Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Cost Professional (CCP) Exam

Last Update 9 hours ago Total Questions : 189

The Certified Cost Professional (CCP) Exam content is now fully updated, with all current exam questions added 9 hours ago. Deciding to include CCP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CCP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Cost Professional (CCP) Exam practice test comfortably within the allotted time.

Question # 21

Which of the following is NOT an advantage specific to a cost reimbursable contract?

A.

Evaluation of proposals are much simpler

B.

Provides flexibility in dealing with changes

C.

An early start can be made

D.

Owner controls all aspects of the work

Question # 22

Which of the following best describes the concept of total cost management:

A.

A method of quantifying construction damages where the total job costs are subtracted from the original bid or estimate to determine the total cost amount for a claim

B.

The practices and processes utilized to manage the total life cycle cost investment in a portfolio of strategic assets

C.

A job cost system for ensuring all aspects of a particular manufacturing process are accumulated completely

D.

An integrating process that maps the fields of practice of cost engineering without linking it to project management, resource management, or accounting

Question # 23

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

What is the median unit cost?

A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Question # 24

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Depreciation (in the United States) is calculated in accordance with which of the following?

A.

Modified Accelerated Cost Recovery System (MACRS)

B.

The Federal IRS Reform Act (FIRSRA)

C.

Generally Accepted Accounting Practices (GAAP)

D.

Accelerated Cost Recovery System (ACRS)

Question # 25

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Profits that could not be formally recognized during a specific financial accounting period because the goods and services did not satisfy all the customer's requirements are:

A.

Marginal profits

B.

Lost profits

C.

Incurred profits

D.

Postponed profits

Question # 26

What relationship more accurately defines a situation model of parallel activities that require a partial start of one activity?

A.

Start to start

B.

Star to finish

C.

Finish to start

D.

Finish to finish

Question # 27

A contract clause that provides the owner with the right to terminate the contract irrespective of the general contractor's liability is:

A.

Termination of contract - convenience

B.

Termination of contract - default

C.

Substantial completion

D.

Breach of contract

Question # 28

Which of the following is a disadvantage to using target contract as a method of contracting?

A.

Encourages economic and speedy completion

B.

No opportunity to competitively bid the targets

C.

Almost immediate start on the work, even without scope definition

D.

Flexibility in controlling the work

Question # 29

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Question # 30

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Which statement best describes the type of information available for a design phase estimate?

A.

Home office detail, specific vendor quotes, preliminary quantities with labor and material factors applied

B.

Square footage of buildings, factored indirects, types of rides and exhibits identified, utility requirements, conceptual layouts

C.

Detailed construction drawings, quantity takeoffs, detailed labor hours and material costs applied, quotes from all major subcontractors

D.

Utility requirements, detailed building plans and (- specifications, types of rides and exhibits identified, all vendor quotes or estimates received from subcontractors

Go to page: