Last Update 4 hours ago Total Questions : 140
The Certified Contract Manager content is now fully updated, with all current exam questions added 4 hours ago. Deciding to include CCM practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our CCM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Contract Manager practice test comfortably within the allotted time.
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)
Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?
(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)
The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?
Choose all of the correct answers (multiple possibilities):
(You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:
(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer’s Requirements.
(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).
What is your determination for the Contractor?)
In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?
Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?
Choose all of the correct answers (multiple possibilities)
(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))
Which of the following form a Contractor ' s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
