You'll find that our PSK-I exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSK-I sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Professional Scrum with Kanban (PSK 1) Exam practice test comfortably within the allotted time.

Question # 4

Who is in the best position to decide if Kanban may be a valuable complementary practice for a Scrum Team?

(choose the best answer)

A.

The Scrum Master.

B.

The Scrum Team.

C.

The Developers.

D.

The Product Owner

E.

Stakeholders

Question # 5

How do Work in Progress (WIP) Limits relate to self-management?

(choose the best two answers)

A.

WIP Limits inhibit self-management since they limit the team's autonomy to pull

work.

B.

WIP Limits provide a boundary/container in which the Scrum Team self-

manages.

C.

A Scrum Master defines a WIP Limit to help the Scrum Team self-manage.

D.

As part of self-managing, Scrum Teams figure out their own WIP Limits.

Question # 6

Which statements best describe the purpose of a Scrum Team’s Definition of Workflow?

(Choose the best three answers)

A.

It defines how value flows through the system.

B.

It helps Service Request Manager track the percent completeness of a work item.

C.

It provides a mutual understanding of when the work is considered to be started and finished.

D.

It makes handoff policies explicit by defining clear quality gates between the development stages.

E.

It is used as a checklist of all the states that every work item should go through before it is considered to be done.

F.

It creates transparency over the Work in Progress (WIP) limiting rules.

Question # 7

What is the best chart to determine when a single item that has not been started will be

finished?

(choose the best answer)

A.

Cycle Time scatterplot.

B.

Cumulative Flow diagram (CFD).

C.

Throughput run chart.

D.

WIP Aging chart.

Question # 8

When using Kanban in a Scrum environment, some resistance toward introducing Work in Progress (WIP) Limits may be encountered. What is an alternative to introducing WIP Limits in Kanban?

A.

Using Kanban boards that improve visualization and enhance communication.

B.

None, Professional Scrum with Kanban cannot be used without explicit WIP Limits.

C.

Building a strong team identity using Squads and tribes.

D.

Conducting Daily Stand-Up meetings that control not having too much work.

Question # 9

Which of the following are leading indicator metrics?

(choose the best two answers)

A.

Cycle Time.

B.

Service Level Expectation.

C.

Work in Progress.

D.

Work Item Aging.

E.

Monte Carlo.

Question # 10

A cumulative flow diagram can show you:

(Choose the best two answers)

A.

The total amount of Work in Progress (WIP) for a specific date.

B.

The average Throughput for a specific date range.

C.

The Cycle Time for an item that completed on a specific date.

D.

The exact average Cycle Time for all items completed on a specific date.