Last Update 11 minutes ago Total Questions : 2040
The Project Management Professional (2025 Version) content is now fully updated, with all current exam questions added 11 minutes ago. Deciding to include PMP practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our PMP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PMP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Project Management Professional (2025 Version) practice test comfortably within the allotted time.
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
During a kick-off meeting at the start of project execution, the vendor presents a
migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.
What should the project manager do?
A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution. The project manager must assess and prioritize the impact of these changes on the project scope/backlog.
Which analytical tool can be used by the project manager to define this scenario?
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value
What should the new project manager do next?
A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on
weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need
What should the project manager do'?
In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?
A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
What should an agile lead do lo ensure their team is set up for success?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix
What should the project manager do with regard to community engagement in this situation''
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.
What strategy should the project manager use to ensure on-time delivery of the solution?
A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?
Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.
What should the project manager do to engage the stakeholders?
The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.
What should the project manager do first?
An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.
What should the project manager do first to resolve this dispute?
A project is approaching its project closure phase, and the project manager receives
an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose
three)
A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.
What action should the project manager take?
A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner's preferred language; however, they are very skilled in the other language.
What should the project manager do?
A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,
What should the project manager do?
During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?
After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has
doubts about the feasibility of the project.
What should the project manager do in this situation?
A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members
Which three actions should the project manager take? (Choose three)
It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.
What should the project manager do?
A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.
What should the project manager do next?
A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.
What technique is the project manager applying?
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
