You'll find that our SPS exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SPS sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Scaled Professional Scrum (SPS) Exam practice test comfortably within the allotted time.

Question # 11

Which statements best describe a Nexus Sprint Review?

(choose the best two answers)

A.

It provides feedback on the Integrated Increment.

B.

It replaces individual Scrum Team Sprint Reviews.

C.

It is a container for each individual Scrum Team ' s Sprint Review.

D.

It is when individual Scrum Teams demo their work.

Question # 12

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Which of the following two strategies would be most effective in dealing with their

dependencies?

(choose the best two answers)

A.

Discover and document dependent work during Cross-Team Refinement of the

Product Backlog, so teams are aware of dependencies before Nexus Sprint

Planning. This will allow Nexus Sprint Planning to focus on resolving

dependencies for the upcoming Sprint.

B.

Have the Nexus Integration Team order the Nexus Sprint Backlog. They should

control and resolve the dependencies.

C.

During Nexus Sprint Planning, have appropriate representatives from each team

in the Nexus briefly meet to discuss dependencies for the upcoming Sprint. This

conversation will help their individual team ' s Sprint Planning.

D.

Gather all people in the Nexus into a 48-hour Nexus Sprint Planning event.

Discover, document, and resolve dependencies during this time.