You'll find that our SMC exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SMC sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Scrum Master Certified (SMC) practice test comfortably within the allotted time.

Question # 31

You are the Scrum Master for your organization and Sally is the Product Owner. The Development Team approaches you with many questions regarding a user story. What should you do next in this scenario?

A.

The Development Team should work with you as this is roadblock.

B.

The Development Team should meet with Sally to determine clarity on the user story, to determine what is possible, and what is acceptable.

C.

The Development Team and Sally should determine which Development Team member(s) should speak with the customer owning the requirement.

D.

The Development Team should determine which Development Team member(s) should speak with the customer owning the requirement.

Question # 32

All of the following statements about Risk Communications are true, EXCEPT:

A.

The Stakeholders should be continuously informed about risks, including the potential impact of these risks

and the plans for responding to each risk.

B.

The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner during

Daily Standup Meetings.

C.

The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to

the Scrum Team.

D.

Information related to risks is maintained and updated through the Risk Burndown Chart.

Question # 33

The table given below presents some Scrum roles that play an important part in business justification and their

responsibilities. Choose the option that correctly matches each role in the left hand column to its action in the

right hand column.

A.

I-b, II-c, III-a, IV-d

B.

I-a, II-c, III-b, IV-d

C.

I-c, II-d, III-b, IV-a

D.

I-d, II-b, III-c, IV-a

Question # 34

You are the Scrum Master for a new project. This project will have 80 developers contributing to the product. As a Scrum Master, how would you divide a group of 80 people into multiple Development Teams?

A.

Create ten teams of eight people per team.

B.

Create eight teams of 10 people per team.

C.

Coach the Development Team about being self-organizing, but also coach the team to form based on relationships from past projects.

D.

Tell the 80 developers about the product, the product vision, and rules of the Scrum framework, then allow the 80 developers to self-organize into separate teams.

Question # 35

Which of the following events does NOT help the Scrum Team in identifying or resolving risks?

A.

Daily Standup Meeting

B.

Sprint Planning Meeting

C.

Financial Planning Meeting

D.

Prioritized Product Backlog Review Meeting

Question # 36

A Scrum Team is estimating the prioritized User Stories. Each team member has been assigned a deck of

numbered cards, in which each card is numbered in a sequence. The team members use these cards to

assess a particular User Story by picking and showing a card from the deck that represents their estimate for

the User Story. Which estimation tool is the Scrum Team using?

A.

Fist of Five.

B.

Wideband Delphi.

C.

Affinity Estimation.

D.

Planning Poker.

Question # 37

Which one of the following is an output of Sprint Planning and is used to give the Development Team a Sprint target?

A.

Sprint Goal

B.

Roles and Responsibilities

C.

Product Backlog

D.

Team charter

Question # 38

During a Retrospect Sprint Meeting, the Scrum team conducted an Explorer-Shopper-Vacationer-Prisoner

exercise. One of the participants indicated that he feels like an Explorer. Which of the following best describes

who an Explorer is?

A.

One who wants to listen to everything and choose what he takes away from the retrospective

B.

One who wants to participate in and learn everything discussed in the retrospective

C.

One who wants to relax and be a tourist during the retrospective

D.

One who wants to explore how other project tackled similar issues and improved processes

Question # 39

Which one of the following statements about the history of Scrum is NOT correct?

A.

The idea of Scrum was derived from a “rugby” approach, in which “a team tries to go the distance as a unit,

passing the ball back and forth.”

B.

Takeuchi and Nonaka proposed that product development should be like a sequential relay race.

C.

Scrum was based on a flexible and all-inclusive product development strategy where the development

team works as a unit to reach a common goal.

D.

Takeuchi and Nonaka based their approach on manufacturing case studies from various industries.

Question # 40

The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort required to develop

the functionality described in each User Story. The team wants to adopt an estimation technique through

which they will be able to quickly estimate a large number of User Stories. Which of the following techniques

do you think they should adopt?

A.

Planning Poker.

B.

Wideband Delphi.

C.

Affinity Estimation.

D.

Relative Sizing.