You'll find that our L6M5 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these L6M5 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Strategic Programme Leadership practice test comfortably within the allotted time.

Question # 1

Juno is completing a Variance Analysis on the sales department ' s spend for the first quarter. He concludes that there is a Favourable Variance. What does this mean?

A.

the department has more money in the budget than what they have spent so far

B.

the department has spent more than the allocated budget

C.

the results are better than expected

D.

the results are worse than expected

Question # 2

Glitter Kitten Ltd negotiates a contract with Paw Ltd (new supplier).

Q: What pricing mechanism is best for visibility into supplier costs and margins?

Answer Options:

A.

Open-Book Costing

B.

Cost Reimbursable Contract

C.

Bottom-Up Pricing

D.

Activity-Based Costing

Question # 3

Which elements define an organization ' s culture? (Select all that apply.)

✔ Beliefs and assumptions

✔ Ways of interacting

✔ The physical environment

✔ Attitudes and customs

Question # 4

Salvador Ltd is a manufacturer of batteries for domestic appliances and hand tools. The company recently expanded due to excellent sales and introduced new machinery for producing solar-powered batteries.

    They contracted Sunshine Ltd to build and install the machinery .

    The contract specified that the machine must produce 5 batteries per hour , but currently, it is producing only 4 batteries per hour .

    Salvador Ltd has agreed to work with Sunshine Ltd to resolve the issue within one month before liquidated damages apply.

Q: What stage is the project at?

Answer Options:

A.

Mechanical completion

B.

Performance testing

C.

Provisional acceptance

D.

Commercial operation

Question # 5

Which project management methodology outlines a process for closing a project?

Answer Options:

A.

Monte Carlo

B.

Critical Path

C.

MRP

D.

Prince2

Question # 6

In which scenario would a Cost Reimbursable contract be most suitable?

Answer Options:

A.

A research project where the exact scope of work is unknown at the onset

B.

A construction project where raw material prices may fluctuate

C.

The creation of a new product, where time is critical, and the client wishes to reward the contractor for speedy delivery

D.

The manufacturing of food items, where the client may return raw materials that do not meet specifications

Question # 7

The Human-Relations Model describes a type of organization with a set of values. Which TWO of the following apply?

A.

high levels of flexibility

B.

low levels of flexibility

C.

a focus on internal business functions

D.

a focus on the external environment

Question # 8

Paradigm Digital Services has strict office rules on branding, workspaces, and dress code.

Q: Which aspect of the Cultural Web does this describe?

Answer Options:

A.

Organizational structure

B.

Symbols

C.

Control systems

D.

Rituals

E.

Power structure

Question # 9

Which of the following is an advantage to the contractor in an EPC contract arrangement?

EPC contracts provide several benefits to contractors, such as clear project scope, reduced risks, and better project management .

Answer Options:

A.

The scope is clearly defined by the client

B.

There is an early completion bonus

C.

There are no subcontractors to manage

D.

The client assumes all risks for the construction

Question # 10

Jane works at a manufacturing organisation based in Europe. The organisation has recently decided to open a new factory in a South-East Asian country and Jane is to head up the project to launch the new factory. She has decided to fly out to the new site ahead of opening to do some research into the local culture and assess how the differences in culture may impact upon the company as a whole. The CFO of Jane ' s company thinks that this is a bad idea and a waste of money. Should Jane go?

A.

yes – understanding the local culture will be important in incorporating the new site into the company

B.

yes – Jane should take advantage of the free trip to learn the language

C.

no – it is racist to assume that the culture is different

D.

no – the CFO is correct that this would be a waste of money because Jane does not speak the local language