You'll find that our EX0-008 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these EX0-008 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Agile Scrum Foundation practice test comfortably within the allotted time.

Question # 11

Who is the owner of a Sprint Backlog Item during the Sprint Planning meeting?

A.

The entire team owns all Sprint Backlog Items.

B.

The Product Owner owns all Sprint Backlog Items.

C.

The team member working on the item owns that item.

Question # 12

During the release planning meeting, it is difficult to agree on priorities.

Sales want to implement some new features to catch up with the competitors.

Marketing want to work on a mobile interface that can prove to be a competitive differentiator.

Customer support want better logging and auditing capabilities to improve maintainability.

What should be done to set the priorities?

A.

Approach Senior Management and ask for priorities.

B.

Survey the existing customers and prioritize according to their views.

C.

The Product Owner will set the priorities.

Question # 13

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

A.

Keeping high priority features at the top of the Product Backlog.

B.

Not allowing changes to the Product Backlog once the Sprint begins.

C.

Supporting the team's decisions and resolving the team's issues.

Question # 14

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.

Which statement is true regarding this scenario?

A.

Points are assigned by the Scrum Master, not by the team.

B.

Points are assigned for the overall Story, not for parts of the Story.

C.

Points are never estimated, but always determined beforehand.

D.

The team forgets to ask the Product Owner about the estimate.

Question # 15

When is a Sprint complete?

A.

When all of the Product Backlog items are completed.

B.

When all the tasks in the Sprint Backlog are completed.

C.

When the Sprint defined time box ends.

Question # 16

What is the objective of the Scrum-of-Scrums meeting?

A.

To inform management about the progress of the project.

B.

Bring together all team members of all teams.

C.

Coordinate the work of multiple Scrum teams.

D.

Kick-off an international Scrum project.

Question # 17

What is the best way to split up teams on a large project which is implemented using Scrum?

A.

Group by domain expertise.

B.

Group by features being developed,

C.

Group by specialty of the team members.