Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Contract Manager

Last Update 4 hours ago Total Questions : 140

The Certified Contract Manager content is now fully updated, with all current exam questions added 4 hours ago. Deciding to include CCM practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CCM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Contract Manager practice test comfortably within the allotted time.

Question # 21

Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?

Choose all of the correct answers (multiple possibilities).

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that " a Variation shall " be executed on a daywork basis.

Question # 22

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Question # 23

Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

A.

A description of the varied work.

B.

A description of the proposed design.

C.

Details of the resources and methods to be adopted by the Contractor.

D.

A Programme for execution of the varied work.

Question # 24

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

A.

True

B.

False

Question # 25

Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?

A.

Amending clauses, supposedly in the interest of the Employer, immediately nullifies all the advantages of standardization, and almost invariably introduces conflicting or ambiguous requirements on the parties, and often causes mistrust between them.

B.

The FIDIC Books provide people who draft contracts with great examples on how to draft a good contract model. Furthermore, arrangements from Red, Yellow and Silver Books can be easily mixed to get a good fit for a specific project.

C.

The Form of Contract is chosen by the Contractor and imposed by him on the Employer, who tenders on that basis.

D.

People who draft contracts should, when preparing a new contract, always start with the question: where do I want to lay the most risks between Employer and Contractor, and does the Employer has the budget to reward Contractors with a high risk apatite?

Question # 26

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

A.

Red Book

B.

Yellow Book

C.

Silver Book

D.

All the above

Question # 27

(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

A.

The Employer shall give a Notice to the Engineer, describing the event or circumstance giving rise to the cost, loss, delay or extension of the Defects Notification Period for which the Claim is made.

B.

The Notice shall be given to the Engineer, as soon as practicable, and no later than 28 days after the claiming Party became aware, or should have become aware, of the event or circumstance.

C.

A Notice from the Employer is not required in order to give a Notice to the Engineer for services requested by the Contractor.

D.

The Notice given by the Employer must also include the legal or contractual basis of the claim, including the clause of the Contract under which it is made.

Question # 28

Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)

A.

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.

B.

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.

C.

The Contractor cannot proceed in accordance with the Programme.

D.

The Engineer is deemed to have no objection to use the revised programme submitted by the Contractor, for the Works.

Question # 29

(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)

A.

You compliment the supervisor and ask him to excavate further and personally deliver the treasure to a university. No extension of time is granted.

B.

You thank the supervisor, secure the Site, instruct guarding measures, inform the Employer and authorities, and issue a Variation to cover the costs of protection measures.

C.

You inform the supervisor that a formal written notice under Sub-Clause 4.24 is required and no further instruction can be given until then.

D.

You instruct the supervisor to cover the finding and resume the Works immediately, and make a determination later.

Question # 30

(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))

A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.

Go to page: