Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Oracle Manufacturing Cloud 2024 Implementation Professional

Last Update 6 days ago Total Questions : 50

The Oracle Manufacturing Cloud 2024 Implementation Professional content is now fully updated, with all current exam questions added 6 days ago. Deciding to include 1z0-1075-24 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our 1z0-1075-24 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these 1z0-1075-24 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Oracle Manufacturing Cloud 2024 Implementation Professional practice test comfortably within the allotted time.

Question # 4

A manufacturing plant works in two shifts of eight hours each. A Manufacturing user wants four units of a work center resource, R1, to be available during nonworking time, outside the regular shift on a particularday.

Which is the correct sequence of steps to create a resource exception on the Manage Work Center Resource Calendar page?

A.

Click Inside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource dropdown list > Enter 4 in Default Units Available.

B.

Click inside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration Fields > Go to the Resource Availability region > Populate A units in the Default Availability column.

C.

Click outside the existing shift time on a specific date > Go to the Actions menu > Select Create Resource Exception > Populate the Start and Duration fields > Go to the Resource Availability and Overrides region > Populate 4 units in the Availability Override column.

D.

Click outside the existing shift time on a specific date > Go to the Create Work Center page > Click the Resource Availability tab > Click the Add icon > Select R1 from the Resource drop-

Question # 5

A manufacturing plant has two shifts of eight hours each for the work center WCI: day shift and night shift. You associate four units each of the resources R1, R2, R3, and R4 to WCI. The customer wants to assign ail units of R2 available for day and night shift.

What is the correct sequence of steps to achieve this?

A.

Associate R2 with WC1 > Select the Available 24 Hours check box > Go to the Resource Availability region > Enter 4in the Day Shift column > Enter 4 In the Night Shift column.

B.

Associate R2 with WC1> Deselect the Available 24 Hours check box > Go to the Resource Availability region > Enter 4in the Day Shift column > Enter 4 In the Night Shift column.

C.

Associate R2 with WCI > Select the Available 24 Hours check box > Go to the Resource Availability region > Enter 2 in the Day Shift column > Enter 2 in the Night Shift column.

D.

Associate R2 with WCI > Deselect the Available 24 Hours check box > Go to the Resource Availability region > Enter 2 In the Day Shift column > Enter 2 In the Night Shift column.

Question # 6

A Plant Manager bought several machines for their ABC manufacturing plant. The plant is set up with a separate cost element set, ABC, in Manufacturing Cloud.

How must the Plant Manager configure these machines so that they are costed to the work order for which operations are performed on them?

A.

Set up the machines with a cost element type of "Resource" by selecting Cost Element Set Common.

B.

Set up the machines with a cost element type of "Overhead" by selecting Cost Element Set ABC.

C.

Set up the machines with a cost element type of "Resource" by selecting Cost Element Set ABC.

D.

Set up the machines with a cost element type of "Overhead" by selecting Cost Element Set Common.

Question # 7

You create a work order, in which some of the operations have components with the Push supply type. While reporting material consumption on the Report Material Transaction page, you want the Push components to default whenever the operator selects Show Components.

Which setup task must you perform in the Manage Plant Parameters section to achieve this?

A.

Set Default Transaction Mode to Entered and Default Transaction Quantity to Work Definition.

B.

Set Default Transaction Mode to Work Definition.

C.

Set Default Transaction Mode to AIL

D.

Set Default Transaction Mode to Entered.

Question # 8

To help ensure compliance with the US Code of Federal Regulations (21 CFR Part 11), your client wants to enable audit trail for manufacturing work definitions and standard operations.

Which is NOT included in the audit trail for standard operations such as creation, update, and deletion?

A.

Work definition header and version attributes

B.

Descriptive flexfields (OFFs) at any level

C.

Item structure component attributes referenced from Product Information Management(PIM)

D.

Attachments at any level

E.

Operation resources. Including alternate resources

Question # 9

The pick release of a project work order creates movement requests with the project and the task from the work order.

Which statement is NOT true about this?

A.

The expenditure type, expenditure date, and expenditure organization are derived when the work-ln-process material issue or work-in-process material pick transactions are interfaced to Costing.

B.

The expenditure type for the item is derived based on the Default Expenditure Type attribute in Inventory Management. The picks for the work order ore grouped by project costing, project, and task using pick slip grouping rules.

C.

The expenditure type and the expenditure organization from the work order are referenced onto the shop floor movement requests.

D.

The expenditure type and the expenditure organization from the work order are not referenced onto the shop floor movement requests.

Question # 10

You are defining a standard operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.

Which setup task must you perform to achieve this?

A.

Deselect the Count Point check box while defining the standard operation.

B.

Select the Automatically Transact check box while defining the standard operation.

C.

Select the Count Point check box while defining the standard operation.

D.

Ensure that the Charge Type of the resource is Automatic.

Go to page: