A project manager has been assigned to a corporate project management office (PMO). They are responsible for leading the development and rollout of updated project management procedures and templates
that would include both predictive and agile approaches,
What should the project manager do after the documents are completed?
A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the keystakeholders.
What should the project manager do first?
A project manager is working with the product owner and customer stakeholders on prioritizing the product backlog and planning the product delivery dates. The customer stakeholders are asking to include several deliverables as high priority. The product manager also has technical tasks that should be added as high priority.
What should the project manager do?
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. Theproject manager has to meet animportant milestone in a week.
What should the project manager do next?
An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allowfor more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, butalso wants to accommodate newinformation and changes as the project progresses.
Which project management approach should the project manager select for this project?
A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides withthe company's financial budget planning period.
Which two actions should the project manager take next to address this concern? (Choose two)
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent
to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not
have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?
A product owner is trying to understand how many of the user stories have been completed within a 2-week sprint. How should the project manager approach this situation?
A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignmentsfrom multiple people and states they are not able to work effectively.
What should the project manager establish first in the project governance structure?
project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining. What will
help the project manager understand why this has occurred?
A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the
organization and have varying levels of interest.
Which approach should the project manager use with the stakeholders?
A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the differentrequirements?
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
A bank wantsto initiate a new service for its customers that will also increase revenue. This service must comply with strict cyber regulation guidelines. Halfway through the project life cycle, the cyber
regulations change, which has a large impact on the project.
What type of status report should the project leader present to the stakeholders?
A project team is working to deliver a solution to manage nationwide crisis relief operations. The project team is spending most of its time in
meetings with end users. The meetings have been slowing down project progress.
What should the project manager do to keep the deployment on track while obtaining stakeholder approval?
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?
A project manager is newly assigned to the second phase ofan ongoing project. During theimplementation, a defect occurred and no oneknows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.
What should the project manager do first?
A project manager has just been assigned to a new project. The project manager's first task is to present the project benefits to the stakeholders.
Which three items should form part of the presentation? (Choose three)
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain. When attempting to gain an understanding of the risks for this agile project, what is the primary tool the project manager should employ?
Some project teams are voicing frustration because of conflicting priorities between agile and predictive work in a complex project. Which leadership style would effectively promote collaboration across the
project teams?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a
timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The
project manager starts to present the budget, but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product
owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.
What should the project manager do?
A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company’s operations support team. However, many new members have just been added
to the operations support team who are not familiar with the project and the project's acceptance is now at risk.
What should the project manager do to mitigate this transition risk?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk. The sponsor forwarded the email to the project managerasking for further details. After speaking with the sponsor, the project manager decided to take preventive action.
Which document should the project manager review with their team?
An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agilepractices, which are relevantto the project.
What should the project manager do to gain buy-in from the different stakeholders?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.
During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
A verbal announcement is made that the new team member joining the Scrum team has limited mobility. The scrummaster is aware that some teammembers are unsure how the dynamics of the team will change.
What should the scrum master do?
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not
be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in
the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for
the second milestone are changed.
Which two actions should the project manager take? (Choose 2)
A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the
project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts arise due to a lack
of clarity on processes and the project manager's relationship with company B.
What should the project manager do to resolve this conflict?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do toovercome this challenge?
A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.
To what level should the project manager decompose their project?
A hybrid project is experiencing several issues with both the agile delivery of the product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know
how frequently the risks are being reviewed.
Which document project manager should check first?
A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team
members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?
A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customerdetailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent theproject from being completed in the number of iterations initially planned.
What should the project manager do next?
An agile project is starting its seventh out of eight iterations. In a planning meeting, the team realizes that an unidentified risk became an issue, and the contingency reserve has to be used.
What should the project manager do?
An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and verycomplex to define at this stage.
What should the project manager do?
A project manager is in the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence. The project isahead of schedule and running under budget.
Which two actions should the project manager take initially to resolve this problem? (Choose two)
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.
How should the project manager handle the situation?
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.
This is going to significantly impact the deliverable.
What should the project manager do?
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the
team had difficulty meeting the iteration goals.
How should the project manager handle this situation?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?
A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.
Which tool is the project manager using?
During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue?
(Choose three)
A company is transitioning from a predictive approach to an agile approach. The team members work remotely, and some have personal conflicts that make themunavailable for some project ceremonies. The product owner has made it clear that the agenda is very tight and the team should make every effort to participate in allceremonies.
What should the project manager, as a servant leader, do to address this situation?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user partywas not included in any of therequirements collection communications.
Which of the documents was likely missed or outdated?
During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail the service instructions to avoid anyredo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.
What should the project manager do next?
A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the
executives regarding the processes to be followed.
How should these conflicts be resolved?
A senior project manager is assigned to lead a team of project managers to run a large initiative. Oneof the key stakeholders oftenbypasses the senior project manager and gives instructions to the other project managers directly.
What should the senior project manager do?
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
Drag the interpersonal skill on the left to the correct scenario on the right.
A team has been working for two months and has consistently missed planned user stories. How should the project manager address this issue?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
A project manager is appointed to manage an infrastructure project that spans across several countries, including different time zones withina subregion. It is likely thatmost of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.
What should the project manager do to ensure good collaboration between the remote project team members?
A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to
continue in the event of this occurrence.
What shouldthe project manager do?
Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of thecomponents is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has
been maintained.
How should the project manager communicate with the customer to help assure them that the project has produced quality products?
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.
What should the project manager do?
A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.
What should the project manager do to improve communication among the team?
A project manager has noticed that the performance of a new team member has increased dramatically over the past fewmonths. The project manager hasbeen measuring this team member's performance through the cost performance index (CPI) and schedule performance index (SPI) of work packages. The
project manager has also assigned new, unrelated work packages to this team member. The project manager wants to formally record the team member'ssuccess in the project documentation.
What should the project manager do?
A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, the company recorded a drastic reduction in revenue. The strategic direction was to implement cost-reduction measuresimmediately.
What should the project manager do next?
During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?
A project manager is meeting with the project sponsor regarding a new project. The project manager tells the sponsor that, as part of the communications management plan, a weekly email will be sent with thestatus of the project, so the sponsor can be informed of the progress. The sponsor indicates that the email is not necessary because they will ask for a status update whenever it is needed.
What should the project manager do next?
Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next
iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.
What should the project manager do next?
Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.
What should the project leader do?
A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?
A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?
An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult toknow what to work on next as so many items are listed as high priority.
What should the project manager recommend?
In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project execution. The
acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.
What should the project manager have done to prevent this from happening?
A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability
to perform a what-if analysis in the tool based on the customer demand and forecast.
What should the project manager do next?
A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
A multicultural team is working on a project. After a few months of observation, the project manager realizes that two teammembers are not responding tothe construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the
construction manager.
What should the project manager do to improve the situation?
A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project manager knows this teammember could add value to the project.
What should the project manager do to get the most value from this team member?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT team, the releases are delayed.
What action should the project manager take?
A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is
dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that
having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team
was average.
What should the project manager do to help the new compliance specialist improve?
A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use toupdatethe details and communicate to relevant stakeholders?
A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for
installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.
What does the project manager need to do now?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.
What should the project manager do next?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project managermainly make reference to?
Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.
What should the project manager do to ensure success of the project?
A project manager has been assigned to a new project. There is one team member who never says anything during meetings. After meetings, however, the team member
sends detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done.
What should the project manager do?
A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.
How should the project manager approach this situation?
A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within the
organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the projects to use
more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?
A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically last 45 minutes with manymisunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?