Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Professional Scrum Master II

Last Update 1 hour ago Total Questions : 74

The Professional Scrum Master II content is now fully updated, with all current exam questions added 1 hour ago. Deciding to include PSM-II practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PSM-II exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSM-II sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Professional Scrum Master II practice test comfortably within the allotted time.

Question # 4

You have just been hired as a Scrum Master by a company new to Scrum. The company wants to use Scrum to build a new product that was conceived by the product management department. You will be the Scrum Master of two new teams that will build a first version of the product. The product management department assigns two new Product Owners, but wants more advice about the required participation with the new Scrum Teams. Which two suggestions would you offer?

(choose the best two answers)

A.

Having one Product Owner will improve the clarity of accountability to the teams and to the product management department.

B.

Two Product Owners are necessary, one for each Scrum Team. They report to an overarching chief Product Owner.

C.

Each Scrum Team has a separate Product Backlog, holding each team's assigned requirements.

D.

A single Product Backlog should be maintained holding all requirements for the new product.

Question # 5

You are the Scrum Master of a Scrum Team that has one Developer who disagrees with team decisions. Their disagreements are becoming disruptive and slowing progress. The Developer often returns to earlier team decisions and re-opens the issue.

What are two ways to go about this problem?

(choose the best two answers)

A.

You organize an offsite team building activity to establish a foundation of trust. You observe whether the problem persists after the offsite activity.

B.

You take the Developer aside to express your concern over their disagreements

and tell them to act as a team player and to comply with the team's decision.

C.

At the Sprint Retrospective you observe whether the topic is raised. If it does not happen, you check on how comfortable everybody is with the way team

decisions are made.

D.

You go to the Human Resources department and ask them to have a

conversation with the Developer based on the issues the team has raised.

E.

To every team member expressing this concern you suggest raising this with the full team. You offer to help initiate the conversation but not to resolve the concern yourself.

Question # 6

Eight months ago your company started developing a new product consisting ot several major components. You are the Scrum Master on the team building the "core" component of the product; your component also integrates all the other components.

The Scrum Teams work in monthly Sprints, and the team has forecast that it will deliver the integrated product in three Sprints. Recently the team's progress slowed because of changes to the other components that they integrate. The program manager is extremely upset when they find out that the team will need two more Sprints. The project managers of the other components confirm their adherence to the original forecast.

As a Scrum Master, what could you do to help the Product Owner?

(choose the best answer)

A.

You calculate how many additional developers it would take to increase velocity to make the original date. You inform the program manager of the additional budget for these developers. This would then allow meeting the original forecast

B.

You remove all items from the Product Backlog tor which development is forecast to be beyond the expected date.

C.

You suggest working with the program manager and the project managers of the

other components on the ordering and the value of your open Product Backlog items to redefine the possible delivery date.

D.

You lengthen your Sprints to accommodate the delays.

Question # 7

How does the Scrum Master serve the Scrum Team?

(choose the best two answers)

A.

The Scrum Master coaches the Scrum Team and the organization how to work empirically.

B.

The Scrum Master resolves every impediment that the Developers run into

C.

The Scrum Master never intervenes in matters of the Scrum Team, but allows

them to maximize their autonomy and freedom.

D.

The Scrum Master facilitates Scrum events as requested or needed

Question # 8

Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are primarily working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.

Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.

What might explain why this Scrum Team is struggling to craft a Sprint Goal?

(choose all that apply)

A.

Scrum might not be the best framework for the work done by this team.

B.

The Sprints are too long.

C.

The Product Owner does not have the mandate to make decisions about items on the Product Backlog nor their ordering.

D.

The Product Owner is not communicating the Product Goal that they want to achieve in upcoming Sprints.

E.

The Scrum Team is too big.

Question # 9

In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient tor going to production In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions tor the Scrum Master to take?

(choose the best two answers)

A.

Agree and praise the Developers for their nard work, so they are motivated to do even more in the next Sprint

B.

Facilitate a discussion on now to improve the quality to a level sufficient tor production, even it the measured velocity will drop in the next Sprint

C.

Acknowledge the nard work, but remind the Developers that they need to

improve to do even more in the next Sprint.

D.

Stress the value of working product over measured velocity.

Question # 10

A Developer from the Scrum Team is always missing the Daily Scrum. She feels that if she is doing her job well, it does not matter whether she attends or not. The other Developers on the team have not done anything about it. As the Scrum Master how should you respond to this situation?

(choose the best answer)

A.

You do not intervene. The Developers own the Daily Scrum, so they should deal with any issues with attendance.

B.

Ask the Developers, what value they get by having the Daily Scrum with all team members present and what might go wrong if all Developers do not attend.

C.

Talk to the Developer who is missing the Daily Scrum and ask her to always attend the Daily Scrum.

D.

Teach the Developers how to deal with this situation by attending the Daily Scrum yourself.

Go to page: