You'll find that our CBCI exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CBCI sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certificate of the Business Continuity Institute (CBCI) practice test comfortably within the allotted time.

Question # 11

Which of the following is used to determine the organization ' s prioritised activities and the recovery timeframes and resource requirements?

A.

A risk assessment

B.

An exercise

C.

A Business Impact Analysis (BIA)

D.

A meeting with owners of product and services activities

Question # 12

Why is it important to use a warning or code word such as “exercise only” when providing communication injects during an exercise?

A.

To ensure that the information is not treated as a real message

B.

To ensure that the information is treated as confidential

C.

To indicate that the message has been approved by the exercise facilitator

D.

To indicate that all information should be treated as real during the exercise

Question # 13

Which of the following is an outcome of personnel embracing Business Continuity and the organization ' s Business Continuity Management System (BCMS)?

A.

A Business Continuity programme that is tailored specifically for the organization, taking into account its organizational culture

B.

A reduction in the need to update and review the BCMS due to the commitment of personnel in the development stage

C.

Increased sales of products and services due to public confidence in the published information about the organization’s resilience capability

D.

Validation of plans is no longer needed due to the high level of commitment from relevant personnel to their effective implementation

Question # 14

Which of the following is a factor that should be taken into consideration when developing an exercise program?

A.

It requires a series of events and activities scheduled over a period of time

B.

It is necessary to carry out exercises only once as initial tests will provide all of the required information

C.

A single type of exercise should be used for all so that participants become familiar with the structure and approach of the exercise activities

D.

It is necessary to carry out exercises for only a sample of the plans and recovery teams in place

Question # 15

When creating an effective response structure, which of the following should be considered as a critical requirement?

A.

A summary of the outcomes of the Business Impact Analysis (BIA)

B.

A method to monitor incidents so that early action can be taken to prevent them from escalating further

C.

Procedures to activate and control the response to an incident

D.

Procedures for carrying out risk assessments following the end of an incident

Question # 16

Which of the following statements best describes the relationship between Business Continuity strategies and solutions?

A.

Strategies align to the direction set out in the Business Continuity policy whilst solutions address the outlined objectives in the Business Continuity Management System (BCMS)

B.

Strategies are based on the outcomes of the Business Impact Analysis (BIA) whereas solutions are based on the outcomes of the risk assessment

C.

Strategies are high-level approaches for meeting the organization ' s Business Continuity requirements whereas solutions detail how the strategies will be implemented

D.

Strategies focus on the methods and procedures for business as usual activities whereas solutions focus on the treatments and actions to minimize risks

Question # 17

Which of the following is NOT a critical requirement for an effective response structure?

A.

A plan to communicate with internal and external interested parties

B.

The number and type of teams required by the organization

C.

A plan to exercise the escalation and response

D.

Guidance on when regulators should be notified and be included in the response

Question # 18

When establishing a Business Continuity Management System (BCMS), engagement with stakeholders is important. Which of the following is NOT a reason for engaging with internal stakeholders?

A.

Existing policies and procedures may be relevant to the BCMS so early identification will reduce the risk for duplication of work

B.

Early collaboration with colleagues will engage them in the process and secure support for the ongoing development and implementation of the BCMS

C.

Engagement of stakeholders will reduce the potential for conflict at later stages of the programme

D.

Involving stakeholders will reduce the workload and responsibilities of the Business Continuity Professional as administrative activities can be delegated to other staff

Question # 19

Which one of the following should be implemented when updating Business Continuity (BC) plans?

A.

A copy should be placed on the organization ' s shared drive so that personnel can identify it for themselves when they look at the system

B.

A formal version control process to identify the date of review and bring attention to changes

C.

A brief note about the update in a staff newsletter that is printed and placed on noticeboards

D.

An internal email to all personnel stating that a new version is available and suggesting that personnel request a copy of the new version if they are interested in seeing it

Question # 20

When implementing solutions so that they can be deployed to respond to disruption, the Business Continuity professional should:

A.

Review and revise the specifications for each solution developed in the design phase prior to launching them

B.

Work with the teams who will utilize the solutions to develop any new systems or tools required to enable implementation

C.

Allocate implementation to the relevant teams and instruct them to manage the implementation as they see fit and to their own timelines

D.

Empower the implementation team to make changes to specifications without referring back to top management