Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Contract Manager

Last Update 4 hours ago Total Questions : 140

The Certified Contract Manager content is now fully updated, with all current exam questions added 4 hours ago. Deciding to include CCM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CCM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Contract Manager practice test comfortably within the allotted time.

Question # 11

In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)

A.

The Engineer

B.

The Engineer ' s Resident Engineer

C.

The Employer

D.

The Employer ' s Representative

Question # 12

Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?

A.

" The Employer obtains the best value for money " AND " Disputes should be avoided to the extent achievable. "

B.

" Only the Employer should be the one to obtain the best value for money " AND " The Contractor/Subcontractor is paid adequately and timely in accordance with the Contract to maintain its cash flow. "

C.

" The Contractor/Subcontractor is paid adequately and in a timely manner in accordance with the Contract to maintain its cash flow " AND " The terms of the Contract are comprehensive and fair to primarily the Employer " .

D.

" The Contractor should take advantage of its bargaining power every time possible " AND " Disputes are avoided to the extent achievable, minimised when they do arise, and resolved efficiently. "

Question # 13

(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)

A.

True

B.

False

Question # 14

The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?

Choose all of the correct answers (multiple possibilities):

A.

The advance payment is to help the Contractor to finance some of its early cost and expenditure until it becomes entitled to first (non-interim) payment.

B.

The advance payment reflects the amount of works the Contractor has already performed up to the moment such advance payment is performed.

C.

Under the General Conditions, the amount of advance payment is to be paid in full by the Employer through one instalment.

D.

Under the General Conditions, the advance payment will be repaid by deducting all amounts from invoices until the entire advance payment is repaid.

Question # 15

(You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project under FIDIC Silver Book (edition 2017). The Contractor submits two claims:

(1) USD 200,000 for additional costs due to an error in national piling standard NTS-PW-01 referenced in the Employer’s Requirements.

(2) USD 300,000 for constructing an additional flood wall due to incorrect hydrological data in Site Data (water level miscalculated).

What is your determination for the Contractor?)

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer ' s Requirements only.

C.

The Contractor is entitled to the Claim for the additional floodwall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both claims.

Question # 16

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

A.

When the works are simple and of short duration.

B.

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.

C.

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.

D.

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.

Question # 17

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor ' s items on the Site.

D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor ' s items on the Site if the Contractor fails, as this is the Contractor ' s obligation.

Question # 18

(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))

A.

The Bill of Quantities

B.

The Specifications

C.

The Breakdown of Lump-Sum

D.

Schedule of Subcontractors

E.

The form of Contract Agreement

Question # 19

Which of the following form a Contractor ' s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

Question # 20

Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?

A.

A declaration of joint and several liability

B.

A bank guarantee

C.

A surety bond

D.

A parent company guarantee

Go to page: