You'll find that our PVIP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PVIP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any PV Installation Professional (PVIP) Board Certification practice test comfortably within the allotted time.

Question # 41

A technician has been called to a scale due to a low-performing array. The technician will perform tests in the 24-source circuit combiner box. After putting on the correct PPE and turning off and performing lock.tagout of the inverted and combiner disconnect. Which is the next step to safely begin electrical testing in the combiner box?

A.

Open all fuse holders in the combiner box.

B.

Test for voltage on the positive out

C.

Remove any surge suppression devices from the circuits.

D.

Test for current on each source circuit coming into the combiner box.

Question # 42

Inspection of a new PV installation shows that the dwelling uses a galvanized water pipe for its grounding electrode and that the PV system now shares the connection. Which of the following is an acceptable supplemental electrode method to ensure the integrity of having a grounding electrode?

A.

Connecting the water pipe to the service entrance panel metal structure

B.

Connecting the water pipe to a gas pipe that is known to be solidly grounded

C.

Connecting the service panel to an auxiliary ground used by a lightning protection system

D.

Connection the service panel to a copper-clad steel ground rod near the panel

Question # 43

A module’s power is 340W at STC. At 700 W/m² and 40°C with a coefficient of -0.38%/°C, what is the output?

A.

224W

B.

236W

C.

248W

D.

260W

Question # 44

In the middle of a winter day, the data acquisition system for a ground-mounted PV system with large central inverters sends an email alert that system performance is at 50% based on irradiance and temperature performance calculations. No inverters are completely offline. The closed technician is a 4-hour drive from the site, and there are no cameras on site. Which is the BEST response to this situation?

A.

Dispatch the technician to the site t investigate the low performance issue in person.

B.

Review power output and weather conditions via the monitoring portal, and review local weather reports.

C.

Report the low performance to the inverter manufacturer and request that a technical be sent to the site for a warranty claim.

D.

Call the data acquisition company to report a monitoring system failure.

Question # 45

A ground-mount array uses driven piles with a lateral load capacity of 500 lbs. The wind load calculation yields a lateral force of 600 lbs per pile. What must be done?

A.

Increase pile depth

B.

Add additional piles

C.

Use a different foundation type

D.

Any of the above

Question # 46

While surveying a potential three-phase project, an installer measures the voltage at the point of utility interconnection. The results are as follows:

* Phase to phase: 240V

* Phase A neutral: 120V

* Phase B neutral: 208V

* Phase C neutral: 120V

Which is a likely cause of these reading?

A.

Supply-side ground fault

B.

Phase-to-phase power imbalances

C.

High-leg transformer configuration

D.

Missing ground in the transformer

Question # 47

A residential PV system uses two 120.240Vac utility-interactive inverters with a sealed lead-acid battery energy backup for protected loads. The MOST important protected load consideration when operating in the backup mode is that:

A.

The protected loads must have automatic restart function.

B.

All protected loads are connected in multiwire branch circuits.

C.

The peak current from the sealed lead- acid batteries must not exceed peak demand currents.

D.

The stand-alone system configuration can adequately supply current to all protected load branch circuit.

Question # 48

A PV module is mounted with a 2-inch standoff from a shingle roof. What is the minimum clearance required for fire access per the International Fire Code (IFC)?

A.

1 inch

B.

3 inches

C.

6 inches

D.

9 inches