Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Construction Documents Technologist

Last Update 14 hours ago Total Questions : 120

The Construction Documents Technologist content is now fully updated, with all current exam questions added 14 hours ago. Deciding to include CDT practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CDT exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CDT sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Construction Documents Technologist practice test comfortably within the allotted time.

Question # 1

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Question # 2

Where can you typically find requirements for temporary toilet facilities?

A.

Supplementary Conditions

B.

Division 22 – Plumbing

C.

The Owner–Contractor Agreement

D.

Division 01 – General Requirements

Question # 3

Where are the limits of the work of each alternate defined?

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Question # 4

Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?

A.

Conformed set

B.

Record set

C.

Change order log

D.

Request for information documents

Question # 5

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Question # 6

What must a specification section indicate?

A.

The building trade that will perform the installation

B.

The likely anticipated cost of the specified product

C.

The interrelationships that exist between the work of this section and the entire project

D.

How the owner will be compensated if the specified item is unavailable

Question # 7

Under SectionFormat®, where would the Article " Manufacturers " be found?

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Question # 8

Who has the right to stop the work if hazardous materials are encountered during the construction?

A.

Architect/engineer

B.

Contractor

C.

Stakeholders

D.

Facility manager

Question # 9

Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?

A.

Mobilization meeting

B.

Preconstruction meeting

C.

Prebid meeting

D.

Coordination meeting

Question # 10

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Go to page: