You'll find that our ENOV612-PRG exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these ENOV612-PRG sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any V6 ENOVIA V6 Program Central (V6R2012) practice test comfortably within the allotted time.

Question # 11

Which dependency code do you assign if the selected task CANNOT start until the current task starts?

A.

Finish-To-Finish

B.

Finish-To-Start

C.

Start-To-Finish

D.

Start-To-Start

Question # 12

If the “Requires Owner Review” option is chosen for a task in a route, then an email will be sent to the:

A.

Route Owner upon completion of the task for review.

B.

Route Owner and Task Assignee upon completion of the task for review by the Route Owner.

C.

Route Owner upon start of the task.

D.

Route Owner only if the assignee rejects the task

Question # 13

The assessment value is calculated by:

A.

manually assigning values to each category

B.

Cost Ratio divided by Slip Days

C.

Risk value multiplied by Slip Days

D.

Cost Ratio divided by the Risk Value

Question # 14

When an issue priority level is set to High that was reported against a Project:

A.

the issue requires upper management for resolution

B.

the project cannot be promoted to complete

C.

the WBS task cannot be promoted to Complete

D.

no change to the system as there is no functionality tied to this

Question # 15

What roles are authorized to create programs?

A.

Only Program Leads and External Program Leads

B.

Any role

C.

Program designers only

D.

Project leads only

Question # 16

When 2 people are assigned to the same task, the default allocation is that...

A.

both are set to 100%

B.

each one is set to 50%

C.

the 1st assigned person is set to 100% and the 2nd to 0%

D.

both are set to 0%

Question # 17

What are the lifecycle states of a program?

A.

Active and Inactive

B.

Create, Active, Archive

C.

Active and Archive

D.

Create, Active, Inactive and Archive

Question # 18

To view all your WBS tasks and subtasks using the structure browser, you would use the expand box and select All levels then,

A.

click the Categories menu and select expand

B.

click the View menu

C.

click the plus box next to the Task

D.

click the Actions menu and select expand

Question # 19

The system sends a notification to the person who is assigned to a task when...

A.

the task is in create state

B.

the person is removed as a task assignee

C.

the task is promoted to the Assign state

D.

the task is complete

Question # 20

When displaying a Gantt Chart, the user CANNOT change what display parameter?

A.

Hide a column

B.

Show a column name

C.

Sort a column

D.

Color