Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Commercial Contracting

Last Update 6 hours ago Total Questions : 233

The Commercial Contracting content is now fully updated, with all current exam questions added 6 hours ago. Deciding to include L4M3 practice exam questions in your study plan goes far beyond basic test preparation.

You'll find that our L4M3 exam questions frequently feature detailed scenarios and practical problem-solving exercises that directly mirror industry challenges. Engaging with these L4M3 sample sets allows you to effectively manage your time and pace yourself, giving you the ability to finish any Commercial Contracting practice test comfortably within the allotted time.

Question # 21

Maximum Score: 1

Which of the following would be considered as advantages of an industry model form contract?

    It provides greater flexibility for negotiation

    It reduces the cost of contract development

    It is usually designed to be fair to both parties

    It removes the need for the buyer to understand it

A.

1 and 2 only

B.

2 and 3 only

C.

1 and 3 only

D.

2 and 4 only

Question # 22

Buyer D agrees a contract with Supplier C which includes the words ' to be agreed ' in relation to the date for delivery of the goods. At the time of the contract, Buyer D is aware that the goods take two days to produce and one day to deliver. Buyer D contacts the supplier one week later, requesting the goods be delivered the following day. Supplier C is unable to deliver the next day but rather delivers the goods three days later. Is it the case that Buyer D can legally refuse to pay for the goods because Supplier C is in breach of contract?

A.

Yes, because the delivery date is an express term within the contract

B.

Yes, because the goods should have been delivered within three days

C.

No, because the goods were delivered within a reasonable time

D.

No, because there is a contract in place and the delivery date does not matter

Question # 23

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK ' s failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Question # 24

John is a new procurement manager who has recently joined Smiths Facilities Management Ltd. The company provides maintenance services through the utilisation of subcontractors. It is experiencing a number of issues with its supply chain which has resulted in customer complaints, and John would like to introduce service level agreements (SLAs) to some of its key providers. Which of the following should be included?

    How often the service will be provided

    The procedures to be followed to resolve disputes

    The qualifications needed by staff providing the service

    The stock maintained by the subcontractor

A.

1, 3 and 4 only

B.

2, 3 and 4 only

C.

1, 2 and 4 only

D.

1, 2 and 3 only

Question # 25

Which of the following are reasons why a buying organisation adopts a model contract?

1. Extremely advantageous terms for buyer

2. Correct legal terminology

3. Supplier cannot make variation to the model form

4. Specific to industry

A.

1 and 2 only

B.

2 and 4 only

C.

2 and 3 only

D.

1 and 4 only

Question # 26

Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:

Short turnaround times

A.

Quick implementation

B.

Driving forward planning culture

C.

Lower administration costs

D.

Reducing risks of bribery and corruption

Question # 27

Company A sends a purchase order complete with a set of conditions of contract for the provision of professional services to Company B. Company B responds with an invoice complete with a set of its own conditions of contract. Company A pays the invoice. Whichconditions of contract take legal precedence?

A.

Company A ' s

B.

Company B ' s

C.

Neither Company A ' s nor Company B ' s

D.

Both Company A ' s and Company B ' s

Question # 28

The cost in cost reimbursable contract is...?

A.

Actual cost

B.

Variable cost

C.

Fixed cost

D.

Profit

Question # 29

Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:

A.

Short turnaround times

B.

Quick implementation

C.

Driving forward planning culture

D.

Lower administration costs

E.

Reducing risks of bribery and corruption

Question # 30

Maximum Score 1

Adornical Toys Ltd have recently declared their commitment to international labour standards. Karim is sourcing a supplier for a new range of wooden toys and is keen to ensure that the organisation ' s corporate objectives are met. Which of the following approaches could he include as part of his specification requirements to achieve this labour outcome?

A.

Certification to an ethical trading initiative

B.

Use ecologically certified raw materials

C.

Accreditation to waste reduction schemes

D.

Formally measure their carbon footprint

Go to page: