You'll find that our AD0-E911 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these AD0-E911 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Adobe Workfront Project Manager Certified Professional practice test comfortably within the allotted time.

Question # 21

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

A.

Utilization section

B.

Hours tab

C.

Finance section

Question # 22

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads " Project cannot be marked Complete if there are open issues and tasks that are not complete. " How can the Project Owner determine which tasks are incomplete?

A.

There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

B.

There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.

C.

The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

Question # 23

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

A.

Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.

B.

Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.

C.

In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.

Question # 24

What are two ways to associate milestone steps to tasks? (Choose two.)

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Question # 25

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Question # 26

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

A.

Update the project status.

B.

Recalculate the project timeline.

C.

Update the project baseline.

Question # 27

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

A.

Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A ' s access level.

B.

Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.

C.

Share the program with Program Manager A with Manage access and remove Program Manager A ' s Manage access on the portfolio.

Question # 28

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

A.

The primary task owner has time off logged in Workfront.

B.

The team needs to review the task before confirming the start date.

C.

The task duration and planned hours are set to begin on Friday.