Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Technology Specialist

Last Update 4 hours ago Total Questions : 254

The Certified Technology Specialist content is now fully updated, with all current exam questions added 4 hours ago. Deciding to include CTS practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CTS exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CTS sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Technology Specialist practice test comfortably within the allotted time.

Question # 41

When doing a site survey, it is MOST IMPORTANT to consider the client ' s

A.

budget.

B.

timeline.

C.

expectations.

D.

knowledge of technology.

Question # 42

An AV system has a dedicated managed switch with an IP address scheme of 192.168.10.0/24, but one component is not talking to the rest of the system. What network property should be checked to ensure it connects to the rest of the system?

A.

QoS

B.

VLAN

C.

Subnet

D.

Gateway

Question # 43

If content is protected, the HDCP handshake(s) occurs

A.

every few seconds after the hotplug circuit is first completed.

B.

only when the hotplug circuit is first completed.

C.

only when the display is turned on.

D.

only when the source is turned on.

Question # 44

If the nominal light output of a projector was measured at 5000 ANSI lumens using an f/1.4 lens, what would happen if the lens was changed to an f/2.8 large zoom?

A.

The projected image will be darker

B.

The projected image will be brighter

C.

The screen will need to be changed to 1:1 gain

D.

The screen will need to be changed to a high contrast screen

Question # 45

A client has ordered a large project from a company. This project has several critical components and a fixed schedule. Which of the following will be VITAL for ensuring that the company meets the deadlines?

A.

proper job costing

B.

confirming lead times

C.

qualifying the customer

D.

confirming price changes

Question # 46

Your client has requested a 50inch monitor be mounted on the south wail of this boardroom. Which two recessed lights will need to be separated into the r own zone in order to turn them off when the monitor is on?

A.

A

B.

B.

C.

C

D.

D

Question # 47

At what time of day is it BEST to conduct a site survey?

A.

Early mornings

B.

During normal operations

C.

After normal business hours

D.

Only at specially scheduled appointments

Question # 48

When evaluating site conditions for an AV project that requires a free-standing rack that is 49 RU or taller, the condition that will force assembly on site instead of building the rack in the shop and delivering it fully assembled is when the:

A.

Lighting is better onsite

B.

Elevator/lift is only 7 feet [2.13 meters] tall

C.

Room is only accessible after normal working hours

D.

Construction dumpster is located close to the loading dock

Question # 49

A typical speech reinforcement system which is broken down into zones, with each zone corresponding to its own set of microphones, power amplifiers, and loudspeakers is known as:

A.

Mix-minus

B.

Public address

C.

Audio conferencing

D.

Interruptible feedback

Question # 50

Milestones are key events or deliverables in a project. On a Gantt Chart or Network Diagram, milestones are represented by a(n)

A.

circle or oval.

B.

diamond or triangle.

C.

square or rectangle.

D.

asterisk or apostrophe.