Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Technical Examination - Civil Engineering Technology C.E.T

Last Update 19 hours ago Total Questions : 110

The Technical Examination - Civil Engineering Technology C.E.T content is now fully updated, with all current exam questions added 19 hours ago. Deciding to include Civil-Engineering-Technology practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our Civil-Engineering-Technology exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Civil-Engineering-Technology sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Technical Examination - Civil Engineering Technology C.E.T practice test comfortably within the allotted time.

Question # 21

In which step in this diagram will a general contractor need to consider their bonding capacity?

A.

Management review

B.

Complete bid report

C.

Notify subcontractors

D.

Decision to bid

Question # 22

What must an employer do if an employee could be exposed to hazardous materials on a work site?

A.

Remove hazardous materials from the work site prior to starting work.

B.

Provide hazmat suits for employees’ use.

C.

Establish procedures to minimize employee exposure.

D.

Conduct air sample testing prior to starting work.

Question # 23

The invert elevation of a sanitary sewer line is 98.150 m, the pipe thickness is 12 mm and its outside diameter is 600 mm. Using the image below, what is the crown elevatf m

A.

101,238 m

B.

101.250 m

C.

101.488 m

D.

101.500 m

Question # 24

Which of the following can a civil engineering technologist request from a concrete supplier to verify that concrete falls within municipal specifications?

A.

Batch location

B.

Structural mix design

C.

Geotechnical mix design

D.

Batch ticket from the plant

Question # 25

A civil engineering technologist is designing a sanitary collection system that is being constructed below the groundwater table. The owner requested that the system be pressure tested in order to minimize the infiltration into the collection system. Which of the following would be a major design consideration for the collection system?

A.

Pipe diameter

B.

Pipe material

C.

Manhole type

D.

Manhole material

Question # 26

What are the coordinates of the valve in the image below ?

A.

N 4512.25, E 3345.73

B.

N 4507.25, E 3345.73

C.

N 4507.25, E75, E 3345.23

Question # 27

A continuous bridge spans over multiple piers. If one of the piers collapsain standing because the adjacent piers will pick up the load. What type of redundancy does the bridge have?

A.

Structural

B.

Internal

C.

Multi-span

D.

Load path

Question # 28

What should a contract administrator do when the contractor is falling behind schedule?

A.

Find a new contractor who can meet the original completion date.

B.

Write a contemplated change order to hurry the contractor up.

C.

Maintain daily records in preparation for seeking liquidated damages from the contractor.

D.

Keep accurate daily records of activities, progress, and site conditions, and hold regular meetings with the contractor.

Question # 29

According to Occupational Health and Safety legislation, who is responsible for safety in the workplace?

A.

Employees

B.

Employees and employers

C.

Employees and supervisors

D.

Supervisors and employers

Question # 30

A road to be filled is 6 m wide with 3:1 side slopes and a maximum of 6 m fill at the road centre line. The cut and fill are symmetrical, as shown in the image below. The cost of moving material is $4.00 per m³ per km haul length. What is the minimum cost to fill in the road?

A.

$384,000

B.

$576,000

C.

$864,000

D.

$1,152,000

Go to page: