Last Update 4 hours ago Total Questions : 140
The Certified Contract Manager content is now fully updated, with all current exam questions added 4 hours ago. Deciding to include CCM practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our CCM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Contract Manager practice test comfortably within the allotted time.
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?
Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)
(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)
(During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers discovers a possible ancient treasure on the Site. The supervisor stops the Works, secures the Site, and informs the Engineer. How should the Engineer react?)
(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))
