Summer Sale Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ex2p65

Exact2Pass Menu

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing

Last Update 23 hours ago Total Questions : 80

The SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing content is now fully updated, with all current exam questions added 23 hours ago. Deciding to include C_TS422_2022 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our C_TS422_2022 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these C_TS422_2022 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing practice test comfortably within the allotted time.

Question # 4

What can you use heuristics in Advanced Planning (PP/DS) for?

A.

To optimize costs and times in production plans

B.

To solve planning problems for defined objects

C.

To automate material movements in material staging

D.

To set default values in production master data

Question # 5

What does a line hierarchy in repetitive manufacturing represent?

A.

A production line with more than one work center

B.

A production line with prioritized work centers

C.

A production line with a parallel sequence in the routing

D.

A production line with an alternative sequence in the routing

Question # 6

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

A.

Create an object selection variant for priority-category-related alerts.

B.

Assign the alert profile to the overall profile.

C.

Create an object selection variant for production-planning-related alerts.

D.

Assign the overall profile to the authorization profile.

Question # 7

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched, how does the insertion take place?

A.

The new operation is inserted at the desired time; the previous dispatched operation is moved forward.

B.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward

C.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

D.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

Question # 8

How can you characterize dependent requirements in material requirements planning?

Note: There are 2 correct answers to this question.

A.

They are created with exact times in Advanced Planning.

B.

They are created when an independent requirement is created for the finished product.

C.

They are created on assembly level during the planning run.

D.

They are only created for multilevel bill of material (BOM) structures

Question # 9

Which master data object governs the relationship between supply source and demand source in the Kanban process?

A.

Replenishment strategy

B.

Production supply area

C.

Control cycle

D.

Rate routing

Question # 10

Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

A.

Routing

B.

Work Center

C.

Bill of material (BOM)

D.

Material Master

Go to page: