You'll find that our AgilePM-Foundation exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these AgilePM-Foundation sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Agile Project Management (AgilePM v3) Foundation Exam v3 update practice test comfortably within the allotted time.

Question # 21

When assessing the impact and severity of options on how to handle change, not all costs are financial. What type of cost is reflected in the downtime experienced while staff are trained to use a new process or system?

A.

Productivity dip.

B.

Safety & Wellbeing.

C.

Reputational.

D.

Opportunity.

Question # 22

Identify the missing words in the following statement.

In projects, especially when using non-agile methods, governance often seems to focus on [ ? ] .

A.

Process and tools

B.

Comprehensive documentation

C.

Contract negotiation

D.

Following a plan

Question # 23

Identify the missing words in the following sentence.

AgilePM planning concepts help keep [?] without excessive bureaucracy.

A.

Scrum work progressing

B.

projects on track

C.

Backlog items arranged

D.

commitments in place

Question # 24

According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?

A.

During evolutionary development

B.

At the start of the project

C.

When the Business Advisor is available

D.

Whenever the level of solution quality is known.

Question # 25

How does DSDM differ from most other Agile approaches?

A.

It focuses on the entire project lifecycle

B.

It focuses on the development of products

C.

It focuses on the delivery of products

D.

It focuses on the collaborative working of teams

Question # 26

To show the change is on track, Change Managers must define and agree on a set of measures that reflect the desired outcomes. What are these often called?

A.

Islands of stability.

B.

Key performance indicators.

C.

Incremental milestones.

D.

Transition tranches.

Question # 27

What is defined as " The means by which an organization increases involvement of its employees and other stakeholders with organizational change " ?

A.

Engagement.

B.

Change Agent.

C.

Sponsor.

D.

Line Leader.

Question # 28

In combination with Scrum, what does AgilePM provide for Scrum Masters?

A.

An opportunity to serve the organization by leading, training, and coaching the organization in its Scrum adoption

B.

A set of practices, tools, techniques, and methods to enhance the use of Scrum

C.

A framework that helps teams generate value through adaptive solutions for complex problems

D.

An incremental and evolutionary approach to product development that evolves with time

Question # 29

What DSDM Principles requires the transparency of all work being performed by the team?

A.

Principle 1- Focus on the Business Need

B.

Principle 1 – Build incrementally from Firm Foundations

C.

Principle 66-Develop iteratively

D.

Principle 8-Demonstrate Control

Question # 30

What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?

A.

Business Analyst

B.

Workshop Facilitator

C.

Business Ambassador

D.

Business Visionary