You'll find that our D-VXB-DY-A-24 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these D-VXB-DY-A-24 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Dell VxBlock Deploy Achievement practice test comfortably within the allotted time.

Question # 11

Which data layout technique is used on an Isilon cluster?

A.

Parity Correction Error (PCR)

B.

Backward Correction Error (BCR)

C.

Error Correction Code (ECC)

D.

Forward Correction Error (FEC)

Question # 12

In the Enhanced Knowledge Transfer Phase, what is the correct sequence of steps in the Finalize Project Deliverables?

Question # 13

You are testing a recently expanded VxBlock 1000. How can you verify that the hosts can communicate with XtremIO?

A.

Deactivate the storage controller

B.

Failover the Data Mover

C.

Reboot the BBU

D.

Power off a ToR switch

Question # 14

Which statement about the differences between Cisco ACI and VMware NSX is NOT correct?

A.

NSX supports both x86 and non-x86 servers; ACI does not

B.

NSX requires a gateway for the physical environment; ACI works the same for physical and virtual environments

C.

NSX is hardware independent; ACI is hardware dependent

D.

NSX is network topology independent; ACI supports only spine-leaf architecture

Question # 15

A customer is planning to integrate a VxBlock to a new Cisco ACI fabric. What major physical connectivity change is needed if the customer intends to convert their existing

VxBlock Nexus 9396PX switches to ACI mode?

A.

Connect the switch directly to the APIC to download the ACI software. Then connect the existing Nexus 9396PX switches to a spine Nexus 93180YC switch.

B.

Remove the dual peer link connection but keep the peer link connection for ACI fabric heartbeat traffic exchange.

C.

Connect the Nexus 9396PX switch to spine Nexus 9500 switches. Remove other connections between the Nexus 9396PX switches.

D.

Nexus 9396PX switch cannot be integrated directly to ACI fabric.

Question # 16

What is used to collect VxBlock component information during an RCM Assessment?

A.

VMware vRealize Operations

B.

VMware Configuration Automation Tool

C.

Dell EMC SCR

D.

Element Manager

Question # 17

In addition to the Final Test Plan and Customer Satisfaction Survey, what document/form is required to be signed by the customer at the Project Closure Meeting?

A.

Milestone Completion Form

B.

Final Project Signoff

C.

Project Workbook

D.

Project Feedback Form

Question # 18

What is the maximum number of X-Bricks that can be installed on a single XtremlO X2 array?

A.

8

B.

6

C.

2

D.

4

Question # 19

What is a primary use of the RCM Assessment Workbook?

A.

Collect the health report of all VxBlock remediation components

B.

Create the upgrade plan for the ToR switch only

C.

Identify items and components that require remediation

D.

Create the upgrade plan for Compute only

Question # 20

A System Engineer is working on an implementation of the VxBlock 1000. What is a required task in the final implementation step during the Deployment Phase?

A.

Verify system physical configuration against LCS

B.

Execute the agreed-upon test plan

C.

Configure Cisco Smart Call Home

D.

Connect to individual Element Managers