Last Update 11 hours ago Total Questions : 80
The ISTQB Certified Tester Advanced Level - Test Automation Engineering CTAL-TAE (Syllabus v2.0) content is now fully updated, with all current exam questions added 11 hours ago. Deciding to include CTAL-TAE_V2 practice exam questions in your study plan goes far beyond basic test preparation.
You'll find that our CTAL-TAE_V2 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CTAL-TAE_V2 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any ISTQB Certified Tester Advanced Level - Test Automation Engineering CTAL-TAE (Syllabus v2.0) practice test comfortably within the allotted time.
You are employed as a TAE on a project to build a purchasing system. The main requirements for the system are:
1) Allow users to enter details of items that they wish to have purchased and, from these details, create a purchase request.
2) Take each purchase request through a workflow that will allow the requestor’s line manager to approve the request, reject it, or return it for clarification/modification.
3) Forward approved requests to the Purchasing Department.
4) Allow purchasers to find the best available supplier and place the request on that supplier as a purchase order.
Requirement 1 has now been delivered and has been satisfactorily tested manually. In parallel, you have developed a TAS so that functional suitability testing can be automated.
The functional suitability testing of Requirement 1 has now been automated as fully as possible. A change to add audit logging of user activity is planned but has not yet been made. After a small change to the UI code, the last regression run contained a significant number of unexplained test failures. At the point each test stopped, the actual and expected results showed no discrepancies. In each case, the run was able to continue with the next test in the suite. Preliminary investigation showed that the points at which these tests stopped had nothing obvious in common.
Which option below contains the BEST next steps to investigate this?
Which statement correctly describes what a Test Automation Architecture should do?
An automated test case that should always pass sometimes passes and sometimes fails intermittently (non-deterministic behavior) when executed in the same test environment, even if no code (i.e., SUT code or the test automation code) has been changed. Which of the following statements about the root cause of this non-deterministic behavior is TRUE?
You are working as a TAE for a large insurance company that offers a wide range of products, including home, health, and motor insurance. Your next project will be a major change to the existing system for processing policy claims. The project’s objective is to provide more flexibility in the process for claim authorization, according to the type of policy and nature of the claim, so that simple claims can be processed faster. It will follow a hybrid methodology with development and testing completed in 3-week iterations.
The most important functional and non-functional tests for the existing system have been automated. The older tests feature structured scripting, but the more recent ones have benefited from data-driven testing.
Which automation approach for the system-level tests would be MOST suitable for this project?
You are a TAE responsible for a TAS that is used on several products, all of which have complex UIs. A substantial proportion of the automated tests break on a regular basis, usually for reasons associated with the UI. The investigation and maintenance this requires is significantly reducing the productivity of the teams and the return on investment.
You are looking for ways to improve the test cases in this TAS. Which of the following approaches would be MOST appropriate?
a) Artificial intelligence
b) Test histograms
c) Reliability growth modelling
d) Schema validation
e) Operational profiles
You have agreed with your organization's managers to conduct a pilot project to introduce test automation. Managers' expectations about the benefits of automation are too optimistic. Which of the following is LEAST relevant when deciding the scope of the pilot project's objectives?
As a TA-E, you have successfully verified that a test automation environment and all other components of the TAS are working as expected. Now your goal is to verify the correct behavior for a given automated test suite that will be run by the TAS. Which of the following should NOT be part of the verifications aimed at achieving your goal?
What does contract testing verify?
(Which of the following answers describes the LEAST relevant concern in selecting suitable test automation tools for a test automation project?)
Your TAF writes detailed test logs for every test that it executes. Data storage space in the test environment is limited, so after each run it is necessary to remove unnecessary detail from the log for tests that passed and move the data that must be kept to a different place.
What would be the BEST way to do this?