Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

What visibility should Scrum Masters provide during the Agile Release Train Sync?

A.

Visibility into progress and impediments

B.

Visibility into system Solution Intent

C.

Visibility into collaboration deployment

D.

Visibility into single source design decisions

Full Access
Question # 5

Which of the following SAFe Core Values involves coaching aspiring developers to grow their skillsets and fill new roles throughout the organization?

A.

Built-In Quality

B.

Respect for People

C.

Transparency

D.

Alignment

Full Access
Question # 6

What can be used to script the change to SAFe?

A.

The Lean-Agile Center of Excellence (LACE) charter

B.

The portfolio canvas

C.

The steps in the Business Agility

D.

The SAFe Implementation Roadmap

Full Access
Question # 7

What is one key purpose of DevOps?

A.

DevOps focuses on a set of practices applied to large systems

B.

DevOps joins development & operations to enable continuous delivery

C.

DevOps enables continuous release by building a scalable Continuous Delivery Pipeline

D.

DevOps focuses on automating the delivery pipeline to reduce transaction cost

Full Access
Question # 8

Which SAFe Lean-Agile Principle includes an emphasis on "deliver early and often"?

A.

Organize around value

B.

Make value flow without interruptions

C.

Build incrementally with fast, integrated learning cycles

D.

Take an economic view

Full Access
Question # 9

What is a quality of an Agile team?

A.

Each team has a Scrum Master/Team Coach and a Product Manager

B.

Managers direct their work

C.

Cross-functional

D.

Composed of 10 to 20 members

Full Access
Question # 10

The Lean Thinking principle, "make value flow without interruptions" means identifying what?

A.

Predictability issues of the train

B.

Key performance indicators

C.

Activities that lack innovation

D.

Delays

Full Access
Question # 11

What is one of the Lean budget Guardrails?

A.

Objective measurements

B.

Continuous Business Owner engagement

C.

Participatory budgeting

D.

Spending caps for each ART

Full Access
Question # 12

What is scrum?

A.

A methodology used to deliver usable and reliable solutions to the end user

B.

A process for continuously maintaining deployment readiness

C.

A lightweight process for cross-functional, self-organized teams

D.

A routine method of deploying deliverables to operations

Full Access
Question # 13

What best describes the process of the confidence vote?

A.

Business Owners vote

B.

The teams and the ARTs vote

C.

The managers vote

D.

Each person votes

Full Access
Question # 14

What is the purpose of building a continuous delivery pipeline?

A.

To deliver new functionality more frequently than with traditional processes

B.

To identify key stakeholders within the system architecture

C.

To prioritize system stability over development speed

D.

To prioritize development speed over system stability

Full Access
Question # 15

What does the ART planning board show?

A.

Risks

B.

Significant dependencies

C.

Capacity and load

D.

Epics

Full Access
Question # 16

What is one Story component to consider when estimating size?

A.

Scope

B.

Depth

C.

Knowledge

D.

Dependency

Full Access
Question # 17

What do Strategic Themes influence directly?

A.

Lean budget Guardrails

B.

Organization of the ART

C.

Enterprise Strategy

D.

PI cadence

Full Access
Question # 18

What is one responsibility of the Scrum Master?

A.

To prioritize the Team's Backlog

B.

To define the tasks and assign owners

C.

To remove impediments in order to help protect the team

D.

To facilitate the PI Planning session

Full Access
Question # 19

During which PI planning activity do team members commit to do everything they can to meet the agreed-to-objectives?

A.

The draft plan review

B.

The second team breakout session

C.

The PI confidence vote

D.

The Management Review and Problem-Solving workshop

Full Access
Question # 20

What is an example of applying cadence-based synchronization in SAFe?

A.

Using a Portfolio Kanban system

B.

Allocating budgets to Value Streams

C.

Creating cross-functional ARTs and Agile teams

D.

Conducting a PI Planning event

Full Access
Question # 21

Which factor helps unlock the intrinsic motivation of knowledge workers?

A.

Pay-for-performance

B.

Autonomy

C.

Parallel development

D.

Team performance incentives

Full Access
Question # 22

What is one responsibility of Product Management?

A.

Provide estimates for the Team Backlog

B.

Own Spike stories on the Team Backlog

C.

Maintain the Architectural Runway

D.

Define priorities in the ART Backlog

Full Access
Question # 23

On day two of PI Planning, management presents adjustments based on the previous day's management review and problem-solving meeting. What is one possible type of adjustment they could make?

A.

Create new User Stories

B.

Adjust business priorities

C.

Change a team's plan

D.

Redefine the length of the PI

Full Access
Question # 24

Which pillar in the House of Lean focuses on the Customer being the consumer of the work?

A.

Value

B.

Innovation

C.

Respect for People & Culture

D.

Flow

Full Access
Question # 25

What is the recommended final agenda item of PI Planning?

A.

Reviewing the final plan

B.

Surfacing the ART risks

C.

Participating in the planning retrospective

D.

Taking the PI confidence vote

Full Access
Question # 26

What replaces detailed requirements documents?

A.

Pair work

B.

Task boards

C.

Stories

D.

Unit tests

Full Access
Question # 27

What is the purpose of the Team Sync?

A.

To identify ART PI risks

B.

To coordinate daily work

C.

To identify Iteration goals

D.

To make announcements to the entire ART

Full Access
Question # 28

During System Demo, Team B states that the most recent release failed because of poor version control. They share their plan for preventing similar mistakes from happening in the future. Which of the following SAFe Core Values is Team B demonstrating?

A.

Organize around value

B.

Siloed Thinking

C.

Transparency

D.

Visualizing work

Full Access
Question # 29

Which Lean budget Guardrail helps ensure the appropriate allocation of budgets to balance near-term opportunities with long-term strategy and growth?

A.

Applying capacity allocation

B.

Guiding investments by horizon

C.

Approving significant initiatives

D.

Continuous Business Owner engagement

Full Access
Question # 30

What are two reasons Agile development is more beneficial than waterfall development? (Choose two.)

A.

It requires phase-gate approvals to ensure that everyone is moving together

B.

It increases productivity and employee engagement

C.

It allows businesses to deliver value to the market more quickly

D.

It relies on external provider dependencies

E.

It allows management to track project progress based on steering committees and metrics

Full Access
Question # 31

What is the purpose of an empathy map?

A.

To facilitate collaboration with other team members

B.

To identify the customer

C.

To gain deeper insight to the members of an Agile Team

D.

To help develop a deeper understanding of the customer

Full Access
Question # 32

According to SAFe, a Feature should be sized to fit into what duration?

A.

One month

B.

One year

C.

One Iteration

D.

One PI

Full Access
Question # 33

Which of the following SAFe Core Competencies of Business Agility includes the built-in quality dimension?

A.

Agile Product Delivery

B.

Team and Technical Agility

C.

Organizational Agility

D.

Enterprise Solution Delivery

Full Access
Question # 34

What are the SAFe Core Values?

A.

Code Quality, Fast Feedback, Alignment, Trust

B.

People and Culture, Transparency, Collaboration, Responding to Change

C.

Commitment, Competency, Collocation, Culture

D.

Built-in Quality, Program Execution, Alignment, Transparency

Full Access
Question # 35

Which statement is a value from the Agile Manifesto?

A.

Build incrementally with fast, integrated learning cycles

B.

Responding to change over following a plan

C.

Respect for people and culture

D.

Working software is the primary measure of progress

Full Access
Question # 36

Who has content authority to make decisions at the User Story level during PI Planning?

A.

Release Train Engineer

B.

Scrum Master/Team Coach

C.

Product Owner

D.

Agile Team

Full Access
Question # 37

What is part of the role of Product Management?

A.

To assign business value to Features

B.

To define Enablers

C.

To prioritize the ART Backlog

Full Access
Question # 38

What is the first step in Kotter's 8-step process for leading change?

A.

Generate short-term wins

B.

Enlist a volunteer army

C.

Create a sense of urgency

D.

Build a guiding coalition

Full Access
Question # 39

What is the recommended length of an Iteration?

A.

Two weeks

B.

Ten weeks

C.

Four weeks

D.

Eight weeks

Full Access
Question # 40

Which of the following work types is defined as "a short description of a small piece of desired functionality written in the user's language”?

A.

User Feature

B.

User Story

C.

User Requirement

D.

User Criteria

Full Access
Question # 41

What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers", require besides purpose and minimum possible constraints?

A.

Autonomy

B.

Innovation

C.

Incentive-based compensation

D.

Transparency

Full Access
Question # 42

What does the "C" represent in the CALMR approach to DevOps?

A.

Completion

B.

Cycle-time

C.

Culture

D.

Continuous Integration

Full Access
Question # 43

What is a major benefit of reducing batch size?

A.

Increases visibility

B.

Decreases stress on the system

C.

Increases work in process

D.

Increases throughput

Full Access
Question # 44

What is the primary purpose of the ART Planning Board?

A.

To show sizing of the Epics in relation to each other

B.

To show dependencies between teams relating to the Feature development

C.

To show Feature priority in association with business value

D.

To satisfy System Demo expectation by demonstrating incremental delivery

Full Access
Question # 45

The "3 Cs" is a popular guideline for writing user stories. What does each of the three Cs represent? (Choose three.)

A.

Confirmation

B.

Conform

C.

Clarification

D.

Card

E.

Conversation

F.

Concept

Full Access
Question # 46

What are the four types of team topologies?

A.

Stream-aligned, platform, enabling, and complicated subsystem

B.

Stream-aligned, functional requirements, product domain, and technical

C.

Functional requirements, platform, enabling, and technical

D.

Functional requirements, product domain, technical, and complicated subsystem

Full Access
Question # 47

Which statement describes a cadence-based PI Planning event?

A.

As many team members as possible should attend remotely to reduce travel costs

B.

It is very important and should be postponed until all participants can attend

C.

It is not a required event but tasks move forward at higher velocity when the meeting occurs

D.

It is an all-hands, two-day event with the goal to create alignment

Full Access
Question # 48

Who is responsible for managing the Portfolio Kanban?

A.

Product Management

B.

Release Train Engineer

C.

Solution Management

D.

Lean Portfolio Management

Full Access
Question # 49

Which SAFe Core Value includes "use common terminology" and "understand your customer"?

A.

Alignment

B.

Relentless Improvement

C.

Transparency

D.

Respect for People

Full Access
Question # 50

What is the role of the System Architect/Engineer?

A.

To manage dependencies

B.

To implement continuous improvement methods

C.

To guide the teams and support the Architectural Runway

D.

To define the design for the system

Full Access
Question # 51

What is one dimension of the Team and Technical Agility Core Competency?

A.

Relentless Improvement

B.

Innovation Culture

C.

Built in Quality

D.

Leading by Example

Full Access
Question # 52

Volume, complexity, knowledge, and uncertainty are all qualities of what?

A.

Weighted shortest job first (WSJF)

B.

Cost of Delay

C.

Story points

D.

Risks

Full Access
Question # 53

Iteration planning, Iteration review, and backlog refinement are examples of which type of event

A.

PI event

B.

Team event

C.

Sync event

D.

Program event

Full Access
Question # 54

What is the product vision?

A.

A method for aligning to the product direction

B.

The user stories required to meet customer needs

C.

A set of prioritized Features

D.

An explanation of the architectural runway needed to deliver products to the customer

Full Access
Question # 55

What is the role of the Scrum Master?

A.

To coordinate Portfolio Epics through the Portfolio Kanban system

B.

To act as a servant leader who helps teams self-organize, self-manage, and deliver using ^ effective Agile practices

C.

To be a stakeholder who has the primary business and technical responsibility for fitness for u use

D.

To facilitate Agile Release Train processes and Solution Train execution

Full Access
Question # 56

What best supports Innovation in the SAFe House of Lean?

A.

Visualizing work

B.

Optimizing the whole

C.

Built-in quality

D.

Fast learning cycles

Full Access
Question # 57

What is the formula to calculate flow efficiency?

A.

Total wait time / Flow time [Total wait time divided by Flow time]

B.

Total active time / Flow time [Total active time divided by Flow time]

C.

Total wait time + Flow time [Total wait time plus Flow time]

D.

Total active time + Flow time [Total active time plus Flow time]

Full Access
Question # 58

What brings structure to analysis and decision making around Epics?

A.

Portfolio Vision

B.

Portfolio Backlog

C.

Portfolio Canvas

D.

Portfolio Kanban

Full Access
Question # 59

Which of the following types of work is found within the Agile Team Backlog?

A.

Features

B.

Capabilities

C.

User Stories

D.

Epics

Full Access
Question # 60

Which of the following aspects of the continuous delivery pipeline focuses on getting to production early for verification?

A.

Continuous Exploration

B.

Continuous Integration

C.

Release on Demand

D.

Continuous Deployment

Full Access
Question # 61

Which statement describes a cross-functional team?

A.

Each team can deliver Features across multiple domains

B.

Each team member can do all the activities to define, build, and test a Solution

C.

Each team member can define and build, with a System Team testing the Solution

D.

Each team member can define, build, and test a component or Feature

Full Access
Question # 62

What is the role of the Product Owner?

A.

To ensure quality by testing the Solution

B.

To prioritize the Program Backlog

C.

Estimate the Stories in the Product Backlog

D.

To represent the Customer to the Agile Team

Full Access
Question # 63

Which of the following types of information is shown in a cumulative flow diagram?

A.

Team velocity

B.

Costs of producing artifacts

C.

Work that is in process across the whole team

D.

Time to complete a Feature by the rollup of Stories

Full Access
Question # 64

Which statement is true about Iteration goals?

A.

They verify that teams are working at their full capacity

B.

They align the team to a common Vision of work in the Iteration

C.

They are used to track scope changes over time

D.

They are used to measure business value achieved for each Iteration

Full Access
Question # 65

Deploy, verify, monitor, & respond are all activities of what?

A.

Continuous Integration

B.

Continuous Exploration

C.

Continuous Deployment

D.

Release on Demand

Full Access
Question # 66

A SAFe Portfolio is a collection of what?

A.

Development Value Streams

B.

Functional teams

C.

Solutions

D.

Business units

Full Access
Question # 67

What is "precisely specify value by product" central to?

A.

SAFe Principles

B.

Agile Manifesto

C.

SAFe Core Values

D.

Lean Thinking

Full Access
Question # 68

What is found on an ART planning board?

A.

Epics

B.

Features

C.

User stories

D.

Tasks

Full Access
Question # 69

What is the goal of the PI Planning event?

A.

Build a release Roadmap

B.

Achieve alignment on what needs to and can be built

C.

Create a plan for the upcoming PI showing how Stories map to Iterations

D.

Identify the risks in the upcoming Features using a ROAMing exercise

Full Access
Question # 70

What is one way Lean-Agile leaders lead by example?

A.

By using the SAFe Implementation Roadmap to script the path for change

B.

By mastering the Seven Core Competencies of the Lean Enterprise

C.

By applying empathic design and focusing on Customer Centricity

D.

By modeling SAFe's Lean-Agile Mindset, values, principles, and practices

Full Access
Question # 71

Which responsibility belongs to the Product Owner in the team?

A.

To foster normalized estimating within the team

B.

To facilitate team meetings and drive Agile behavior

C.

To foster adoption of Agile technical practices

D.

To sequence backlog items to program priorities, events, and dependencies

Full Access
Question # 72

Which of the following design-thinking techniques helps break down Features while considering the end-to-end user flow?

A.

Story Mapping

B.

Personas

C.

Gemba walks

D.

Market research

Full Access
Question # 73

Which statement is a principle of the Agile Manifesto?

A.

Measure everything

B.

Visualize and limit WIP, reduce batch sizes, and manage queue lengths

C.

Simplicity "the art of maximizing the amount of work not done" is essential

D.

Respect for people and culture

Full Access
Question # 74

Which practices are demonstrated during the Inspect and Adapt event?

A.

New start, job sequence, funnel, and enable

B.

Reflect, problem solve, and identify improvement actions

C.

Move forward, analyze future Stories, integrate, and iterate

D.

Forward focus, develop, cross-domain plan, and expedite execution

Full Access
Question # 75

Which statement is true about batch size?

A.

Large batch sizes ensure time for built-in quality

B.

The handoff batch should be made as large as possible

C.

When Stories are broken into tasks, it means there are small batch sizes

D.

Large batch sizes increase variability

Full Access
Question # 76

What is the purpose of Customer Centricity?

A.

To design custom-built Customer Solutions

B.

To interpret market rhythms

C.

To build small, partial systems just in time

D.

To understand the Customer's needs

Full Access
Question # 77

What is one element teams present during the draft plan review?

A.

Iteration goals

B.

Planned business value

C.

Milestones

D.

ART PI risks

Full Access
Question # 78

What are two behaviors of an effective Scrum Master? (Choose two.)You have reached the max number of allowed answers

A.

Facilitate the PI Planning session

B.

To act as a servant leader and exhibit Lean-Agile Leadership

C.

To guarantee no changes are made to the scope during an Iteration

D.

To facilitate the team's progress toward the Iteration goals

E.

Facilitate more than two teams

Full Access
Question # 79

An Agile Team has which two characteristics? (Choose two.)

A.

A stand-alone unit of individuals who do not require input from other teams to complete their tasks

B.

A group of dedicated individuals who are empowered, self-organizing, self-managing, and deliver value

C.

A small group of typically 5 - 11 dedicated individuals who have the skills necessary to define, build, test, and deploy increments of value

D.

A large group of individuals who all work together to create value for the client

E.

A group of dedicated individuals that work in phase-gate steps to complete their PI Objectives

Full Access
Question # 80

Which of the Lean Thinking principles includes the activities from recognizing an opportunity through release and validation?

A.

Identify the Value Stream for each product

B.

Make value flow without interruptions

C.

Pursue perfection

D.

Precisely specify value by product

Full Access