You'll find that our CLSSGB exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CLSSGB sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Lean Six Sigma Green Belt (CLSSGB) practice test comfortably within the allotted time.

Question # 31

As part of a Visual Factory plan Kanban cards are created and utilized to identify areas in need of cleaning and organization.

A.

True

B.

False

Question # 32

The 5 Why Analysis is only useful if the possible independent variable can be broken down into five possible causes.

A.

True

B.

False

Question # 33

The Central Limit Theorem helps us understand the ___________ we are taking and is the basis for using sampling to estimate population parameters.

A.

Analysis

B.

Kurtosis

C.

Risk

D.

Route

Question # 34

In the late 1980’s William Smith coined the name Six Sigma for a methodology that had its origins at __________________ for quality related work being done there.

A.

Honeywell

B.

Allied Signal

C.

General Electric

D.

Motorola

Question # 35

Which element of waste best describes " the unnecessary movement of materials and/or goods " ?

A.

Overprocessing

B.

Motion

C.

Conveyance

D.

Correction

Question # 36

Voice of the Customer is a Lean Six Sigma technique to determine ____________________ attributes of a product or service.

A.

At least 6

B.

The profitable

C.

Critical-to-Quality

D.

The majority of the

Question # 37

The Z score is a measure of the distance in Standard Deviations of a sample data point from the Median of the sample population.

A.

True

B.

False

Question # 38

Which statement(s) are true about the Fitted Line Plot shown here? (Note: There are 2 correct answers).

A.

When Reactant increases, the Energy Consumed increases.

B.

The slope of the equation is a positive 130.5.

C.

The predicted output Y is close to -18 when the Reactant level is set to 6.

D.

Over 85 % of the variation of the Energy Consumed is explained by the Reactant via this Linear Regression.

Question # 39

Customers make a purchase decision based on a number of factors. In Lean Six Sigma we refer to these decision points as CTQ’s or as ____________________.

A.

Critical-to-quality

B.

Conscious thought qualities

C.

Conspicuous time quandaries

D.

Cost of the quantity

Question # 40

The 80:20 rule is associated with which of these tools?

A.

Pareto Chart

B.

Simon ' s Cross-Functional Tool

C.

SIPOC

D.

Framing Tool