do?

A.

Support the team to find and execute the minimum viable product (MVP).

B.

Subdivide the team to handle different aspects of the project.

C.

Organize project execution to satisfy the project sponsor's request.

D.

Encourage and motivate the team with project incentives.

Full Access
Question # 103

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.

How should the project manager approach this situation?

A.

Educate the customer and have them participate in daily standup meetings. ®

B.

Request that the customer reviews and clarifies feature definitions for the current sprint.

C.

Send a burndown chart of the current sprint to the customer and seek clarifications.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements.

Full Access
Question # 104

A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within the

organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the projects to use

more agile methodologies.

Before mandating any agile methods to be used in a project, what should the project manager do first?

A.

Pause the current projects to align them to the new agile cadence.

B.

Shift all existing projects to agile methodologies with a strict timeline.

C.

Provide agile training to those who will be part of the project team.

D.

Assess the organizational culture and readiness for the transformation.

Full Access
Question # 105

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically last 45 minutes with manymisunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

A.

Instruct the meeting participants to speak only about blockers during the meeting.

B.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

C.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.