Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: buysanta

Exact2Pass Menu

Question # 4

You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Full Access
Question # 5

You need to configure the bicycles’ production resource.

Which option should you use?

A.

Exclusive capacity set to yes and enter a Batch capacity.

B.

Exclusive capacity set to no and infinite capacity.

C.

Exclusive capacity set to yes and infinite capacity.

D.

Exclusive capacity set to no and enter a Batch capacity.

Full Access
Question # 6

You need to resolve the production manager issue.

How should you configure manufacturing execution? To answer, select the appropriate option in the answer area.

NOTE:Each correct selection is worth one point.

Full Access
Question # 7

You need to configure lot number control for inventory. Which option should you use?

A.

Physical inventory

B.

Blank receipt allowed

C.

Blank issue allowed

D.

Primary socking

Full Access
Question # 8

You need to plan scheduling for Customer1’s order of unscented solution.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

A.

Schedule production based on the availability of raw material.

B.

Split and plan operations in detail for each of the resources.

C.

Schedule productions based on the capacity of the resources.

D.

Run master planning with a specific time fence.

E.

Plan scheduling of the production at the resource group level.

Full Access
Question # 9

You need to resolve the issue for UserG.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 10

A company uses Dynamics 365 Supply Cham Management.

Several production orders are in the started status.

An issue with equipment causes a rollback in the production status tor some of the orders.

Some orders must be reset once the equipment is repaired, based on which products were being manufactured.

You need to reset the production orders based on the requirements

Which status should you use for each requirement? To answer, drag the appropriate statuses to the correct requirements. Each status may be used once, more than once, or not at all.

You may need to drag the split bar between panes or scroll to view content.

Full Access
Question # 11

You need to configure the requirements for metal fabrication equipment maintenance. What must you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 12

You need to enable the features and configuration keys for the firepits.

Which two features should you enable? Each answer presents part of the solution.

NOTE: Each correct selection is worth one point

A.

Engineering attributes

B.

Change management for process manufacturing

C.

Engineering product variants

D.

Engineering change management

E.

Production floor execution management

Full Access
Question # 13

You need to meet the needs for the large teakwood furniture order.

What must you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 14

You need to meet the substitution requirements for User4 and User5.

What must you configure? To answer, drag the appropriate configurations to the correct substitution requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Full Access
Question # 15

You need to determine the sales price for a new limited-edition bicycle for the summer season.

What should you do?

A.

Run inventory close for the BOM items for the limited-edition bicycle.

B.

Create the production order for the limited-edition bicycle and click estimate.

C.

Run the category price rules for the limited-edition bicycle using a cost-plus calculation.

D.

Run the pricing simulator for the limited-edition bicycle for a quantity of one.

Full Access
Question # 16

You need to resolve the issue for UserF.

What should you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 17

You need to configure the system to meet the requirements.

What should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 18

A manufacturer is implementing Dynamics 365 Supply Chain Management with warehouse management processes (WMS).

Warehouse workers use hand-held devices to pick and stage batch-tracked products for production. The warehouse manager requires that products are removed from on-hand inventory and consumed when they are picked and staged for production.

You need to remove the products from on-hand inventory.

What should you configure?

A.

mobile device menu item, start production order

B.

flushing principle, available al location

C.

flushing principle, start

D.

manufacturing execution, job card device

Full Access
Question # 19

You are a manufacturing consultant helping a client test out different bill of material (BOM) and route consumption options when starting production orders. Material and labor consumption are to be completed before Report as finish.

You are running a production order with BOM lines that have a Flushing principle set to Start. The Automatic Route Consumption Runtime has been set to Yes.

You have set up the default Start user options for all production orders as shown in the exhibit below.

Full Access
Question # 20

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.

The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor ingredient A is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.

You need to ensure that the system is set up to support the manufacturing process.

Solution: Create a dimension-based product master with variants and use the trade agreements to specify the different pricing.

Does the solution meet the goal?

A.

Yes

B.

No

Full Access
Question # 21

You need to create the constraint for the ML seat selection.

Which expression constraint should you use?

A.

Implies[Trim==Legend,Seat==ML]

B.

Seat!=ML

C.

[Trim==Legend|Seat==ML]

D.

Implies[Seat==ML,Trim==Legend]

Full Access
Question # 22

You need to configure system attributes.

Which attribute types should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Full Access
Question # 23

You need to set up the metal production route and BOM.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE:Each correct selection is worth one point.

A.

Set the operation route type as Standard.

B.

Set the input warehouse on the resource to the vendor warehouse.

C.

Set the operation route type as Vendor.

D.

Set all BOM lines warehouse to the production warehouse.

E.

Set all the BOM lines to resource consumption.

Full Access
Question # 24

You need to set up the configuration model to price the motorcycles correctly. What should you do?

A.

Set Order type in price model to Sales Order and Pricing method in Version to Attribute based

B.

Set Order type in price model to Sales Order and Pricing method in Version to Cost based.

C.

Set Order type in price model to Sales Quotation and Pricing method in Version to Attribute based.

D.

Set Order type in price model to Sales Quotation and Pricing method in Version to Cost based

Full Access