Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Construction Manager (CCM)

Last Update 8 hours ago Total Questions : 65

The Certified Construction Manager (CCM) content is now fully updated, with all current exam questions added 8 hours ago. Deciding to include Construction-Manager practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our Construction-Manager exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these Construction-Manager sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Construction Manager (CCM) practice test comfortably within the allotted time.

Question # 1

During the design phase of a CM agency project, the designer submits several design options for the stakeholders to review and provide input on. Whose responsibility is it to ensure that the stakeholders are able to provide input on the designs?

A.

Owner

B.

Designer

C.

Commissioning agent

D.

CM

Question # 2

As the owner’s representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.

The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor’s office. Which entity is best-suited to resolve this risk?

A.

Owner (Municipality)

B.

Architect (DOR)

C.

Owner’s rep

D.

Design-Build Team

Question # 3

The current construction market is extremely busy, and the trade/sub-contractors are being very selective in the projects they bid on. What options do owners have when the marketplace is vastly different from when their project was a concept to when its ready to be advertised?

A.

Market conditions should not be a factor in when a project is advertised.

B.

Postpone advertising for one year.

C.

Advertise the project and award to lowest bidder.

D.

Consider the impacts of current market conditions and revise project strategy.

Question # 4

A project in schematic design with sustainability goals will soon begin a value engineering study. Which of the following would ensure that the value engineering study will not harm the project's sustainability?

A.

Add a LEED Platinum requirement.

B.

Establish clear sustainability functional requirements.

C.

Hold a partnering workshop first.

D.

Add a LEED Silver requirement.

Question # 5

Bid contract documents have been prepared for LEED certification, but the owner has decided not to formally register for LEED certification. The owner still requires LEED equivalency. How does the CM proceed with the bid process?

A.

Inform owner that LEED process as specified in the specifications will not be implemented.

B.

Notify bidders at prebid conference of changes in LEED registration.

C.

Instruct architect to make changes to bid documents to reflect deletion of LEED registration.

D.

Issue bid instructions that owner will not register project for LEED certification but the contract terms remain unchanged.

Question # 6

It is ideal for the CM to assist in mitigating potential impacts and unforeseen issues that may develop as early as the

A.

construction phase.

B.

post-construction phase.

C.

design phase.

D.

pre-design phase.

Question # 7

BIM best assists the CM with

A.

managing time, safety, quality, and facility operations.

B.

planning, coordination, and control of the project.

C.

developing drawings and facility management.

D.

gathering energy, cost, facility maintenance, safety, and spatial data.

Question # 8

A CM team on a new project which is in the pre-design phase is planning their climate resiliency strategy. Which of the following is the team's BEST first step in this process?

A.

Collect relevant data and reports.

B.

Establish a third-party certification.

C.

Establish QA/QC specifications.

D.

Hire a commissioning agent.

Question # 9

While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is

A.

document the non-conforming work and distribute the documentation to the contractor, design professional, and client.

B.

discuss the concerns with the owner.

C.

direct the contractor to correct the non-conforming work.

D.

schedule a meeting with the design professionals and the client to discuss the issues.

Question # 10

When developing schedule specifications, which of the following practices should the CM recommend to the Owner to avoid disputes regarding weather delays per year?

A.

Using a recognized reference such as NOAA. define the number of allowable "normal" weather impact days expected to occur on the project within the contract documents.

B.

Ask the contractor to specify the number of weather days they believe necessary for the project.

C.

Defer all issues related to weather to NOAA.

D.

Consult a local meteorologist to determine the best estimate of the number of weather days to allow on the project.

Go to page: