Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Oracle EBS R12.1 Purchasing Essentials

Last Update 19 hours ago Total Questions : 261

The Oracle EBS R12.1 Purchasing Essentials content is now fully updated, with all current exam questions added 19 hours ago. Deciding to include 1z0-520 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our 1z0-520 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these 1z0-520 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Oracle EBS R12.1 Purchasing Essentials practice test comfortably within the allotted time.

Question # 71

The materials manager has noticed that several items were created and assigned to various inventory organizations, but the analyst skipped the Copy from Template step. The manager would like to know how to correct the items. Which three statements are true? (Choose three.)

A.

Apply the template in the organization item. It would automatically update the Master Item window.

B.

You can use the Item Attribute Copy form to update the value of an item attribute across multiple organizations in a given organization hierarchy.

C.

You can change an organization-level attribute with the Master Item window. If you do this, it will update the organization-level attribute across all organizations.

D.

You can use the Organization Item window to update organization-level itemattributes. This would update organization-level attributes in your current organization only.

E.

To update master-level attributes, use the Master Item window. If an attribute is controlled at the master level, the value of the attribute applies for all organizations to which the item is assigned.

Question # 72

The Child Lots check box is enabled at the organization item level. Which two statements are true? (Choose two.)

A.

The lot splitting process is enabled by this feature.

B.

The system would maintain lot genealogy with child and parent lots.

C.

Child lot characteristics are completely different from that of parent lots.

D.

Child lots are unique and independent lots. They are not linked with parent lots.

E.

Short expiry lots are child lots. Child lots generate unique numbers across items.

F.

Child lots are a subdivision of the parent lots and maintain integrity with the parent lots.

Question # 73

You need to set up a Material Review Board (MRB) subinventory for storing defective goods that are awaiting disposition. The management team does not want the material in the MRB subinventory to be considered by the Material Requirements Plan (MRP). Which is the key flag in the setup that instructs MRP not to account for the material in the MRB subinventory?

A.

Nettable flag deselected

B.

Planning flag deselected

C.

Quantity Tracked flag selected

D.

Allow Reservation flag deselected

E.

Asset Subinventory flag deselected

Question # 74

What is the prerequisite for entering unscheduled entries in a cycle count?

A.

Run a manual schedule request to generate counts.

B.

Generate cycle count requests before entering counts.

C.

Run an automatic schedule request to generate counts.

D.

Run the count generation program for unscheduled entries.

E.

Set the Unscheduled Entries flag to Yes in the cycle count header.

Question # 75

ACME requires cycle counting variance approval tolerances and the Approval Required option is set to: If out of tolerance. When the actual count falls within tolerance, Inventory __________ .

A.

automatically approves and posts the cycle count adjustment

B.

automatically approves, but does not post the cycle count adjustment

C.

holds the cycle count adjustment for approval and posts it after approval

D.

holds the cycle count adjustment for a recount and does not post the adjustment

Question # 76

You are moving items from locator A to locator B within the same inventory organization. Which two types of inventory transactions are required? (Choose two.)

A.

Move Order

B.

Locator transfer

C.

Subinventory transfer

D.

WIP component issue

E.

Miscellaneous Receipt

F.

WIP assembly completion

G.

Interorganization transfer direct

Question # 77

Which three statements are true about ABC Analysis and cycle count Classes? (Choose three.)

A.

The hit/miss% for the Class overrides the hit/miss% of the cycle count header.

B.

The hit/miss% for the cycle count header overrides the hit/miss% of the Class.

C.

An ABC Analysis can be compiled for a subinventory that is defined as a non-quantity-tracked subinventory.

D.

An ABC Analysis can be compiled for nonasset (expense) subinventories for which quantities are tracked.

E.

In ABC Analysis, a quantity variance must always be submitted for approval, regardless of the tolerance levels.

F.

Positive and negative tolerances can be entered for each class, which will override the tolerance at the cycle count header level.

Question # 78

Which key area in the Procure to Pay process involves using Oracle iExpenses to enter expense reports via a Web browser?

A.

Payment

B.

Invoicing

C.

Sourcing

D.

Reporting

E.

Receiving

Go to page: