You'll find that our CDT exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CDT sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Construction Documents Technologist practice test comfortably within the allotted time.

Question # 11

Peer reviews or internal reviews of completed documents are examples of what?

A.

Quality control

B.

Commissioning

C.

Quality assurance

D.

Construction administration

Question # 12

Which document directly modifies the requirements of the general conditions?

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Question # 13

For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?

A.

Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.

B.

Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.

C.

Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.

D.

Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).

Question # 14

In what project stage does the architect/engineer obtain and document the owner ' s decisions about specific products and systems?

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Question # 15

Which of the following is a scaled view?

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Question # 16

When does a project reach substantial completion?

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor ' s final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Question # 17

The dual nature of design includes what two elements?

A.

Site and building

B.

Aesthetic and technical

C.

Programming and planning

D.

Innovation and authenticity

Question # 18

Which of the following should be avoided when specifying warranties?

A.

Requiring or permitting a warranty that strengthens the owner ' s rights

B.

Requiring minimum warranty coverage available for a particular product

C.

Including language to require warranties extending beyond the contractor ' s one-year correction period

D.

Relying on a warranty as a substitute for thorough investigation of a product and its manufacturer

Question # 19

What four considerations are included in site selection programming?

A.

Use, space, funds, date

B.

Function, form, economy, time

C.

Purpose, shape, cost, schedule

D.

Goal, condition, budget, calendar

Question # 20

If the contractor discovers that a part of the contract documents is in violation of the building code, what should the contractor do?

A.

Notify the architect/engineer in writing

B.

Proceed with the work in accordance with the contract documents

C.

Request a variance from the building authority

D.

Stop all work until the issue is resolved