You'll find that our SSM exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these SSM sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any SSM (6.0) - SAFe Scrum Master Practice 6.0 practice test comfortably within the allotted time.

Question # 11

What is one characteristic of high-performing teams?

A.

Having fun with the work and with each other

B.

Having similar backgrounds and points of view

C.

Having shared interests outside of work

D.

Having a competitive drive between team members

Question # 12

Which of the following statements is true about the team backlog?

A.

The team backlog is where Stories are accepted

B.

The team backlog is where the team finalizes work

C.

The team backlog is where the team refines possible Stories

D.

The team backlog is where the team commits to work

Question # 13

According to SAFe, what is one approach to retrospectives?

A.

Ensure the event ends with sustainable ideas for the next Iteration

B.

Ensure the event ends with essential working agreements in place for the team

C.

Ensure the event ends with relevant goals for how the team will handle dependencies

D.

Ensure the event ends with actionable improvement items for the backlog

Question # 14

What is one benefit of having an IP Iteration every PI?

A.

It provides dedicated time for innovation and continuing education

B.

It provides committed time for more team communication

C.

It provides time for teams to take vacation

D.

It provides focused time for teams to complete quality testing

Question # 15

What is one anti-pattern of the Inspect and Adapt?

A.

No actionable improvement Features are created

B.

Not enough team members attend the PI System demo

C.

Too many ideas enter the problem-solving workshop

D.

Only one problem is identified by each team in the retrospective

Question # 16

What is one goal of the Iteration Review?

A.

To demonstrate completed Stories from the prior PI

B.

To identify dependencies in the backlog

C.

To add acceptance criteria to Stories in the Iteration

D.

To receive feedback on the increment

Question # 17

During which of the following stages of team development do team members stop focusing on their own goals and begin focusing on developing better ways of working together?

A.

Forming

B.

Norming

C.

Storming

D.

Transforming

Question # 18

What are the three parts of an Inspect and Adapt event?

A.

Retrospective, qualitative and quantitative measurement, and Strategic Theme presentation

B.

Actual business value review, root cause analysis, and retrospective

C.

PI System Demo, qualitative and quantitative measurement, and problem-solving workshop

D.

Problem-solving workshop, actual business value review, and Strategic Theme presentation

Question # 19

Which of the following types of information is shared between the teams on an ART?

A.

A commitment to business agility

B.

A set of regulations

C.

A set of metrics

D.

A common mission using a single backlog

Question # 20

What is the intended value of the Backlog Refinement event?

A.

The team is able to prepare requirements for Iteration Planning

B.

The team aligns on the progress of Iteration Goals

C.

The team is able to commit to a set of goals to be delivered in the Iteration

D.

The team reviews and improves processes before the next Iteration