Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Planning & Scheduling Professional (PSP) Exam

Last Update 5 hours ago Total Questions : 216

The Planning & Scheduling Professional (PSP) Exam content is now fully updated, with all current exam questions added 5 hours ago. Deciding to include PSP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our PSP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these PSP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Planning & Scheduling Professional (PSP) Exam practice test comfortably within the allotted time.

Question # 1

What is the free fl oat for Activity F?

A.

3 months.

B.

0 months.

C.

1 months.

D.

2 month.

Question # 2

What method offers the best chance of the schedule being used effectively to implement the project in the field?

A.

Issue detailed schedule updates as frequently as possible.

B.

Obtain consent and agreement to the schedule from the key project personnel.

C.

Include detailed and stringent set of scheduling specifications in the contract.

D.

Allow large time contingencies on milestones and completion deadlines.

Question # 3

Using the " crashed " schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

Question # 4

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Question # 5

What is a critical path method schedule?

A.

List of work to be accomplished by responsible party and when it is to be accomplished

B.

The timeline of the riskiest work

C.

A graphical means of showing the important work

D.

A network diagram of logically interconnected activities

Question # 6

Which of the following will always describe the critical path? The path with

A.

The longest duration through the network.

B.

Zero float.

C.

Negative float.

D.

The shortest duration and negative float.

Question # 7

What activities are concurrent to Activity 2001 in the " normal " schedule?

A.

7001.

B.

1001.

C.

1000.

D.

2003 .

Question # 8

Why does activity 1001 have two successor activities?

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Question # 9

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

Question # 10

What does the heavy, vertical line at " X " represent?

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Go to page: