Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7

Last Update 4 hours ago Total Questions : 165

The SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 content is now fully updated, with all current exam questions added 4 hours ago. Deciding to include C_TPLM22_67 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our C_TPLM22_67 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these C_TPLM22_67 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 practice test comfortably within the allotted time.

Question # 11

Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.

Which of the following costs can be planned?

There are 3 correct answers to this question.

Response:

A.

Cost element level

B.

Each material

C.

Each internal activity

D.

Internal service

Question # 12

A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?

There are 2 correct answers to this question.

Response:

A.

Define Layout Detail Screen for WBS to specify customer-specific tabs.

B.

Define Create User-Defined Fields for WBS to specify the mandatory fields.

C.

Define Field Selection for WBS to specify the mandatory fields.

D.

Define Table Settings for WBS to specify customer-specific tabs.

Question # 13

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?

Please choose the correct answer.

Response:

A.

The system status created is active.

B.

The system status master data locked is activate.

C.

You are not the responsible person for that WBS element.

D.

The confirmation exceeds the budget assigned to the WBS.

Question # 14

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?

Please choose the correct answer.

Response:

A.

Contractual management

B.

Claim management

C.

Claim Planning

D.

Variance management

Question # 15

You are using the bottom-up scheduling scenario for a project containing WBS elements and networks. This means that ...

There are 2 correct answers to this question.

Response:

A.

... basic dates of WBS elements are determined automatically.

B.

... the networks determine the schedule.

C.

... strict bottom-up planning is selected as the planning method.

D.

... forward scheduling is selected as the scheduling type.

E.

... the work breakdown structure determines the schedule.

Question # 16

Which of the following master data fields of an internally processed activity have an impact on capacity requirements? Choose the correct answers (3)

A.

Usage

B.

Work

C.

Activity type

D.

Work center

E.

Duration

Question # 17

In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?

Please choose the correct answer.

Response:

A.

Deactivate actual date consider indicator in Parameters for Network Scheduling.

B.

Deactivate the shift order indicator in Parameters for Network Scheduling.

C.

Activate the actual date consider indicator in Parameters for Network

Scheduling.

D.

Activate the shift order indicator in Parameters for Network Scheduling.

Question # 18

Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?

There are 2 correct answers to this question.

Response:

A.

WBS elements

B.

Activities

C.

Milestones

D.

Structures

Question # 19

Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?

Please choose the correct answer.

Response:

A.

Operative network

B.

Task network

C.

Standard network

D.

Internal network

Question # 20

What do you choose when creating a new network by copying an operative network?

There are 3 correct answers to this question.

Response:

A.

PS texts

B.

Relationships

C.

Milestones

D.

WBS elements

Go to page: