You'll find that our CSSBB exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CSSBB sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Six Sigma Black Belt practice test comfortably within the allotted time.

Question # 51

A patient arrives at the clinic at noon and was called into an exam room at 12:43 pm by a nurse for a blood draw. The blood draw tubes were not available in the exam room, so the nurse went to the clinic supply room and found that no blood draw tubes were left. In addition to waiting, which of the following forms of waste were present?

A.

Inventory

B.

Overproduction

C.

Motion

D.

bottleneck

Question # 52

A company that is selecting a Six Sigma project from four potential projects should select the one that

A.

focuses on the area with the highest DPMO

B.

will reduce the overall cost of quality

C.

offers the highest production yield

D.

is aligned with the company’s strategic goals

Question # 53

The ultimate goal of benchmarking is to

A.

acquire information to develop corporate strategies

B.

determine the industry performance level

C.

achieve best-in-class performance

D.

identify industry leaders and competitors

Question # 54

During which phase of the Six Sigma process is a design of experiments (DOE) most likely to be used?

A.

Define

B.

Measure

C.

Improve

D.

Control

Question # 55

The engineering specification for a new circular part is 25 mm ± 1 mm. The distribution of part measurements is assumed to be normal, with 99.73% of the parts meeting the specification. For a sample size of 36, what process control limits should be used for the sample means?

A.

25 ± 0.028

B.

25 ± 0.167

C.

36 ± 0.028

D.

36 ± 0.167

Question # 56

Two catalysts are being analyzed to compare their effect on the yield of a chemical process. Catalyst 1 is currently being used, and catalyst 2 is being considered as it is a less expensive alternative, provided the yield is the same. An experiment is run with 10 observations for each catalyst and t = -1.06. Assuming equal variances and α = 0.05, which of the following conclusions can be made?

A.

t0.025,18 = -2.101 < -1.06 < 2.101, and yields are different

B.

t0.025,18 = -2.101 < -1.06 < 2.101, and yields are not different

C.

t0.05,18 = -1.734 < -1.06 < 1.734, and yields are different

D.

t0.05,18 = -1.734 < -1.06 < 1.734, and yields are not different

Question # 57

A hospital is preparing for a survey for a certification process by an accreditation body. Administration has provided hospital managers with a list of items that the assessors will be asking about. Which of the following analysis tools should management use as part of their preparation for this assessment?

A.

Failure mode and effects analysis (FMEA)

B.

Root cause analysis (RCA)

C.

Gap analysis

D.

Measurement system analysis (MSA)

Question # 58

Which of the following conditions is a typical organizational roadblock to a Six Sigma program?

A.

Management uses a data-driven approach.

B.

A team-based model provides the basis for work units.

C.

The program operates independently of the organizational structure.

D.

The organization’s leadership is focused on sustained performance and outcomes.

Question # 59

A bottle-filling operation is required to fill glass bottles with 16–17 ounces per fill. Fill levels are normally distributed. When a customer requested a process capability study, the company sampled 4 bottles every half hour over five 8-hour shifts. The mean fill level for this sample was X̄ = 16.4 and the fill range was 15.9–16.8 with R̄ = 0.6. The fill process has a capability index of

A.

0.57

B.

0.81

C.

1.06

D.

1.33

Question # 60

A Black Belt tells a project team, “For our control charts, we need samples that are as homogeneous as possible and that allow the maximum opportunity for variation between them.” The Black Belt is describing

A.

a critical parameter

B.

rational subgrouping

C.

inspection sampling

D.

randomness