You'll find that our INTE exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these INTE sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Supply Management Integration practice test comfortably within the allotted time.

Question # 11

A chemical supply company creates a new liquid chemical product which must be shipped by tanker truck. The new chemical is expected to constitute 10% of the firm’s sales over the next five years. The company ' s other sales are all solid powder chemicals. Given these circumstances, which of the following will be the MOST cost effective method for the company to ship the new product’

A.

Purchase a fleet of tanker trucks at a discounted price

B.

Purchase a single tanker truck initially, buying more trucks as sales increase

C.

Market only to customers who will pay for their own transportation

D.

Engage a 3PL liquid transport company provider

Question # 12

Selection of a supplier takes place during which of the following phases of the project management process?

A.

Project planning

B.

Project initiation

C.

Project monitoring and control

D.

Project execution

Question # 13

XYZ, Inc. has experienced a significant increase in the number of expedited orders with a key supplier over the last few months. In this situation, XYZ should

A.

raise the reorder point level of the products purchased from the supplier, so that XYZ will not be affected by any stock shortages

B.

request that the supplier offer a discount on its products, as the expedited requests are a financial burden

C.

contact a freight forwarder and sign a priority shipping agreement, so that XYZ can secure the expedited services

D.

determine the reasons for the ongoing expedited orders, identify the root cause, and take corrective action

Question # 14

Which of the following is the BEST reason to use Monte Carlo simu-lations to improve a forecast7

A.

To create a forecast that is accurate but has a wider distribution of potential outcomes

B.

To provide a single correct forecast that removes uncertainty

C.

To increase confidence in the forecast by reducing uncertainty

D.

To simulate potential outcomes and accept the resulting forecast without question

Question # 15

An ERP purchasing module indicates a gross requirement of 100 units for part number A123. There is an open purchase order for 55 units. The item master for this supplier shows an order lot size of 30 units each. In this situation, how many units of this part will the exception report indicate should be ordered7

A.

60

B.

100

C.

45

D.

30

Question # 16

A product has the following characteristics:

COGS $1,000,000

Starting Inventory 20,000

Ending Inventory 10,000

What is the inventory turnover of this item’

A.

The product will turn 100 times.

B.

The product will turn 33.3 times.

C.

The product will tum 50 times.

D.

The product will tum 66.7 times.

Question # 17

FGH, Inc., a specialty construction company located in Italy, orders bulky customized sound equipment from a sole-source supplier in Asia. The equipment is to be installed in a new auditorium that FGH is constructing. Failure to complete the project in time for its scheduled opening will subject FGH to penalties. FGH receives notice from the supplier that the equipment is packaged and ready to ship as planned via ocean freight but that an impending storm may cause delays. FGH needs to stay within budget. In this situation, which of following is the BEST course of action for FGH to take?

A.

Wait until the storm ' s path can be predicted more accurately

B.

Evaluate options for a multimodal shipment

C.

Arrange for immediate air freight of the equipment

D.

Use ocean freight after the storm subsides

Question # 18

Which of the following refers to a procedure whereby data are collected and compared to requirements in order to make an acceptance decision?

A.

Process mapping

B.

Inspection

C.

Internal audit

D.

Peer review

Question # 19

XYZ Company is a manufacturer that buys raw materials from Supplier A. In the past several years, Supplier A has experienced increasingly unpredictable order patterns from XYZ, which has necessitated it carry more inventory as safety stock. A meeting with XYZ reveals that this is because XYZ frequently stocks out of items its upstream customers require, and thus orders more than it needs in order to ensure that it is covered. Which of the following BEST describes the problem within this supply chain?

A.

Growth stage in a product cycle

B.

Risk transfer

C.

Fluctuating lead times

D.

Bullwhip effect

Question # 20

A manufacturer receives notice from one of its largest customers stating that, from this point on, it will only accept environmentally friendly boxes for packaging. The manufacturer checks the remaining packaging in its inventory and finds that it still has over six months ' worth of boxes that are not made of environmentally-friendly materials. These boxes are custom-designed and cannot be returned to the packaging material supplier. In this situation, the manufacturer would be BEST served by doing which of the following?

A.

Disposing of the existing boxes and switching to environmentally-friendly materials

B.

Explaining the situation to the customer and offering the products in the existing boxes at a discounted price

C.

Negotiating a grace period with the customer to allow a gradual switch from the existing design to the new one

D.

Using the leftover boxes for internal purposes within the organization