You'll find that our IIBA-AAC exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these IIBA-AAC sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any IIBA Agile Analysis Certification practice test comfortably within the allotted time.

Question # 41

When decomposing stories, the concept of “breadth before depth” signifies progressively breaking down:

A.

Estimates and resources required to accomplish the story

B.

Backlog items to the lowest level of detail upfront

C.

Business goals into user stories representing smaller increments of value

D.

Tests to align with usable functionality delivered through each story

Question # 42

The team is debating how they will gather stakeholder input for a new initiative. Which of the following proposals is most closely aligned with the agile mindset?

A.

Develop a simple interview for team members to use, and interview stakeholders directly.

B.

Buy a third party research firm report about people similar to the stakeholders.

C.

Create a broad and deep set of user personas that describe each stakeholder group.

D.

Send out one detailed survey to all the stakeholders.

Question # 43

In situations where learning is frequent and fast-paced, and the product owner is reacting to the new information, the prioritization of solution components should be expected to:

A.

Be unaffected

B.

Remain stable

C.

Alter intermittently

D.

Change frequently

Question # 44

While establishing the components to include in the initiative, the team realizes they need to use a technique to help them avoid wasted work. What can help them achieve this?

A.

Behaviour Driven Development

B.

Waste Management

C.

Kano Analysis

D.

Retrospective

Question # 45

Work at the Strategy Horizon is completed to establish a portfolio management approach and decision framework for the organization. This is considered a component of the following BA Task:

A.

Plan Business Analysis Information Management

B.

Plan Stakeholder Collaboration

C.

Plan Business Analysis Governance

D.

Plan Requirement Approval Approach

Question # 46

One agile principle the team adopts is to consider the capabilities of the technology, skills of the team, and time to deliver the solution. The goal of this is:

A.

Understanding What is Doable

B.

Stimulating collaboration among stakeholders

C.

Deciding the architecture to be implemented

D.

Communicating the architecture design

Question # 47

The team realizes that the agile business analysis principle of stimulate collaboration and continuous improvements aligns with the BACCM core concept of:

A.

Context

B.

Stakeholder

C.

Needs

D.

Solution

Question # 48

The delivery team is discussing what to include in a user story. They determine that a user story should identify in clear, concise terms, the following three things:

A.

Customer, feature, value

B.

Situation, capability, frequency

C.

Who, how, when

D.

Actor, function, constraint

Question # 49

A team member has written a full user guide about a feature that has not yet been developed. Shortly before delivery is to start, the feature is dropped. What did the team member forget to value highly?

A.

Following the plan

B.

Detailed processes

C.

Fixed iterations

D.

Working solutions

Question # 50

A team member is examining an initiative on which the team will begin work in roughly 6 months. The team member writes all the stories and diagrams necessary for the initiative. This is an example of:

A.

Creating waste

B.

Initiative acceleration

C.

Paper prototyping

D.

Analyst engagement