Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Certified Cost Professional (CCP) Exam

Last Update 9 hours ago Total Questions : 189

The Certified Cost Professional (CCP) Exam content is now fully updated, with all current exam questions added 9 hours ago. Deciding to include CCP practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our CCP exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these CCP sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Certified Cost Professional (CCP) Exam practice test comfortably within the allotted time.

Question # 41

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

A.

$46.13

B.

$47.63

C.

$48.35

D.

$48.09

Question # 42

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The main financial objective of many enterprises is:

A.

To maximize the total long-term economic return

B.

Subject to a well-conceived quality control plan

C.

To balance opportunities and risks

D.

Dependent on the backlog projects and the availability of resources

Question # 43

When the project plan is implemented:

A.

Activities are carefully monitored and controlled against the baseline

B.

The basis for payment applications is formalized

C.

The forward and backward pass is identified

D.

CPI and SPI can be calculated and reported

Question # 44

You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:

unable to be calculated from the information given

A.

< 1

B.

=1

C.

=1

D.

> 1

Question # 45

A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?

A.

3.0 cubic yards

B.

2.0 cubic yards

C.

3.5 cubic yards

D.

2.5 cubic yards

Question # 46

What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?

A.

Liability insurance

B.

Performance bond

C.

Bid bond

D.

Surety bond

Question # 47

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?

A.

1

B.

1.04

C.

0.89

D.

0.96

Question # 48

An owner advertised his villa for sale. An investor worked out an estimate on the basis mat the villa could be rented out for $1000 per month. Maintenance charges and other taxes are estimated to be $1,500 per year. The tenant has to pay all utility charges. The investor thinks that he can sell this villa for S100.000 alter 6 years. Assuming that the minimum acceptable rate of return is 12%. answer the following question.

The villa could be recommended for purchase at all of the below-mentioned prices except:

A.

$94,500

B.

$92.800

C.

$90,5000

D.

$93,500

Question # 49

The four steps to writing are:

A.

Introduction, paragraph, conclusion, works cited

B.

Start, write, complete, revise

C.

Abstract, body conclusion, bibliography

D.

Plan, write, cool, revise

Question # 50

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of SO 45 cents is estimated.

The monthly fixed costs are: Rant-$1,600

Wages - S4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

A.

$33,750

B.

$375,00

C.

$7,500

Go to page: