Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Technical Examination - Civil Engineering Technology C.E.T

Last Update 17 hours ago Total Questions : 110

The Technical Examination - Civil Engineering Technology C.E.T content is now fully updated, with all current exam questions added 17 hours ago. Deciding to include Civil-Engineering-Technology practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our Civil-Engineering-Technology exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Civil-Engineering-Technology sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Technical Examination - Civil Engineering Technology C.E.T practice test comfortably within the allotted time.

Question # 11

A civil engineering technologist is performing a concrete test on a site. What minimum number of cylinders should the technologist make?

A.

One

B.

Three

C.

Four

D.

Five

Question # 12

When should soil compaction tests be completed?

A.

During pre-design

B.

During backfill of a trench

C.

During record drawing completion

D.

After paving operations

Question # 13

A civil engineering technologist is providing culvert location staking in the field for a project. What information is placed on the survey stakes?

A.

Culvert top-of-pipe elevations and diameter

B.

Culvert material type and thickness

C.

Culvert manufacturer’s name and material

D.

Culvert invert elevations and offset to end of culvert

Question # 14

What is a silt fence used for?

A.

To mark the construction limits of the project

B.

To prevent water from moving through the site

C.

To prevent the public from accessing the construction site

D.

To prevent soil from moving through the site due to erosion

Question # 15

For a land development project to be initiated, which of the following documents must be submitted to the municipality for approval?

A.

Area Structure Plan

B.

Neighbourhood Structure Plan

C.

Historical resources overview

D.

Transportation network analysis

Question # 16

For granular material, what is the typical optimum moisture content for dry densities ranging from 2100 kg/m³ to 2200 kg/m³?

A.

4–7%

B.

8–15%

C.

16–20%

D.

21–25%

Question # 17

Which soil test identifies the minimum water content at which the soil begins to crumble?

A.

Liquid limit

B.

Plastic limit

C.

Shrinkage limit

D.

Permeability limit

Question # 18

What is a typical concrete slump for a municipal sidewalk?

A.

10–50 mm

B.

25–75 mm

C.

50–100 mm

D.

80–100 mm

Question # 19

Which of the following statements best describes the for piling loads in the diagram below?

A.

It is less than .

B.

It is less than .

C.

It is less than or equal to .

D.

It is less than or equal to .

Question # 20

A civil engineering technologist who works for a structural consulting firm discovered a conflict between the design and existing site conditions during the construction stage of the project. What type of site instruction should the technologist provide to the contractor to resolve the conflict?

A.

Structural

B.

Architectural

C.

Mechanical

D.

Electrical

Go to page: