Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Cost Professional (CCP) Exam

Last Update 9 hours ago Total Questions : 189

The Certified Cost Professional (CCP) Exam content is now fully updated, with all current exam questions added 9 hours ago. Deciding to include CCP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CCP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Cost Professional (CCP) Exam practice test comfortably within the allotted time.

Question # 51

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The recognition of loss of value of a natural resource used in the production process is referred to as:

A.

Capital reduction

B.

Net loss

C.

Depreciation

D.

Depletion

Question # 52

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following is NOT an advantage of the critical path method:

A.

The ability to determine cost overruns of critical path activities

B.

The ability to identify activities that cannot have their schedules slip if the desired project end date is to be achieved

C.

Reveals activities that additional resources need to be dedicated toward

D.

The ability to show slippage in the progress of key activities

Question # 53

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses

What is the amount of capital recovery with salvage?

A.

$11,499.00

B.

$4,124.00

C.

$9,876.00

D.

$10,765.00

Question # 54

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

How many years will it take to earn $400 in interest on $800 at 4% compounded annually?

A.

10 years

B.

11 years

C.

12 years

D.

13 years

Question # 55

A work breakdown structure (WBS) is developed because:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Question # 56

When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?

A.

For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.

B.

For changes in construction cost 'or varied works carried out beyond the original dale of completion

C.

In no situation

D.

For changes in The cost of resources beyond the control of either party

Go to page: