You'll find that our CFM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CFM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Facility Manager practice test comfortably within the allotted time.

Question # 61

A facility manager may be responsible for status reviews on projects. Why are status reviews important and valuable?

A.

To identify reasons for variance from baseline and ensure responsible parties are identified

B.

To keep accurate records of all project tasks regardless of variation from baseline

C.

To identify issues and corrective actions to ensure the project remains on track

D.

To keep the project team aware of others’ progress on a project

Question # 62

When a facility manager initiates an office relocation project, which item is completed first?

A.

Develop the project program.

B.

Secure the budget.

C.

Develop the project charter.

D.

Secure the new lease.

Question # 63

Employees in a research laboratory have been reporting an increased amount of static electricity charges that are negatively impacting their ability to perform certain experiments. What indoor air quality system should be assessed?

A.

Heating

B.

Air circulation

C.

Humidification

D.

Cooling

Question # 64

What is your role as a Facility Manager in developing an emergency preparedness plan that ensures organizational success ?

A.

Ensure that all of the materials and equipment are on hand to respond.

B.

Ensure that communication devices are in place to respond.

C.

Create an emergency plan and ensure that employees are trained to respond.

Question # 65

What action should you take to address the premature aging of a roofing membrane?

A.

Plan and budget for replacing the roof system as soon as possible to prevent degradation or damage to other building components and contents.

B.

File a warranty claim with the manufacturer based on the membrane’s failure to reach its expected service life.

C.

Extend the service life of the roofing membrane with patches and repairs as leaks are detected until the full expected service life of the membrane is realized.

D.

Explain to occupants that water infiltration is expected in any facility and it will be addressed as an ongoing maintenance and repair item.

Question # 66

What is MOST important when creating a facility culture of safety and security?

A.

Relying on a risks and hazards assessment after an incident has occurred

B.

Evaluating potential hazards and implementing corrective action, if needed

C.

Involving only senior management in the risk assessment

D.

Focusing exclusively on near misses

Question # 67

You are planning a landscaping project in a densely populated area. What considerations are needed for the community outside your property?

A.

Choose alternative energy sources to power outdoor lighting and security stations, decrease costs to your facility, and provide energy back to the grid, which will bring energy costs down to the neighboring community.

B.

Ensure that lights and basic security sounds (e.g., beeping noises at an outdoor security station) are not intrusive on daily living, but that they may also be used to alert the neighborhood, when such alerts are appropriate and of value (e.g., in an emergency).

C.

Use the brightest possible lights and loudest sounds (e.g., sirens) to prevent security issues at night to support the community in decreasing crime in that area and announcing emergency situations.

D.

Provide security staff to walk the perimeter of your property, checking for damaged lights or other security issues while maintaining communication with a dispatcher for emergencies while keeping a low profile in the neighboring community.

Question # 68

What is the most important factor to consider when upgrading the Building Management System (BMS)?

A.

The provider indicates the software version is obsolete

B.

Requirement to automate FM tasks

C.

An upgraded version is now available from the manufacturer

D.

Additional metrics are required for management reporting

Question # 69

What approach best promotes indoor environmental quality and health ?

A.

The maintenance and monitoring of acceptable levels of ambiance, safety, lighting, and environmental wellness.

B.

The strategies and systems used to provide occupants with a healthy, productive, comfortable, and safe workplace.

C.

The measurement and monitoring of hazardous conditions that pose threats to health, the environment, and the quality of life.

Question # 70

A new department manager is not clear on the services provided by the facility management department and is often negative about facility management while at management meetings. How should a facility manager address the customer ' s expectations?

A.

Request that the manager refrain from complaints at this meeting as it is not the appropriate venue.

B.

Request that the other managers have a discussion with him about office protocol.

C.

Request that he read his service level agreement.

D.

Review the customer service level agreement to determine a mutually agreed performance standard.