Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Data Centre Professional (CDCP)

Last Update 6 hours ago Total Questions : 88

The Certified Data Centre Professional (CDCP) content is now fully updated, with all current exam questions added 6 hours ago. Deciding to include CDCP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CDCP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CDCP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Data Centre Professional (CDCP) practice test comfortably within the allotted time.

Question # 11

Which one of the following is an Audible Signaling and Notification Device?

A.

Sirens

B.

Strobes

C.

Alarms

D.

Clocks

Question # 12

What factor should be considered when placing fluorescent lighting in the data centre?

A.

Fluorescent lights should not be connected to the back-up generator.

B.

Fluorescent lights should only be installed in equipment supporting areas and not in the Computer/Server room.

C.

Fluorescent lights should not be connected to the mains power supply.

D.

Fluorescent lights should not be connected to the same UPS that supports the ICT equipment.

Question # 13

What should be considered when implementing hot- or cold-aisle containment in an existing computer room?

A.

Equipment will get too hot at the rear (back) of the rack potentially resulting in more ICT hardware failures.

B.

The delta-T of the equipment will increase too much causing reliability issues.

C.

It creates potential issues with the existing fire suppression system(s).

D.

It will be more difficult to install power and network cabling in the contained area.

Question # 14

When referring to the internal mounting space in racks, equipment manufactures generally refer to standardized height of electronic modules “U” or “RU”. What is the height of 1 “U” or “RU”?

A.

19 inches (60 cm)

B.

24 inches (80 cm)

C.

1.75 inches (4.445 cm)

D.

3.5 inches (8.59 crn)

Question # 15

IP protection grades consist of two numbers.

Which levels of protection do they describe and what is the best protection?

A.

First digit; protections against the ingress of solid objects. Second digit; protection against ingress of water/fluids. The lower the number the better the level of protection.

B.

First digit; protections against the ingress of solid objects. Second digit; protection against ingress of water/fluids. The higher the number the better the level of protection.

C.

First digit; protections against the ingress of water/fluids. Second digit; protection against ingress of solid objects. The higher the number the better the level of protection.

D.

First digit; protections against the ingress of water/fluids. Second digit; protection against ingress of solid objects. The lower the number the better the level of protection.

Question # 16

What is the best practice for cutting holes in the raised floor tile?

A.

Anywhere as data centre tiles are designed to allow cut-outs anywhere.

B.

Draw a cross on the tile and when making a cut-out do not touch a line and avoid the corners.

C.

Draw a line in the middle of the tile and never touch the line when making the cut.

D.

Cut the tiles at the corner so the pedestals can be used as a vertical cable manager.

Question # 17

Measuring " Business Values " begins first with .

A.

Physical Infrastructure

B.

Topology

C.

Network

D.

Budget

Question # 18

Which one of the following is an Objective of Data Center Fire Protection?

A.

Information

B.

Representation

C.

Depression

D.

Suppression

Question # 19

Does unplanned downtime of a data centre have an impact on the business results?

A.

No, because data centres operate independently from the business.

B.

No, unplanned data centre downtime is already financially planned for in the yearly budget planning process.

C.

Yes, data centre downtime can result in business downtime.

D.

Yes, but data centre downtime only impacts the airline industry.

Question # 20

By what are magnetic fields of the type ' H ' or ' B ' created?

A.

Magnetic fields are created when an electric current flows; the greater the current, the stronger the magnetic field.

B.

Magnetic fields are created by the magnetic flux of the earth which varies per month.

C.

Magnetic fields are created by voltage; the greater the voltage, the stronger the magnetic field.

D.

Magnetic fields are created when there is a high level of common mode noise (CMN); the greater the common mode noise (CMN), the stronger the magnetic field.

Go to page: