You'll find that our SPS exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SPS sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Scaled Professional Scrum (SPS) Exam practice test comfortably within the allotted time.
True or False: There is one Product Backlog for a Nexus.
How should Product Backlog items be chosen when multiple Scrum Teams work from the same
Product Backlog?
(choose the best answer)
Scenario A: Nexus Sprint Review with Five Scrum Teams
There are five Scrum Teams working on a product. During the Nexus Sprint Review, the teams
present the results of the Sprint. After introductions, each team takes time to present their work
for inspection by individually showing the new features they have built. They are not using a
shared environment. The stakeholders do not provide much feedback. The event ends and
people filter out of the room.
Since teams are not using a shared environment, what is likely?
(choose the best two answers)
True or False: A Nexus Integration Team is accountable for ensuring that a Integrated
Increment is produced at least once a Sprint.
True or False: Many Scrum Teams working on the same product create coordination
challenges that can be fully addressed by creating a communication plan.
Currently, your Scrum Teams are organized to address a single functional (component) area of
the product. What should be considered when deciding to move away from such component
teams toward feature teams?
(choose the best three answers)
The purpose of Nexus Sprint Planning is to:
(choose the best two answers)