Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Technical Examination - Civil Engineering Technology C.E.T

Last Update 16 hours ago Total Questions : 110

The Technical Examination - Civil Engineering Technology C.E.T content is now fully updated, with all current exam questions added 16 hours ago. Deciding to include Civil-Engineering-Technology practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our Civil-Engineering-Technology exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Civil-Engineering-Technology sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Technical Examination - Civil Engineering Technology C.E.T practice test comfortably within the allotted time.

Question # 4

Which of the following tests would most likely be used to determine if engineered fill was placed to meet contract specifications?

A.

Sieve analysis

B.

Compaction test

C.

Triaxial compression test

D.

Moisture content check

Question # 5

If a controlled product is used, stored, handled, or manufactured at a work site, what documents should be discussed at safety meetings with workers?

A.

Material Safety Data Sheets (MSDS)

B.

Product Application Procedures

C.

Product Colour Board Samples

D.

Workplace Hazardous Materials Information System (WHMIS)

Question # 6

A geotechnical report indicates the presence of a peat layer in several boreholes. The peat layer ranges in thickness from 450 mm to 1200 mm and is found at a depth of 1.5 m below the existing grade. How should this be addressed in the project specifications that are being prepared?

A.

Advise the bidders that the peat layer is present

B.

Propose a method of stabilizing the peat layer in the specifications

C.

Include a clause stating that the peat should be removed from the area

D.

Determine the bearing strength of the peat material and include this information in the specifications

Question # 7

A surveyor is laying out the invert elevations of a storm sewer. Centre elevation is 10 m, storm pipe outside diameter is 1 m, and storm sewer pipe wall thickness is 0.05 m. What is the storm sewer invert elevation in the diagram below?

A.

6.50 m

B.

6.55 m

C.

6.75 m

D.

7.00 m

Question # 8

In an oil and gas project, the location of a pile is offset by 78 mm north and 54 mm east of the key location plan. The location was stamped and issued for construction by a consulting engineering company. The statement on the drawings says, “Offset more than 75 mm is not accepted.” Which of the following is the best approach for the civil engineering technologist to take?

A.

Inquire with the client if the pile location is acceptable.

B.

Accept the pile location as is because the offsets are close enough to 100 mm.

C.

Submit a non-conformance report to the design engineer for review and advice.

D.

Fill up the hole and re-drill the pile hole based on the pile key location plan.

Question # 9

What two municipal plans are required to define a new civil infrastructure project?

A.

Residential/commercial development plan and transportation plan

B.

Municipal Development Plan and Transportation Master Plan

C.

Residential/commercial development plan and city transit plan

D.

Municipal Development Plan and city transit plan

Question # 10

What is the primary force that a bridge in the diagram needs to resist?

A.

Compression

B.

Tension

C.

Moment

D.

Shear

Go to page: