Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Huawei Certified ICT Professional - Wireless Local Area Network- Planning and Optimizing Enterprise WLAN

Last Update 14 hours ago Total Questions : 282

The Huawei Certified ICT Professional - Wireless Local Area Network- Planning and Optimizing Enterprise WLAN content is now fully updated, with all current exam questions added 14 hours ago. Deciding to include H12-322 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our H12-322 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these H12-322 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Huawei Certified ICT Professional - Wireless Local Area Network- Planning and Optimizing Enterprise WLAN practice test comfortably within the allotted time.

Question # 81

In an outdoor wireless coverage scenario of a WLAN, the AP6510DN is used to cover the external antenna, and the throughput of the wireless terminal is maintained at a low value.

What are the reasons for the results?

A.

Test terminal to support 802.11ac

B.

Interference causes a drop in throughput

C.

RSSI is too low, the link speed is low

D.

Flow rate limit configurationd

Question # 82

In the indoor BYOD scene, which of the following is the edge RSSI value of the key area?

A.

-45dBm

B.

-55dBm

C.

-65dBm

D.

-75dBm

Question # 83

The outdoor bridge backhaul needs to focus on confirming the installation of the AP at the node and paying attention to the transmission path between the nodes.

What is the correct statement about leaf nodes, aggregation nodes, and transmission paths?

A.

If the leaf node needs to be used for coverage, it is necessary to pay attention to the outdoor coverage of the survey.

B.

If there are multiple aggregation points, you need to confirm the location of each aggregation point. Each aggregation point also needs to confirm the AP installation location and power supply mode.

C.

There should be no obstructions or distances between the convergence points and leaf nodes. There are allowed between the relay nodes and the convergence points, relay nodes and leaf points.

Obstacle obstruction

D.

The transmission path is the path between the stations. In the site survey, it is necessary to confirm the distance between the connected nodes. The PMP mode needs to confirm the most between the links.

large angle

Question # 84

When using omnidirectional antenna coverage outside the WLAN, it is recommended to hang the antenna higher than 12m to avoid tree blockage.

A.

True

B.

False