You'll find that our LEED-AP-O+M exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these LEED-AP-O+M sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any LEED AP Operations + Maintenance (LEED AP O+M) practice test comfortably within the allotted time.

Question # 1

Which of the following prerequisites or credits has a minimum occupancy requirement?

A.

Indoor Environmental Quality Credit, Daylight and Views

B.

Water Efficiency Prerequisite, Indoor Water Use Reduction

C.

Energy and Atmosphere Prerequisite, Minimum Energy Performance

D.

Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance

Question # 2

An urban office building project is installing a cooling tower. To save on potable water, the project would like to use a non-potable water source to provide 20% of the cooling tower makeup water to achieve the maximum number of points under Water Efficiency Credit, Cooling Tower Water Use. Which non-potable water source would be the most appropriate for use?

A.

Municipally supplied tap water

B.

Ground source stormwater runoff

C.

Air conditioner condensate

D.

Graywater from the building's hand-washing sinks

Question # 3

A standard reference when creating an indoor air quality management program is

A.

Home Energy Rating System (HERS)

B.

American Society of Heating, Refrigerating and Air - Conditioning Engineers 90.1 - 2010 (ASHRAE)

C.

Chartered Institution of Building Services Engineers (CIBSE)

D.

Indoor Air Quality Building Education and Assessment Model (I-BEAM)

Question # 4

The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction

ensures that eligible newly installed plumbing fixtures will

A.

be advertised as LEED compliant

B.

be both water efficient and high performing

C.

comply with mandatory federal government regulations

D.

comply with all international plumbing system requirements

Question # 5

Which of the following best meets requirements of Sustainable Sites Credit, Site Development - Protect or Restore Habitat?

A.

Leaving 50% of the site undisturbed

B.

Using native or adaptive vegetation on 20% of the site area

C.

Protecting the habitat of an offsite area of land equal in size to the building site area

D.

Building a rainwater detention pond and using the water for irrigation

Question # 6

For projects not eligible for the ENERGY STAR® rating, the project team could demonstrate compliance with Energy

and Atmosphere Prerequisite, Minimum Energy Efficiency Performance by

A.

conducting an energy audit that develops a commissioning plan for the building's major energy using system

B.

providing a program demonstrating no or low cost measures of improvement to increase energy efficiency

C.

developing a master list of findings identifying systems or pieces of equipment including the defects or problems

and proposed solutions

D.

demonstrating an energy efficiency of at least 25% better than the national average for typical buildings of similar

type based on energy source

Question # 7

One tenant occupying 50% of a commercial office building pursuing LEED® O+M certification has provided purchasing data. The other tenants in the building occupying the remaining 50% have chosen not to provide purchasing data. For credits related to purchasing, the LEED applicant must

A.

estimate the purchases of the other tenants and assume they are compliant in the Materials and Resources credit calculations

B.

estimate the purchases of the other tenants and assume they are noncompliant in the Materials and Resources credit calculations

C.

estimate the purchases of the other tenants and apply the compliance rate from LEED applicant in the Materials and Resources credit calculations

D.

exclude the purchases of the other tenants from the Materials and Resources credit calculations

Question # 8

When tracking waste data during the performance period for Materials and Resources Credit, Solid Waste Management - Ongoing, which strategy may be used to document total and diverted waste?

A.

Measure and document waste in weight or volume

B.

Use replacement value as the metric for ongoing waste

C.

Extrapolate data from one month of the performance period

D.

Do not allow tenant waste outside the building's waste program to be included

Question # 9

The LEED AP has identified a pilot credit that is relevant to the project. This would be documented in LEED Online as a(n)

A.

Regional Priority credit

B.

Innovation credit

C.

Exemplary Performance for a related credit

D.

Special Circumstances within a related credit

Question # 10

The project team of an existing urban site has 4% total vegetated area and desires to increase the percentage to

equal or be greater than 5%. Which strategy can the team implement to achieve this goal?

A.

Install a vegetated roof system

B.

Convert lawn areas to native plants

C.

Mitigate the vegetated area off-site through a land trust

D.

Convert the paved areas of the site to pervious pavement