You'll find that our 1z0-1075-24 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these 1z0-1075-24 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Oracle Manufacturing Cloud 2024 Implementation Professional practice test comfortably within the allotted time.
A manufacturing plant works in two shifts of eight hours each. A Manufacturing user wants four units of a work center resource, R1, to be available during nonworking time, outside the regular shift on a particularday.
Which is the correct sequence of steps to create a resource exception on the Manage Work Center Resource Calendar page?
A manufacturing plant has two shifts of eight hours each for the work center WCI: day shift and night shift. You associate four units each of the resources R1, R2, R3, and R4 to WCI. The customer wants to assign ail units of R2 available for day and night shift.
What is the correct sequence of steps to achieve this?
A Plant Manager bought several machines for their ABC manufacturing plant. The plant is set up with a separate cost element set, ABC, in Manufacturing Cloud.
How must the Plant Manager configure these machines so that they are costed to the work order for which operations are performed on them?
You create a work order, in which some of the operations have components with the Push supply type. While reporting material consumption on the Report Material Transaction page, you want the Push components to default whenever the operator selects Show Components.
Which setup task must you perform in the Manage Plant Parameters section to achieve this?
To help ensure compliance with the US Code of Federal Regulations (21 CFR Part 11), your client wants to enable audit trail for manufacturing work definitions and standard operations.
Which is NOT included in the audit trail for standard operations such as creation, update, and deletion?
The pick release of a project work order creates movement requests with the project and the task from the work order.
Which statement is NOT true about this?
You are defining a standard operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
Which setup task must you perform to achieve this?